Irish Railway Record Society

Home Operations 151 Rolling Stock 151 Stations 151 Track 151 NIR News 151

STATIONS

HEUSTON RE-DEVELOPMENT

Progress was good on the installation of track and signalling and all commissioning dates were achieved on time. Phase 3, stage 3.1, was commissioned on Sunday 23 February. This brought back into use platforms 1 to 4 and two running lines south of the Valeting Plant. Along with previously commissioned platforms 5 to 8 and platform 10, this greatly enhanced operational flexibility.

From 23 February, the line formerly known as the Down Main line and situated on the north side of the Valeting Plant was taken out of service at the west end to became a stub ended siding. This left a single-track arrival and departure line, the Up Main Line (north of the Valeting Plant), to access Platforms 6 to 8. This was a temporary arrangement until track in the vicinity of the west end of the Valeting Plant was completed in April.

Platform 1 is 93 metres long from signal to buffer stop, while platforms 2, 3, 4 and 5 are 280 metres, 6, 7 and 8 are 255 metres and platform 10 is 212 metres. All have three aspect starting signals, with platforms 1 to 8 signals numbered HN311 to HN318 respectively. ‘OFF’ indicators are provided at the departure ends of platforms 2, 7 and 8. These indicate to platform staff unable to see the starting signal that it has been cleared and the train depart.

New sidings on the south side of the Relief Line in the area of the former ‘old’ Guinness/St. John’s Road sidings, are designated the Run-out siding, Loop siding, Maintenance of Way sidings, and Machine siding. The former catch points leading into these sidings have been replaced by motorised points normally set for the Run-out sidings. The loop siding has connections at both end to the Relief Line and is 105-metres long.

A total of twenty new signals and twelve new sets of points were commissioned as part of Phase 3, stage 3.1 in February. Many of the points are ‘Automatically Normalised’ i.e. if they are in the Reverse position after the passage of a train, they will automatically move to the Normal position. The Continuous Automatic Warning System (CAWS), which is based on pulse codes transmitted through the running rails that repeat the signal aspect in the driver’s cab, was commissioned over part of the new layout when the track was brought into use, with the remainder being commissioned on 28 February.

The extended concourse at the buffer stop end of platforms 2 to 5 was brought into use. Platforms 1 to 4 have been re-surfaced with cobble-lock type brick. Two new large departure indicator boards have been provided, one at the main concourse and the other at the concourse for platforms 6, 7 and 8. Located throughout the station are many smaller TV screen size monitors that show arrivals. These are also located in all retail outlets. Each platform has an electronic information board at its entrance that normally shows train destination details. There are ticket vending machines for the purchase of mainline tickets in the main concourse.

On late evening of Friday 21 and during Saturday 22 February, there were various cancellations and amendments to mainline and Kildare services to allow commissioning take place. These included combining some Westport and Galway departures, with other trains starting and terminating at Newbridge and Tullamore. There were no cancellations on the Sunday.

The newly laid and signalled track was handed over on time at 14.00 on Sunday 23 February following a period of testing using locomotives 154 and 170. The first arrival via the new track on the south side of the Valeting plant was the 14.00 Cork-Dublin (229 + 8 Mk III + EGV) into platform 5 at 16.50. The flexibility of the new layout was demonstrated by the fact that this train was only two minutes behind the 13.50 Galway-Dublin (071 + 4 Mk IId + EGV), which arrived into platform 8 via the north side of the Valeting plant. The first departure using the new track was the 19.05 Dublin-Tralee, which departed from platform 5 at 19.23. This delay was due to the late arrival, at 18.59, of the incoming train, the 13.45 Tralee-Dublin, which was unrelated to the work at Heuston. The first arrival into the ‘old’ train shed was the 17.20 Limerick-Dublin, a 4-car 2600-class, which arrived six minutes early at 19.45.

From 23 February, access to the Valeting Plant, the Wash Road and a new siding between them, known as the Holding Road, was only available from platforms 4 and 5. No access was provided to the Valeting Plant from the west end. This was restored on Sunday 27 April with the commissioning of the remaining points and signals for the entire project.

Finishing work includes excavating, re-laying and concreting the track on platforms 4 and 5 between April and July 2003 and construction of a secondary concourse to service platforms 6 to 8, scheduled from July 2003 to February 2004. Platform 5 was taken out of service on 6 April, followed by Platform 4 on 27 April.

Connolly   The buffer stops at platforms 3 and 4 were re-located towards the concourse on 8 February by 20 and 15 metres respectively. They had been temporarily moved northwards to allow the concourse be extended several years ago. Platform 3 is now 205 metres from the top of the ramp to the buffer stop, while platform 4 is 290 metres long.

Platform Lengthening   The Minister for Transport told the Dáil that he had approved expenditure by IÉ for a feasibility study in the Border-Midlands-Western Region to examine all railway platforms. He said that funds had been allocated to raise and lengthen platforms at Mullingar, Longford, Ballyhaunis, Castlebar, Westport and Clara. He also said that Kilcock station platform would be extended to accommodate 8-car trains in 2003. Enfield down platform will also be extended in 2003.

Tidy Stations   Tullamore was named as the overall winner of the 2002 Tidy Stations competition. It was Tullamore's first win and it also won the Best InterCity Station award. Dundalk retained the Heritage award, as well as the Best Major Station award. Skerries was named Best Suburban Halt for the seventh year in a row. Castlebar was the best InterCity Halt for the sixth year in a row. Other winners were Killiney as Best DART Halt, Hazelhatch as Best Unmanned Station, Malahide for Community Involvement, Mallow for Best Staff Effort and Rathdrum for Innovation.

 

Home
Copyright © 2003 by Irish Railway Record Society Ltd.
Revised: January 07, 2004 .