|

Irish Railway Record
Society
Journal 173 Accident Reports
Malahide
Viaduct Accident Report
RAIL ACCIDENT INVESTIGATION
UNIT
The
RAIU is a functionally independent investigation unit of the Railway Safety
Commission (RSC) and on 16 August it issued its report into the collapse of
Malahide Viaduct (See JOURNAL xxxx). “The purpose of an investigation by the
RAIU is to improve railway safety by establishing, in so far as possible, the
cause or causes of an accident with a view to making recommendations for the
avoidance of accidents in the future. It is not the purpose of the RAIU to
attribute blame or liability.”
The
“Executive Summary” is substantially re-printed here:
On 21
August 2009 as an Iarnród Éireann (IÉ) passenger service, travelling from
Balbriggan to Pearse, passed over the Malahide Viaduct the driver witnessed a
section of the viaduct beginning to collapse into Broadmeadow Estuary. The
driver reported this to the controlling signalman who immediately set all
relevant signals to danger ensuring no trains travelled over the viaduct. Within
minutes of the report of the accident, by the driver, Pier 4 of the Malahide
Viaduct had collapsed into the Broadmeadow Estuary. All post accident emergency
procedures were properly employed by the operating staff resulting in no
fatalities or injuries to any members of the public or staff.
At the
time of the accident, the Malahide Viaduct piers were formed on a grouted rock
armour weir, with stones intermittently discharged along this weir to maintain
its profile.
The
immediate cause of the collapse of Pier 4 was as a result of the undermining of
the weir that surrounds and supports Pier 4 through the action of scouring. This
was as a result of a combination of factors:
 |
An
inspection carried out on the Malahide Viaduct three days before the
accident did not identify the scouring defects visible at the time; |
 |
A
scour inspection undertaken in 2006 did not identify the Malahide Viaduct as
a high-risk structure to the effects of scouring; |
 |
IÉs
likely failure to take any action after an independent inspection carried
out on the Malahide Viaduct in 1997 identified that scouring had started at
the base of Pier 4 and that the rock armour weir was “too light for the
job”; |
 |
The
historic maintenance regime for the discharge of stones along the Malahide
Viaduct appears to have ceased in 1996, resulting in the deterioration of
the weir which was protecting the structure against scouring |
The above
factors were necessary for the accident to happen. Contributory to the accident
happening were the following factors:
 |
IÉ
had not developed a flood/scour management plan at the time of the accident,
despite the IRMS Implementation Review (2001) and the AD Little Review
(2006) recommending that this plan be developed. Contributory to IÉ not
developing this flood/scour management plan was the fact that the RSC closed
this recommendation in 2008; |
 |
Engineers
were not appropriately trained for inspection duties, in that the
inspections training course they completed was an abridged version of the
intended format, and there no formal mentoring programme, for Engineers on
completion of this course; |
 |
There
was a shortfall in IÉs suite of structural inspection standards in that a
standard which provided guidance for inspectors in carrying out inspections
was not formalised; |
 |
There
existed an unrealistic requirement for patrol gangers to carry out annual
checks for scour, as they do not have access under the structure and in
addition, they did not have the required specialist training/ skills to
identify defects caused by scouring; |
 |
A
formal programme for Special Inspections for structures vulnerable to scour
was not adopted, as per IÉs Structural Inspections Standard, I-STR-6510, at
the time of the accident. |
Underlying
factors to the accident were:
 |
There
was a loss of corporate memory when former IÉ staff left the Division,
which resulted in valuable information in the relation to the historic
scouring and maintenance not being available to the staff in place at the
time of the accident; |
 |
There
was a dearth of information in relation to the Malahide Viaduct due to IÉs
failure to properly introduce their information asset management system; |
 |
IÉs
inadequate resourcing of Engineers for structural inspections to be carried
out at the Malahide Viaduct; |
 |
IÉs
failure to meet all the requirements of their Structural Inspections
Standard, I-STR-6510, in that: |
Visual inspections were not carried out for all visible elements of
structures;
Bridge Inspection Cards, for recording findings of inspections, were not
completed to standard or approved by the relevant personnel;
A formal programme for systematic visual inspections of all elements of a
structure, including hidden or submerged elements, despite an independent review
recommending that IÉ implement this programme in 2006.
Immediately
after the accident, IÉ carried out inspections on over a hundred viaducts on
the network. IÉ have now reinstating the Malahide Viaduct, ensuring that the
overall structure has been significantly strengthened, that the weir profile has
been restored and improved.
IÉ are
currently reviewing all the Civil Engineering technical standards in order to
improve the content, readability and practicable implementation of these
standards. Improved control mechanisms are being introduced to ensure compliance
with these standards. A competency management system is also being implemented
to ensure the appropriate training is received by Engineers.
In
relation to tracking recommendations made by independent organisation, the RSC
has formalised their system for closing recommendations, and is now, in
conjunction with IÉ developing an action plan to close all outstanding
recommendations.
As a
result of the findings of this RAIU investigation, the RAIU have made fifteen
safety recommendations. Thirteen safety recommendations have been made to IÉ,
one safety recommendation has been made to the RSC, and one joint recommendation
has been made to IÉ and the RSC.
Recommendation
1 IÉ should put appropriate interface processes in place to ensure
that when designated track patrolling staff (who report to two or more
divisional areas) are absent from their patrolling duties, that appropriate
relief track patrolling staff are assigned to perform these patrolling duties.
Recommendation
2 IÉ should amend the Track Patrolling Standard, I-PWY-1307, to
remove the requirement for track patrollers to carry out annual checks for
scour.
Recommendation
3 IÉ should formalise their „Civil Engineering and Earthworks
Structures: Guidance Notes on Inspections Standard‟, I-STR-6515, which
should include guidance for inspectors on conducting inspections and identifying
structural defects. On formalising this document IÉ should re-issue, in the
appropriate format, to all relevant personnel.
Recommendation
4 IÉ should introduce a verification process to ensure that all
requirements of their Structural Inspections Standard, I-STR-6510 are carried
out in full.
Recommendation
5 IÉ should ensure that a system is put in place for effective
implementation of existing standards and to manage the timely introduction of
new and revised standards.
Recommendation
6 IÉ should ensure that a programme of structural inspections is
started immediately in accordance with their Standard for Structural Inspection,
I-STR-6510, and ensure that adequate resources are available to undertake these
inspections.
Recommendation
7 IÉ should carry out inspections for all bridges subject to the
passage of water for their vulnerability to scour, and where possible identify
the bridge foundations. A risk-based management system should then be adopted
for the routine examination of these vulnerable structures.
Recommendation
8 IÉ should develop a documented risk-based approach for flood and
scour risk to railway structures through:
 |
Monitoring
of scour risk at sites through scour depth estimation, debris and hydraulic
loading checks, and visual and underwater examination; |
 |
Provision
of physical scour / flood protection for structures at high risk; |
 |
Imposing
of line closures during periods of high water levels where effective
physical protection is not in place. |
Recommendation
9 IÉ should adopt a formal process for conducting structural
inspections in the case of a report of a structural defect from a member of the
public.
Recommendation
10 IÉ should introduce a training, assessment and competency
management system in relation to the training of structural inspectors, which
includes a mentoring scheme for engineers to gain the appropriate training and
experience required to carry out inspections.
Recommendation
11 IÉ should review their network for historic maintenance regimes
and record this information in their information asset management system. For
any future maintenance regimes introduced on the network, IÉ should also record
this information in their information asset management system.
Recommendation
12 IÉ should incorporate into their existing standards the
requirement for the input of asset information into the technical database
system upon completion of structural inspections.
Recommendation
13 IÉ should carry out an audit of their filed and archived
documents, in relation to structural assets, and input this information into
their information asset management system.
Recommendation
14 The RSC should review their process for the closing of
recommendations made to IÉ by independent bodies, ensuring that they have the
required evidence to close these recommendations. Based on this process the RSC
should also confirm that all previously closed recommendations satisfy this new
process.
Recommendation
15 The RSC, in conjunction with IÉ, should develop an action plan in
order to close all outstanding recommendations in the AD Little Review (2006)
and the IRMS Reviews (1998, 2000, 2001). This action plan should include defined
timescales for the implementation and closure of all these recommendations.
RAILWAY SAFETY COMMISSION
Also
on 16 August 2010, the RSC published its compliance audit into the Viaduct
collapse. This audit is separate and independent of the RAIU investigation. It
was completed in March 2010, but under section 57(1) of the Railway Safety Act
2005, the RSC could not make its findings public before the RAIU had published
its investigation report.
“The
compliance audit examined whether correct safety management systems were in
place and whether key safety checks were being undertaken by the railway
operator, IÉ, prior to the collapse of the viaduct ...”
The
RSC found four non-compliances by IÉ:
 |
Front
line inspection staff failed to carry out monthly and yearly inspections of
the viaduct, as laid out in IÉ standard I-PWY-1307 |
 |
There
was a failure by Engineering grade staff to undertake the required number of
inspections/ checks as set out in IÉ standard I-SMS-9021 |
 |
There
was a failure to carry out structural inspections and keep proper records
using the correct forms, as set out in IÉ standard I-STR-6510 |
 |
IÉ
had failed to implement a competence assessment for all personnel engaged in
safety critical roles in accordance with IÉ Railway Safety Standard 67. |
The
RSC made 16 recommendations, including that IÉ:
 |
Review
the need for a Coastal Defence Inspector or inspection team Review the
Structural Inspections Standard I-STR-6510, to include all relevant
elements, including scour |
 |
Develop
a procedure to manage reports of safety related events, e.g. information
from the public |
 |
Review
patrol ganger (frontline inspection team) competence requirements |
“IÉ
was requested and has provided an improvement plan and the RSC will monitor the
implementation of this plan closely.”
“The
purpose of an investigation by the RAIU is to investigate for cause – why an
incident occurred. The purpose of the RSC audit is to check for compliance with
agreed safety standards and legislation. As the regulator, the RSC has the power
to bring sanctions under s.76-78 of the Railway Safety Act 2005. Based on the
evidence in the RAIU report, the RSC will now consider what sanctions, if any,
are appropriate or possible under the legislation.”
The
RSC said: “In relation to Recommendations 14 and 15 made by the RAIU about the
RSC’s own role, we have already implemented Recommendation 14 and are
currently planning to implement Recommendation 15, as detailed in p110/1 of the
RAIU report.”
MINISTER FOR TRANSPORT
Mr
Noel Dempsey, TD, Minister for Transport issued a statement saying: “This is
an important report into a very serious event. Thankfully due to the speedy
actions of the train driver on that day and the effective operation of all post
accident procedures, there were no fatalities or injuries to any members of the
public or staff. However, this report gives a detailed and worrying account of
the inadequate maintenance and inspection regime in IÉ of recent years which
failed to safeguard the viaduct structure from the impact of scour and erosion
in Broadmeadow Estuary... I understand from the report and from updates by IÉ
that significant changes have now taken place to meet the short-comings
identified and to ensure that there is no repetition of this event.”
IARNRÓD ÉIREANN
IÉ
issued a statement saying: “At the outset, IÉ accepts the findings of the
RAIU and RSC, and together with the findings of our internal investigation, we
sincerely regret those issues – which have been highlighted in the reports -
which led to this accident on 21 August 2009, and apologise to customers, who
experienced significant disruption to services as a result.”
“Following
the accident, IÉ commenced a programme of major reform across all aspects of
the safety management of infrastructure...” “Following receipt of the
compliance audit, IÉ agreed an action programme with the RSC to address the
findings, and excellent progress has been made to this end.”
“These
actions, which address the issues arising from the RAIU accident report and RSC
audit, are part of a much wider review undertaken by IÉ since the accident of
the Civil Engineering Department, and the approach towards the management of IÉ’s
infrastructure.”
“Therefore,
the actions to address the non-compliances and recommendations have been
undertaken in the context of fundamental change implemented since January 2010
in the Civil Engineering area, including:
 |
A
new Safety Management System for Civil Engineering |
 |
A
re-organisation and re-staffing of the Civil Engineering area, with new
management and structures |
 |
A
thorough review of all the Civil Engineering technical standards is being
conducted in order to improve the content, readability and practicable
implementation of these standards. |
 |
A
“compliance verification” process to regularly audit and check that the
new processes are continuously followed in practice |
 |
The
Civil Engineering Department have now implemented a competency management
process that is resourced with a Competency Manager supported by
Assessors.” |
“In
conclusion, the actions completed by the Civil Engineering team comprehensively
covers the requirements and recommendations of the RSC Compliance audit, and
will ensure that the issues arising from this incident – both in relation to
the physical infrastructure of the viaduct, and the systems and processes
supporting our management of infrastructure – are addressed, and our safety
management significantly strengthened.”


Copyright © 2010 by Irish Railway Record Society Ltd.
Revised: January 04, 2016
.
|