Irish Railway Record Society

Home News 171 Dargan 171 Drumsna 171 Malahide171 Mk. IV 170 Timetable 171 Society Matters 171 Reviews 171 Obituaries 171

Journal 171

River Shannon Bridge, Sligo Line

AIDAN McADAM, Specialist Engineer; Structural Section, IÉ

OLIVER DOYLE, Operations Schemes Development Manager, IÉ

When the Grand Canal reached the River Shannon in 1804, the small village of Drumsna, Co. Leitrim, became the limit of navigation northward and a distribution point for goods to the surrounding area. The opening of the Shannon Navigation through the Jamestown Cut and the Albert Lock in 1848 diminished Drumsna’s importance as vessels could then access Carrick-on-Shannon and Leitrim village. This was soon followed by the opening of the railway from Longford to Sligo on 3 December 1862. The bridge across the River Shannon was just 2 miles south of the village and a station was provided about 11/2 miles from the village on the opposite side of the Shannon.

The Midland Great Western Railway was the main provider of rail services in the province of Connaught with its main line from Dublin (Broadstone) to Galway and two other important routes, Westport & Achill, and Sligo. The Galway route was double track except for two sections, Ballinasloe-Attymon and Athenry-Oranmore. On the Mayo line the double track was constructed as far as Roscommon. When opened to Longford on 8 November 1855, the Sligo line was double track and some passive provision was made for double track onward to Ballysodare. The railway between Ballysodare (MP 1293/4) and Sligo (MP 1341/4) was double track from the opening and this was extended a mile southward to Carrignagat Junction (MP 1283/4) with the opening of the Sligo Leitrim & Northern Counties Railway on 1 September 1881. On the Longford-Sligo section provision was made for a second line of rails on the bridge over the River Shannon by constructing double-track abutments and piers – Underbridge (UB) No. 500, MP 92, about a mile east of the station at Drumsna.

ORIGINAL BRIDGE

The original bridge was supplied by Fox, Henderson & Co., Derby. The company was co-founded by Sir Charles Fox who drove the locomotive Novelty at the Rainhill trials on the Liverpool & Manchester Railway in 1830. Fox Henderson supplied the roofs of London Paddington, Bradford Exchange and Birmingham New Street stations but their best known structure was the Crystal Palace for the Great Exhibition of 1851. In Ireland, they also constructed the MGWR bridge at Athlone and the Chetwynd Viaduct on the Cork & Bandon Railway.

The bridge was shipped in through Limerick and taken up the River Shannon to the site. With an overall length of 94.4m, the bridge consisted of six spans – two 9.2m spans at each end and two 23m spans in the centre. Spans 1 & 2 form an interesting opening section, spans 3 & 4 are single spans each using lattice girders whereas spans 5 & 6 are a single lattice girder with Pier 5 acting as a central support. With a height of 1.98m and square ended, this span differs from the two central spans which are 2.45m high and have the top ends curved. The bridge was maliciously damaged during the Civil War by an explosive device on 9 October 1922. The damage is said to have been mainly burning of timbers and the line was quickly re-opened. In the 1950s, spans 5 & 6 were replaced by a single long bridge section recovered from a disused line, though which line could not be established.

Locally the eastern end of the bridge is known as the Leitrim end and the western end the Roscommon end, but for clarity in this paper Dublin and Sligo ends are used respectively.

The railway across the bridge was supported throughout on way-beams which, with modern standards, limited the speed to 25mph. However, due to the age of the bridge, the speed was reduced to 10mph on 12 December 2004, with cascading restrictions of 35mph for 3/8-mile approaching the bridge and a restriction of 50mph for 3/4-mile before the 35mph restrictions.

On span No. 1, lattice iron girders support the railway using conventional cross-members with the rails on way-beams. However, the railway on span No. 1 was supported on two lattice girders resting on recesses in both the Dublin side abutment and Pier No. 1, with cross members  on the girders to carry the track. The cross members at the Dublin end were attached to the short fixed side girders extending about 1/3 of the way across the span.

The arrangement for the opening span, No. 2, was unusual as it spanned the then navigation channel and was a single-leaf bascule structure pivoted over the water on the Dublin side of Pier No. 1. A continuation of the No. 2 beams extend about 2/3rd way across span No. 1 where there is a counter-balance weight. On the Dublin side of the counter-balance the steel girder was rather crudely cut suggesting that originally it may have had a clearance problem.

 

SIGNALLING

The MGWR signalling diagram dated June 1897 shows a signal cabin on the down side at the Dublin end of the bridge. It had 5 levers:

1          Up Distant

2          Up Stop

3          Bridge Bolt Locks and Dis-engagers

4          Down Stop

5          Down Distant

 

A masonry dome topped mooring dolphin was provided up river from the bridge close to the Dublin bank of the river for boats to moor awaiting the bridge to open.

On 26 March 1934, the signal cabin and associated signals were removed and replaced by a one-lever ground frame with an Annett’s lock located on the down side at the Dublin end of the bridge and released by the Drumsna-Dromod Electric Train Staff. According to the 1935 GSR Appendix to the Working Timetable, the Stationmaster at Drumsna had to advise the Permanent Way Ganger when it is required to open the bridge so that his men could attend and disconnect the rails and assist with the opening and closing. When the Stationmaster was satisfied that the PW Dept were in attendance, he obtained a Drumsna-Dromod staff from the signalman at Drumsna and then proceed with the staff to the bridge and unlocked the one-lever ground frame. This freed the Bridge Lock Lever, allowing the bridge to be unlocked. The Stationmaster was also required to telephone his counterpart in Dromod before the bridge was opened and after it was closed. The bridge was not opened in many decades and its last suggested opening was in the early 1950s to allow a residential barge, which had spent many years moored in the nearby Jamestown Cut, to pass through.

 

WINDING MECHANISM

The bridge was hand wound using a basic crank-handle (1) rotating a small pinion which, in turn, rotated a much larger gear wheel (2) with a ratio of approximately 5:1. This large gear wheel was fixed to a shaft which had a brake drum (3) and a small 3-toothed pinion (4). The brake drum used a hand-operated iron band to control the bridge speed where necessary. The 3-toothed pinion was 710mm (2’ 4”) in circumference and engaged a long chain (5) to rotate a much larger toothed wheel (6) of 4,260mm (14’ 21/2”) circumference with 5 teeth which gave a ratio of 6:1. The chain was alternating between a single and double link. The drive shaft, on which the large toothed wheel was mounted, extended to both sides of the bridge, where each side has a small pinion affixed. At each side of the bridge the small pinions engaged with a quadrant (7) affixed to the bridge pivot with a ratio of 4:1 – the small pinion had 10 teeth while the quadrant had 44 teeth. However, the 44th tooth was blocked by a limiting nut to prevent overthrow and disengaging. Mathematically it would have taken approximately 120 turns of the handle to move the quadrant 90° and open the bridge fully. Apart from two lengths of chain between two iron posts (8), there was little to safeguard the bridge operator. The winding mechanism was attached to the pier on the Sligo side by two rods (9) each side of the bridge, anchoring it about three-quarter way down the pier. Two Barlow rails braced it to anchor points about three quarters way down the pier on both sides on the Dublin side.

OVERALL RENEWAL PLAN

In the early 2000s, the bridge was being considered for renewal but the cost was high. Eventually in 2008, it was decided funding had to be allocated to the bridge’s renewal. The cost, 5.5m, was funded by the Government’s Railway Safety Investment program. The planned new structure was to be of four spans, increase the vertical clearance for river craft by a metre, and have a ballasted deck for the railway, thereby allowing trains to cross at the full line speed of 75mph.

The plan was that the new spans would be fabricated by a specialist contractor and taken to a riverside site where the concrete deck would be poured together with the ballast containment side walls. One of the world’s largest cranes would be hired to lift out the old spans, lift in the new bed stones, and follow with the new spans. New track would then be laid across the bridge and connected to the existing track. The track approaching the bridge would have to be raised by up to a metre at each side. The program was carefully planned to fit within a total line closure of eleven days.

SPANS

The bridge was designed by IÉ’s Structural Design Section at Inchicore Works. Taking all factors into account, it was decided to use four Half Through Girder Warren Truss spans, two of 25m length for the centre spans and two 22.2m units for the end spans. These weighed 129t and 122t respectively. The Warren Truss provides optimum efficiency and was in keeping with the design of the original bridge. The Warren Truss is a parallel chord truss with diagonals in alternating directions creating a “W” pattern. SIAC Butlers Steel, Portarlington, were awarded the contract for the fabrication of the units using S355J2+N steel. The spans are first fabricated and then grit blasted followed by a thermally applied metal spray. Two intermediate modified epoxy aluminium coats were then applied and the bridge then finished off in a green polyurethane paint. On completion in February 2009 they were transported by road in April to IÉ Bridge Gang depot in Mullingar for storage until the reception area at the bridge site was ready.

RIVERSIDE SITE

The bridge has always been remote from any road and before a construction site could be established adjacent to the bridge, a road 900m long had to be built from the nearest public road, at OB 498, to the proposed site. There were three elements required at the river; offices as well as equipment and material storage, space for the bridge spans, and a strong concrete pad for the crane. First, a 7m road 7m wide was constructed 800m to the site. There an office compound was established and on the riverside of this four pairs of concrete pads were cast in situ, with a temporary steel bearing on each side to receive the spans in preparation for concreting.

Given that the crane, when moving the furthest span into position, would have an all-up weight close to 2,500t a substantial concrete pad was required. First, sheet piles were driven in along the riverside perimeter of the site and then back filled to a depth of 11/2-2m with boulder clay excavated from the access road site. Then 239 piles of 323mm diameter were driven into the area allocated to the base and a blinding layer of concrete applied. Steel plates, 450mm2, were welded to the top of the piles and then the reinforcing steel H25 (25mm) was fitted and 900m3 of 50kN concrete was poured to give a finished slab thickness of 750mm.

TRANSPORTING THE SPANS TO SITE

The road network between the main Dublin-Sligo N4 road at Aghamore and the riverside site was quite unsuitable for transporting the spans because of their size. It was decided to take them to a roadside site, which proved very suitable, between two over-bridges (OB 489A & 490) near MP883/4 and crane them onto railway bogies. The road at the site was part of an earlier upgrade to the N4 but had been recently bypassed by a further upgrade and getting a road closure would not cause any significant inconvenience to local residents.

To transport the spans to the site, IÉ purchased two air-braked 4-wheel bogies from Unilokomotive Ltd. (Unilok), Tuam, Co. Galway. Each bogie has self-levelling cross members controlled by an inclinometer, which gives an electric signal to a process controller. This in turn controls the hydraulic lifting and lowering system to maintain the load level at all times the cross-members are fitted with special pads at each end to receive a bridge span. The pads are adjustable to receive different width spans. The cross-member can be adjusted ±50mm. The bogies have 900mm diameter wheels at 3m centres. When travelling light they are coupled by a drawbar and when loaded they are attached to the underside of the end of the span or beams they are conveying. The bogies, which proved extremely useful for the Shannon Bridge renewal, are a long term investment for bridge renewals and between tasks they are stored at the IÉ Bridge Gang’s depot at Mullingar.

To haul the bogies a Unilok locomotive was hired from the manufacturers. This was an 0-4-0 Model E125-s Tracktronic with a 190hp Deutz 6-cylinder water-cooled engine. The four wheels are all independent and not axle mounted, allowing simple adjustment of the gauge. For this project they were, of course, set to 1,602mm (5’ 3”) as they had been for a NIR contract. The locomotive involved had also worked on 1,435mm (4’ 81/2”) gauge in the UK and USA. The rail wheels, which are 760mm diameter with UIC profile and are at 3,100mm centres, have a hydrostatic drive. The unit is a road-rail type with four road wheels in addition to the rail wheels. The front road wheels are retractable on a swivel-pinion suspension axle and the rear tyres are retractable independent trailing arm units. An important feature of the locomotive is its underside mounted, retractable, turntable making it a highly versatile machine.

For the UB 500 job, the locomotive and bogies were parked at over-bridge No. 498 at MP 911/2 on a specially prepared site. Each of the four nights that the spans were being moved, the trolleys were lifted onto the track by a HIAB (a company specialising in load handling solutions) telescopic jib of a lorry, but the locomotive drove on using its road wheels, dropped its turntable and rotated about 90°, raised its road wheels and when the turntable was retracted the locomotive became rail mounted. It then coupled to the bogies and propelled them to the loading site.

It was originally planned to move a span each night from Monday 10 August to Thursday 13 August but after a minor derailment on the first night, the plan was reviewed and it was decided not to move a span on Tuesday night and extend the program until Friday night.

On the Monday night, a possession was taken between Dromod and Sligo, the principal reason was to move the first span to the riverside site and also to allow the local permanent way staff carry out other work in the possession. As the possession could not be granted until the 19:05 Dublin-Sligo train arrived in Sligo at 22:08, it, on reflection was deemed late, and on the subsequent nights it was altered to the Dromod-Carrick on Shannon Loop section to give a 21:20/25 possession start.

A road closure of the older section of the N4 was arranged for each night and a 500-tonne lift capacity mobile road crane was erected nightly in time for the rail possession. When the possession was granted, the Unilok locomotive and trolleys were placed on the track and the trolleys were propelled to the loading site and separated so that there was a trolley under each end of the span. Earlier the lorry conveying the span had parked within reach of the crane, which lifted the span over the side of the cutting, and slowly lowered it onto the awaiting trolleys. The trolley at the Dromod end took the load first. The brakes on the trolleys are ‘fail safe’ – brakes are normally applied unless air pressure is applied to release them. The air brakes between trolleys were connected by long air hoses running along the floor of the bridge span. A generator on the span was used to supply electricity to power a light on each side of each span so the staff, walking beside the span as it was slowly hauled to the bridge site, could observe the wheels and call for the consist to be stopped in the event of a possible derailment situation. The transport time between the two sites at slow walking pace was three hours. On the final night, 14 August, the Central Traffic Control, Northern & Sligo lines signalman granted the railway possession between Dromod and Carrick-on-Shannon Loop at 21:23 and at 23:07, the Unilok locomotive commenced the haul and the span soon disappeared out of sight through the masonry arch of OB 490, the whole operation taking just 1 hour 44 minutes.

On the first night as the initial span was being towed at 5-7 km/h, the up side wheel of the front axle of the rear bogie derailed near the 893/4MP on a 1,818m radius curve where the cant was 95mm and proved difficult to re-rail with a result the railway was closed until 14:32 the following day. Some modification was deemed necessary to the rear bogie to prevent a repeat and this were carried out in time for the second move which was deferred to Wednesday 12 August and the speed was altered to 1-11/2km/h. The modification was the addition of a centrally located pivot bearing located on the self-levelling beam.

CRANE

Given that the centre of the Sligo side span was 83m from the Dublin abutment, a crane with considerable reach was required and it was decided to hire a 1,350 tonnes maximum lift capacity crane from Mammoet, a worldwide hirer of heavy lift cranes. The model selected was a LIEBHERR LR 11350 crawler type with a lift capacity of 1,350t at 12m. The crane is powered by a Cummins 641Kw (872hp) diesel engine with a hydraulic transmission and in full working order weights 2,500t.

Prior to the IÉ job, the crane was engaged at Heuston, Texas, and due to high winds there the lifts could not be completed in time for the shipping deadline to Ireland. Eventually the crane was loaded on the 8,448–tonne MV EDMONDGRACHT, registered at Amsterdam, Netherlands. The vessel is equipped with three derricks, each with a maximum lift capacity of 60t. The crane sections were loaded onto and unloaded from the ship by the derricks as no piece exceeded 50t. After first loading a part-cargo of rice in the Mississippi, the vessel proceeded to Port Arthur, 90 miles east of Heuston, Texas, to load the crane and from there it departed on 23 September, 12 days later than the original schedule, with an estimated arrival in Killybegs of 4 October. The crane sections were to depart immediately upon unloading for the bridge site and it was estimated it would take 3-31/2 days to mobilise the crane and it would be ready for lifting on 8 or 9 October. However, on 29 September the master of the vessel e-mailed to advise that North Atlantic storms had further delayed the vessel, which was then 3,238.4 nautical miles from Killybegs and re-estimating arrival in Killybegs of 11:00 on 9 October. This was based on an average speed of 12.5 knots. After negotiations with Mammoet, it was decided to defer the renewal of UB 500 until 10:05 Tuesday 27 October 2009 – the day after the Public Holiday weekend. The original planned start date was planned for 5 October 2009.

On the afternoon of Thursday 8 October the vessel entered the harbour at Killybegs, swung around 180° to position the derricks on the landward side of the vessel ready for unloading on Friday and Saturday. This was the first trans-Atlantic vessel to dock at Killybegs.

Killybegs was an eminently suitable port for the importation as it was possible to store all the crane sections on part of the large quayside. A 220t lift capacity crane manufactured in Germany by Faun and supplied by Quinn Cranes Ltd., Derrylin, Co. Fermanagh moved the various pieces from the shipside to the storage area. Two 40-tonne pieces were loaded directly onto seven-axle heavy haulage trailers with the four rear axles having steering facility. By Saturday evening the unloading was complete and the vessel secured for sailing to Ipswich, England, with the rice cargo. Starting on 21 October, 77 lorry loads transported the crane sections to the construction site. Using a 100t local crane, the giant Liebherr crane was assembled and ready for use on 27 October. The 126m high red boom (measured from the pivot point approximately four/five metres above ground) dominated the skyline and could be seen for miles around. In contrast the Spire in Dublin’s O’Connell Street is 121.2m.

The crane could accurately measure the weight of each lift and was fitted with an anemometer on the top to measure the velocity of the wind. The crane was restricted to operating where the wind speed was less than 36km/h or Force 5 – Fresh Breeze - on the Beaufort scale.

On completion of the work, the crane was disassembled between 1 & 6 November and returned to Killybegs to await shipping. The 2,981t MV EENDRACHT was chartered to convey the crane and, after the crane sections were loaded, departed for Westdorpe in the Netherlands on 9 November, from where the crane was taken to the next job in Belgium. OB Heavy Haulage, Mullingar, transported the crane between Killybegs and Drumsna.

PREPARATORY RIVERSIDE WORK

After delivery, the basic bridge spans had to have a walkway for permanent way staff attached to the spans on the down side. The walkway of galvanised steel, 1.2m wide, was attached to the spans. Steel reinforcing was erected on the deck which, with the shear pins formed a composite deck. The 200mm concrete floor was poured on each span and when the floor was dry, shuttering was erected on each side and a ballast containment concrete wall poured to give a finished wall 800mm high and 200mm thick. During the concreting process two of the bridge sides were covered with shrink-wrap while the other two had corriboard applied to prevent damage and concrete splashing on the painted bridge. Before installation the concrete floor and walls had a water proof coating applied using Sterling-Lloyd eliminator.

EXECUTING THE PLAN

As enabling work began, both close to and on the railway, the speed over the bridge was reduced to 5mph on and from 28 September 2009. The guard rails were removed. Spans Nos. 3 & 4 were a single bridge unit and as part of the preparatory work riveted joining plates top and bottom were replaced by bolted places. The piers and abutments were surrounded by scaffolding with walkways and debris netting. A scaffold bridge was constructed across the river on the north side of the bridge to give continuous access and had ladders dropping onto each pier.

Prior to the railway closure, two traffic control boats with STOP/GO boards and red/green traffic lights took up position at designated mooring positions north and south of the bridge to control river traffic and create an exclusion zone while the crane was operating over the river. At 10:07 on Tuesday 27 October 2009, the Central Traffic Control Signalman for the Northern & Sligo Lines granted a possession of the railway between the down starting signals at Dromod (SL806 & SL807) and Sligo buffer stop. The local permanent way staff and the Bridge Gang from Mullingar began cutting the track at the span ends ready for the lifts. Each span had brackets pre-fitted to the four corners and these were used to jack the span up approximately 50mm before the crane lifts to ensure the spans were free and ready to be lifted and not apply unnecessary strain on the crane. However, just after midday the wind speed increased and remained too high until 03:00 Wednesday so no lifts were possible. It was planned to remove the spans from the Sligo end and to start with dropping in the new spans from the same end. After the wind abated, the first three spans were removed before daylight. Work started about 10:00 on the lift span but it proved difficult with all its attachments. It was estimated that the span weighed 25t but ultimately it was found to be 53t – possibly having lead in the counter balances or additional iron plates having been added in earlier times. Care had to be taken to ensure excessive lift was not applied by the crane, which could cause whiplash and possibly buckle the crane boom. It was 17:00 before it was finally lifted. Span 1 quickly followed.

Preparations were made to lift in span 4 and 3 starting at the Sligo end. The area for the transition pieces at the Sligo abutment was prepared as was the top of pier No. 5, which was not being fitted with bearings as it would not be providing support to the span. The bed stone for pier No. 4 was completed and the bearing accurate positioned. The required accuracy for the bearing was ±2mm. At 10:30 the crane collected span No. 4 from its pad but the wind velocity increased and the unit had to be parked though the slings remained hooked up. The Metrological Service was indicating that some drop in the wind speed was possible but this did not happen. Overnight Wednesday/Thursday the wind increased considerably and was accompanied by torrential rail. During Thursday morning the forecasters were giving a considerable drop in wind speed and dry weather to occur between 15:00 and 16:00. At 14:00 there was no indication it would happen but at 15:05 the wind dropped dramatically and the rain stopped.

At 15:15 the decision was made to go with the installation of Span No. 4 and what followed in the next 22 hours was a remarkable feat of engineering. All four spans, three bed stones and four transition pieces were lifted into place, completing the lifts, recovering the lost time, putting the program ahead of schedule, and allowing the giant crane to be decommissioned.

First, span No. 4 was lifted in and quickly followed by span No. 3. The next pieces to be lifted in were the two transition pieces for the ballasted track at the Sligo end. Meanwhile piers No. 2 & 1 were then prepared and the bed stones lifted. It was decided to wait until daylight to lift in the last two spans. Between 09:00 and 13:00 the two spans were lifted in completing the lifts. All that now remained was some tidying up and the installation of the ballast and track.

Where the spans connected to each other, the final 1.5m of floor was not pre-poured so the after installation a single pour could give a good connection between the two spans. These were poured on Saturday 31 October and the following week the waterproofing was applied. Where the spans abutted, the ballast containment walls have sealed joints with steel plates on the ballast side to prevent the ballast causing damage. Protection matting was fitted to the side walls and floor to prevent the ballast damaging the waterproofing.

PERMANENT WAY

With the raising of the bridge by a metre, it was necessary, of course, to raise the track either side. Ballast dumps were provided either side of the bridge in advance and a total of 8,000 tonnes of high speed specification type was delivered from Owen’s Concrete, Mullingar. Immediately after the possession was granted the track was cut mainly into 9m panels to comply with the standard for tandem lifting of track panels. On the Dublin side the track was cut for 525m and on the Sligo side the distance was 360m. The panels were removed by two earth moving machines working in tandem. Earth moving machines and dumpers then spread the ballast and by Wednesday night the Dublin approach was ready for re-railing and early the following afternoon the Sligo side was ready. Given that the new bridge was allowing an extra metre clearance to river craft and the track was on a ballasted deck, the existing track level had to be increased by up to 1,100-1,300mm to match the rail level of the new structure.

On Thursday 29 October the rail train from Portlaoise Depot approached the site on the Dublin side and dropped new 144m long rails for the new bridge and where the track had been cut into panels. The total length was 985m. Tamper No. 739 was locked in the Sligo side once the old bridge was taken out. As well as preparing and doing the ballast lift for the bridge, some essential maintenance was also done.

At 10:54 on Friday 6 November the possession of the Dromod-Sligo section was handed back to the Northern & Sligo Lines signalman and the 09:05 Dublin-Sligo was the first train over the new bridge operating on schedule. A temporary speed limit of 25mph was imposed for the reopening and this will be raised to 40mph after some ballast retaining units are put in position on the up side on both ends of the bridge. Later the speed will be increased to 60mph. The line speed of 75mph will apply across the bridge as soon as the new track is consolidated.

CONCLUSION

In conclusion we wish to thank Mike Kiely, Killybegs Shipping Services; Dave Aspell; Ken Manto; Ken Wade; Vincent Brady; John Callanan; Ron Cox, Ulick Egan, Unilok; the library staffs of the British Library, St. Pancras; Institution of Civil Engineers London; National Library, Dublin; and Trinity College, Dublin

 

The remainder of this article appears in IRRS Journal number 171, published February 2010.

Copyright © 2010 by Irish Railway Record Society Limited
Revised: January 04, 2016
.

Home Up