LUAS
to Cherrywood
An Taoiseach, Brian Cowen T.D. officially
opened the new Luas Cherrywood (Line B1) extension on Saturday 16 October ,
2010). The official opening was also attended by the Cathaoirleach of Dun
Laoghaire Rathdown County Council, Cllr Lettie McCarthy, local
representatives, local residents, RPA’s private sector partners and other
key stakeholders. The opening event was held in the Treasury Holdings Central
Park Building which is adjacent to the new Luas Central Park Stop.
Welcoming the opening of the Luas extension to
Cherrywood, the Taoiseach said "This new extension of the Green Luas Line
is a further development in our infrastructure investment programme which
offers sustainable public transport and paves the way for the creation of a
fully integrated network. The Government’s Infrastructure Investment
Priorities 2010-2016 sets out a comprehensive transport programme which aims
to increase Luas passenger numbers to 42 million by 2016. This programme will
contribute to economic recovery, support employment, deliver important social
infrastructure, and assist the transition to a low-carbon economy.”
RPA Chief Executive, Mr. Frank Allen said that
the extension was a major milestone in developing an integrated public
transport network for the Greater Dublin Area and will add to the
competitiveness of business parks in Central Park, Carrickmines and
Cherrywood. He noted that Luas passenger numbers are showing a strong recovery
with Red Line passengers increasing by more than 10% in June to October 2010
compared with the same period in 2009.
RPA submitted a Railway Order Application for
this project in November 2005 which was followed by a Public Inquiry in March
2006. This Order became effective in January 2007 and construction work
started shortly thereafter. The Minister for Transport signed the Railway
Order in August 2006. An application by a third party for a judicial review
(which was settled out of court) delayed the start of construction by several
months. RPA is pleased to note that the new line has been delivered within the
agreed timeframe and within budget.
Construction of new extension began in the
spring of 200 with preparatory works, including the re-alignment and renewal
of utilities, road works and major structures began
Sandyford Stop was upgraded from two to three
platforms and five new stabling tracks were added at the Sandyford Depot to
cater for additional trams.
The Cherrywood extension runs over three
bridges and one viaduct and crosses the M50 twice. The alignment re-uses some
of the old Harcourt Street line and this required the replacement of the old
Glenamuck Bridge.
A Park and Ride facility for Luas with 350
spaces was due to be provided as part of a larger mixed use development by a
private developer adjacent to the Carrickmines Stop.
However, the developer was unable to secure planning permission for his
development from Dun Laoghaire Rathdown County Council.
In March 2010, the RPA applied to DLRCC for permission to construct a
temporary surface car park (on the undeveloped land of the developer) with 350
spaces and the Council granted that permission on 23 September last.
Subject to no appeals being lodged against that permission, the RPA
plan to move quickly to construct the temporary car park and have it open in
the first quarter of 2011.
It is expected that the new 7.5 km line will
add over 2 million passenger journeys a year to the Luas network. It is a key
component of the Government’s Transport 21 investment programme. The cost of
the Cherrywood extension is less than €300million. The main infrastructure
contractors were the international consortium Sacyr Bowen Somague; utility
diversion works for the project and construction of the Ballyogan Road were
carried out by SIAC and bridge construction was by Laing O’Rourke. Luas
Cherrywood has been included in the Dun Laoghaire Rathdown Council development
plan for some time and the Council was a partner in delivering the project.
RPA also entered into direct agreements with a number of private sector
developers.
There are 9 new stops on the line at Central
Park, Glencairn, The Gallops, Leopardstown Valley, Ballyogan Wood,
Carrickmines, Laughanstown, Cherrywood and Brides Glen. There are also two
future stops: Racecourse and Brennanstown. Neither of these stops is opening
at present; proposed development has not occurred at the anticipated pace. The
two stops will however open for passenger service in line with development in
their immediate catchment areas.
Journey time from Brides Glen to Saint
Stephen’s Green is less than 40 minutes.
Tram Frequency (Weekdays)
From Bride’s Glen to St. Stephen’s Green
5.30 – 6.00
20 minutes
6.00 – 8.00
7-10 minutes
8.00 – 15.00
12 minutes
15.00 – 18.00
10 minutes
18.00 – 22.00
12 minutes
22.00 – 00.30
15 minutes
From St. Stephen’s Green to Bride’s Glen
5.30 – 10.00
7-10 minutes
10.00 – 16.00
12 minutes
16.00 – 19.00
10 minutes
19.00 – 23.00
12 minutes
23.00 – 00.30
15 minutes
Some services on the Green Line will continue
to start and terminate at Sandyford; therefore, the overall frequency on the
Sandyford/Stephen’s Green section of the line will be 3 to 5 minutes during
peak periods.