
Irish Railway Record
Society
Achill
Branch Communications
TF WALL
his
branch was promoted in the early 1890’s in two sections. The Westport –
Mallaranny (the spelling varied) portion was built under the auspices of the
MGWR and the Board of Works financed the extension to Achill. The contractor,
Robert Worthington, constructed both sections of the 26½ mile line, opening to
TMallaranny on Wednesday 1 August 1894 and throughout to Achill on Monday 13 May
1895.
In
February 1866, a telegraph had been run by the British & Irish Magnetic
Telegraph Company from Castlebar to Westport for the MGWR, at the time the
railway was opened. In 1873, a wire for the public telegraph service was erected
by the Post Office (PO) from Westport to Newport and this was extended to Achill
in early 1891. Also in 1873, the existing single-needle telegraph instruments on
the main line circuit were substituted by Morse sounders. The Westport
instrument was moved from the Parcels Office to the Ladies’ Waiting Room on 27
April 1876 at a cost of £1-9-1. Mallaranny was looped into the Achill circuit
in March 1891.
The
first contact between the PO and the new railway occurred in 1891, when the
contractor’s representative, Mr Douglas Gray, telegraphed the PO on 23 March
to have two poles moved near Newport. Mr A Raddin, the PO Engineer replied on 3
April:
“I
beg to inform you that the poles were at once removed. An expense of 9/3 has
been incurred by the lineman in doing so. Will you kindly inform me how the
amount is to be recovered”.
The
money was duly forwarded by Mr Gray and Mr Raddin sent it on to his
Superintending Engineer, Mr W Louth. The latter’s reply reveals the procedure
to be followed in dealing with contractors.
“In
future when a work is being carried out by a railway or other company under an
Act of Parliament and you are called on by the contractor or engineer to make
any alteration to the Department’s wires, let him give you a letter
undertaking to pay the cost and then refer it to me for instruction. Of course,
where time presses, you should wire me. But in no case receive the money, as
that should be done by the Accountant’s Branch. What is the exact title of the
Railway in this case? I will have to supply it in getting the amount brought to
account”.
Mr
Raddin replied on the 10 April with an explanation of the circumstances of the
case:
“Your
instructions noted and shall have careful attention. In this case, the matter
was urgent; the public road was diverted and at the junction with new and old
portions of road, two of our poles were thus placed in centre of new road and
being so dangerous, I thought it best to act at once in moving them. It will
also be seen that I only asked Mr Gray for instructions as to who would pay the
cost, the reply I got was the remittance. The title of the railway is Westport
– Mulranny Railway”.
The
contractor again asked for a pole to be moved in July and this was done at a
cost of 6/7½. In sending his estimate for the job to Mr Louth, (after the work
was completed), Mr Raddin explained the low cost;
“The
Contractor supplied the lineman with labour assistance. The lineman also walked
from Westport to Barley Hill. There is therefore no conveyance charge”.
The
contractor sought further PO co-operation in moving poles, as Mr R Worthington
mentioned in a letter of 16 March 1892 to the PO Secretary:
“On
the Westport & Mulraney Railway there are 5 telegraph posts which require to
be shifted; one at Barley Hill just beyond Westport, two at a place called
Kilbride about a mile and a half on this side of Newport, one at a point where
the railway crossed the Achill road a quarter of a mile beyond Newport and
another a quarter of a mile further on. Will you be kind enough to have these
posts shifted at once. I shall of course pay the cost, on your furnishing me
with the bill. If you call at my office at Newport, the posts in question will
be pointed out to you”.
The
work was done by 24 March, except for one pole for which the contractor’s
Travelling Ganger or Inspector, Mr Rice, requested that it not be shifted. The
contractor supplied the labour and the only charge (for the lineman’s time and
travelling expenses) was £1-12-1. The pole omitted was moved on 13 June, Mr B R
Le Fanu of the contractor’s staff undertaking to pay the charge of 12/5½.
Further poles were moved in July, at the request of Mr John Fisher, and in
December, “as we are now laying our rails and the pole will be in our way”.
On the
main line, block working was established in response to the Regulation of
Railways Act 1889. This involved running a new wire from Ballyhaunis to Westport
on the existing poles and this was accomplished by July 1892. Fitting of the
Webb & Thompson ETS instruments in the sections Castlebar – Westport –
Westport Quay was completed on 7 January 1893, from which date the annual
maintenance charge of £4 per instrument commenced.
On 24
March 1893, Mr G W Green, the MGWR Secretary, wrote to the PO Secretary
regarding wires on the branch:
“Westport
& Mallaranny Railway. The above railway now in course of construction is
expected to be completed about August next. We require the telegraph to be
erected in the meantime and I shall be obliged by your sending me an estimate
for putting up two wires from Westport to Mallaranny – one for the ETS and the
other for speaking instruments – the poles and wires to be uniform with those
in use on our existing lines. There will be an intermediate station at
Newport”.
Four
days later, Mr Green wrote again, asking that the PO supply the speaking
instruments (Morse sounders). In his estimate for the work, Mr Raddin specified
double stays on every pole and this was queried by Mr Louth. The former replied
that “railway lines in this District are double stayed – in exposed bog
districts this is most desirable”. Mr Louth did not agree, informing Mr
Raddin:
“All
railway main lines should have double stays on every pole, but I do not think we
should put the Railway Company to such a cost on a light line like this. Only
estimate for double staying every third pole and for stays for curves, at
present”.
Mr
Raddin’s estimate allowed for erecting 360 poles over the 18 miles of new line
at a cost of £167-19-4. Laying out the poles along the course of the line
needed a special train and providing the engine for this seemed to cause some
trouble. Mr Louth requested a special engine from Mr J Tatlow, the MGWR Manager,
on 27 June 1893 “as we are now ready to distribute the poles” and the
Company replied that “the engine can be placed at your disposal by the
Contractor, but it must be paid for”. Mr Louth reminded Mr Tatlow that the
cost of the engine would ultimately be charged to his Company and “possibly
therefore, you can make better terms with the Contractor than I can”. The MGWR
apparently washed their hands of the matter, as Mr Tatlow replied on 8 July “I
would rather not interfere in this matter. I should think that you can make as
good terms with the Contractor as I could”. Mr C Burge, the PO Assistant
Superintending Engineer, tried to negotiate with the contractor, as he reported
to Mr Louth on 14 July:
“With
a lot of waiting and watching, I caught Mr Fisher at his hotel as he was going
away by train. He was not disposed to reduce the figure of £15. Said he would
like to charge nothing, but it was not only wages, engine, etc, but dislocation
of traffic arrangements, etc. I had to accept and have wired and written Mr
Raddin”.
Meanwhile,
Mr Raddin protested to Mr Louth on 5 July about the work being delayed:
“We
have not yet received any instructions as to special engine for distributing
poles on Westport – Mulrany Railway. The poles are lying at Westport (on
wagons); the gang is hindered in the work. Please say if we can get the engine
soon, otherwise it will be necessary to disband the gang for the present”.
In a
further letter to Mr Louth on 11 July, he expressed annoyance at the frustration
he was suffering at the hands of the contractor:
“We
are still unable to get our poles laid out. We made application to the
Contractor’s Engineer who informed us that the contractor Mr Worthington would
arrange it with the MGWR Engineer, Mr O’Neill. Mr Worthington lives in Dublin
and Mr O’Neill is at present in England. The second Engineer, Mr Prendergast
has not received any instructions. We must therefore wait until Mr O’Neill
returns. In the meantime, we have been getting on as best we could by taking out
poles with our own men on trolley, a slow process, as it is only occasionally we
can get a loan of it and then only when the railway milesmen are off work. Our
men have either to start early between 3 and 4 AM or after 6 PM. We have got as
far as we can go in this way without incurring great loss. If there is still
further delay in getting engine, I suppose the gang must in the meantime be paid
off”.
Mr
Louth replied that he was hourly expecting a reply from the contractor and if a
fair bargain could not be made for the use of the engine, arrangements would
have to be made for carting by road. Someone – perhaps Mr Raddin – made a
marginal note on the letter: “utterly impractical”. However, on 14 July, Mr
Louth telegraphed Mr Raddin and confirmed it in a letter of the same date, that
all was arranged:
“It
has been arranged with Mr Worthington through Mr Fisher, to have the use of an
engine to lay out the poles. The engine to be available for your purpose at 4 PM
on Saturday July 15th. You to do the work between that time and Sunday evening.
It is quite possible the work may not go on with the usual expedition on so new
a line. Please report completion. The trucks will, of course, be returned to the
depot from which they are taken”.
In the
margin of the above letter, opposite to the reference to Sunday work, Mr Raddin
wrote: “Never in the course of my career did I do such work on a Sabbath day
and never will, I hope. AR”. He also made a marginal note on the reference to
the new line: “Line bad enough and in many places yet highly dangerous”. The
work was completed on the Saturday, thus sparing Mr Raddin a crisis of
conscience. He reported to Mr Louth on 17 July:
“Poles,
etc were all distributed on Saturday last. We got contractor’s engine at 4.15
PM and finished the distribution to Mulrany at 8 PM satisfactorily. I also had
all empty trucks returned to Westport at 9.40 PM and verbally informed the
Stationmaster, Westport, of having done so”.
Mr J W
Fisher of the contractor’s staff lost no time in demanding repayment of the
cost of the special engine; he wrote to Mr C Burge on the 15 July:
“Kindly
remit me cheque £15 in payment for use of our engine in distributing telegraph
poles per arrangement”.
Presumably
Mr Fisher received payment shortly afterwards. In November 1893, Mr Louth
inquired of Mr Raddin regarding the progress of the work and the latter replied
on 22 November:
“The
work as far as erection of poles and wires is concerned is completed from
Westport to Malranny. No apparatus yet fixed; neither train staffs or sounders,
owing to huts not being ready to receive them. The Westport and Newport huts are
erected, but no battery accommodation is yet provided. At Mulrany nothing was
done in the erection of either hut or station when our men left on completing
the line to the point where the station is to be erected. In the meantime, the
gang is disbanded”.
Mr
Tatlow wrote to Mr Louth on 7 July 1894 to say that “Mallaranny station will
open for business on Monday 16th inst” and asking to have the ETS and sounder
instruments connected up and ready for use by then. However, Mallaranny station
was not ready and the local lineman reported on 14 July that the instruments had
to be placed in a temporary hut, which was 80 yards from the station and 30
yards from the site of the signal cabin, the foundations of which were not even
“cut out”. Signals were exchanged with Newport and the apparatus was
“working well”.
In
March 1894, Mr Tatlow requested that the sounder apparatus be transferred from
the signal cabin to the Stationmaster’s office at Newport and this was done on
29 March.
On 19
October 1894, some months after the line opened to Mallaranny, Mr Tatlow
requested that the ETS and sounder be transferred to the Stationmaster’s
office there (the signal cabin was still not ready). Mr Raddin visited the
station on 27 October and found that no provision had been made for the
instruments or batteries in the office, which was very small, only 12 x 10 feet
and “is already fitted with the requirements of the office, including desk,
etc”. He thought that “we may be able to cram the ETS and sounder in the
office”, but the batteries would have to be placed in a new compartment at the
signal cabin. This was done shortly afterwards.
The
railway was at this time being extended to Achill but the poles and wires for a
telegraph circuit were not erected by the PO, as Mr Raddin mentioned in a note
to Mr Louth on 25 March 1895:
“The
line of two wires has been erected by the telephone company. The poles are
fitted with an arm, but not in accordance with PO Regulations; a 24 inch arm is
fixed instead of 33 inch. The line is completed thus Mulrany to Achill Sound. On
one wire is fixed a single needle instrument at each end”
It is
not clear if the “telephone company” mentioned was the National Telephone
Company or the contractor for the railway signals. About this time, the MGWR
requested the PO to maintain the pole route (the letter is not extant) and Mr
Raddin duly reported on the condition of the route on 8 April 1895 and provided
an estimate of the cost of putting it into “Post Office order”.
“Line
of two wires supported by 170 poles well creosoted and of sufficient length and
scantling. The poles, which are mounted with 24 inch arms, unseasoned and
unpainted, are on the whole – with a few exceptions – well placed as regards
proximity to the rails and altitude for public crossings. They are however, very
badly secured, little or no attempt being made to firm them by stones, the soil
being nearly altogether bog. The poles are consequently very loose and shaky and
will require to be carefully stoned.
Pole
roofs are plain galvanised, but of a thinner substance than what are used by the
PO. They are fastened with thin wire nails, not galvanised, 2¼ inches long, but
of a very inferior quality; the heads very thin and easily detached, many
already off leaving the pole roofs insecure. There are in most cases only two
nails on each pole roof and for about a mile, the pole roofs are fastened with
straps; the workmen having evidently run short of nails. All these pole roofs
require to be overhauled and secured with proper nails.
Insulators
are Buller’s DSB glazed screw and are of a very superior quality. The wires
are however, very badly bound to the insulators, with two laps only and of
inferior binding wire. All must be rebound with 60 lb binding wire of good
quality”.
The
estimate for overhauling the line came to £22-17-9. By August 1895, the MGWR
apparently were complaining of delays in the work (the letter is not extant) and
Mr Louth replied to Mr W P O’Neill, the MGWR Engineer on the 16th:
“The
sole reason for delay in putting [the line] in Post Office order has been to
save your Company money and see how far the Contractor could go in remedying
defects. I expect to deal with the residue immediately and of course, no charge
for maintenance of wire will accrue until the line is put in order to my
satisfaction”.
The
work was completed by the end of the year and the annual maintenance charge of
60/- for the poles and first wire and 10/- for the second wire commenced on 1
January 1896.
In the
meantime, Mr Tatlow had written to the PO on 22 March 1895 asking to have the
ETS instruments at Mallaranny and Achill connected up by 1 April. This work was
completed on 9 May and the annual maintenance charge commenced on the 13 May.
The single needle instruments fitted by the contractor were replaced by Morse
sounders at the same time.
On 7
April 1896, Mr Worthington inquired of Mr Louth the date some extra stays were
added to the line between Westport and Mallaranny. For some reason, Mr Louth
gave a date – 1 January 1896 – for work done on stays on the Mallaranny –
Achill section, causing an annoyed Mr Worthington to again request the
information he needed, Westport - Mallaranny being heavily underlined in the
letter. Mr Louth replied in a firm tone on the 14th:
“I
beg to say that I do not feel called upon to furnish any information about the
Westport – Mulranny line, except to say that any stays thereon are necessary
to its safety. The same remark applies to the present condition of the Mulranny
– Achill section”.
Why Mr
Worthington needed the date is not clear, but he got no further information from
Mr Louth.
In May
1904, Mr O’Neill requested that the sounders at Westport, Newport, Mallaranny
and Achill be ceased and replaced by telephones. At Westport, the telephone was
fixed in the signal cabin, but in the Stationmaster’s office at the other
locations. The four instruments were brought into service on 13 February 1905.
The annual maintenance charge of 30/- per instrument also commenced on that
date.
About
March 1905, Mr O’Neill requested that telephones be fixed on the block wire
between Westport and Westport Quay. The existing telephone at Westport, working
on the Achill line, was utilised, a switch being fitted to select either the
Quay or the Achill circuit as required. The system was brought into service on
18 August 1905, the long delay being caused by having to cater for the
possibility of interference with existing Post Office circuits on the same pole
route.
In
December 1907 a landslip occurred between Westport and Newport, which involved
resetting some poles and stays. The damage cannot have been too serious, as it
only cost £1-5-0 to rectify.
On 20
November 1912, Mr O’Neill requested that the ETS instruments at Mallaranny be
moved from the stationmaster’s office to the signal cabin. This was to
facilitate a night mail service on the branch and the work was carried out on 14
February 1913 at an estimated cost of £9.
Mr A W
Bretland, the MGWR Chief Engineer, made a similar request on 20 November 1919
regarding the ETS at Achill and this was done on the following 9 March at a cost
of £16-5-0.
During
the Civil War, the line between Mallaranny and Achill was closed from 3 February
1923 (a Friday). On 11 April 1923, Mr Bretland wrote to the PO Engineer in
Chief:
“My
Company propose reopening the line at an early date between Mallaranny and
Achill. I shall be obliged, therefore, if you would arrange for the ETS
instruments, wires, etc, to be put in order at the earliest possible moment and
to replace any telephones which may be required. The batteries will also require
attention”.
The
restoration work cost £25 and block working was reintroduced on 4 May 1923
(also a Friday) in the section.
On 30
May 1923, Mr Bretland requested that the telephone at Mallaranny be moved from
the Stationmaster’s office to the signal cabin, as “on account of the
Military using the telephone night and day, the Stationmaster and his family can
get very little sleep”. This act of kindness cost the Company £2-15-0.
Mr J H
Nicholson, the GSR Signalling Engineer, on 25 October 1928, asked to have the
ETS instruments at Newport transferred to the Stationmaster’s office. This was
not a straightforward job, as the PO Engineer explained in his reply on 28
November:
“I
have to inform you that the cost of transferring the ETS instruments at Newport
is estimated at £16. If you decide to have the removal effected it will be
necessary for you to provide accommodation for the batteries and it is suggested
that the existing press in the Stationmaster’s office might be made use of by
fitting four doors with locks and one additional shelf. Two brackets will also
be required on the wall behind each block instrument to carry the ETS bells”.
Mr
Nicholson’s staff made the necessary alterations by 25 February and the PO
made the transfer of the instruments on 2 April.
The PO
public telegraph circuit between Westport and Achill was transferred from a road
route to the railway poles in February 1931. On 8 August in the same year, ETS
working was ceased between Westport and the Quay, when the instruments were
recovered.
Closure
of the branch loomed in 1934 and a Works Order was issued to recover the ETS and
telephone circuits. Closure took place with effect from Tuesday 1 January 1935
and in August the Works Order was cancelled, as the branch reopened on Monday 20
April 1936. This was but a temporary reprieve to allow the roads in the locality
to be improved and final closure came with effect from Friday 1 October 1937.
The ETS and telephone circuits were dismantled by the PO between January and
March 1938.
Sources:
E
Shepherd: “The Midland Great Western Railway of Ireland”
Post
Office Engineering Branch Works Order records in National Archives
Currency
values are £-shillings-pence and shillings/pence.