|
Irish Railway Record Society Irish Railway News - Journal 167
CENTRAL GOVERNMENT
EU
Funding Details of EU funding of various IÉ
schemes have been released. The table shows total and EU expenditure by
geographical area where BMW is the Border Midlands and Western area and S&E
is the Southern and Eastern area, which attracts lower EU funding:
EU
Commission On
26 June, the Commission sent letters of formal notification to 24 member states
regarding their failure to implement the [EU] First Railway Package of
legislation properly.
RAILWAY
PROCUREMENT AGENCY ANNUAL REPORT The RPA’s annual report for 2007 was published on 9 July. During the year the Railway Procurement Agency (RPA) made significant progress towards the procurement of light rail, metro and ticketing infrastructure through the Transport 21 investment programme. A total of 28.4 million passengers carried in 2007, an increase of 10% on 2006 (see JOURNAL 166). An after taxation surplus of €6.645m (2006: €4.652m) was generated from commercial activities. Amongst these commercial activities, the infrastructure business activities, including the provision of the Luas infrastructure to Veolia, generated a pre tax surplus of €6.868m (2006: €5.646m). Net income from the provision of Luas infrastructure grew by 14% while net income associated with advertising, park and ride and property activities grew by 17%. Trams ran a total of 2.75m km in 2007, 1.75m on the Red Line and 1m on the Green Line. Over 99% of scheduled services were delivered during the year. SmartCard usage was up 45% on 2006, with 53% of passengers using Luas to commute, 36% for shopping and 30% to pursue leisure activities. Some 68% of passengers are regular users, while 32% are occasional. The strong performance of Luas allowed the RPA to invest in improvements to services during 2007: increased frequency on the Green Line, giving a 3.5 minute frequency from 08:00 to 09:00, additional services for special events, installation of a lift at Dundrum, modifications to seating and handrails to give extra capacity, continuing the programme to extend the Red Line fleet to 40m. During 2007, the average number of staff employed by the RPA was 198 (2006: 139). RAILWAY
PROCUREMENT AGENCY (LUAS) RED LINE Red
Cow Services on the Red Line were withdrawn
between Blackhorse and Tallaght from 21:00 on Friday 22 until the start of
services on Monday 25 August. This was to allow the rerouting of the line
through the During the
period of the closure, services operated between Blackhorse and The overhead line through the work site was de-energised at approximately 22:00 on the Friday. Work on disconnecting the old alignment and connecting the new one was completed by early evening on the Sunday and the line was formerly handed back at about 20:00. There followed a period of intensive testing of all aspects of the new section of line, e.g. the track, clearances, the overhead line etc. Starting at approximately 02:00 on Monday, the 11 trams which had been operating between Blackhorse and the city centre were moved back to the depot for servicing, the last entering the yard at 03:00. The first tram for the start up of service left the Red Cow at 05:15. SYSTEM
EXTENSIONS
Line A1 (Belgard-Citywest) Having examined the draft Railway Order, the documents accompanying the application and the Environmental Impact Statement submitted by the RPA, together with the written submissions and the evidence at the Oral Hearing, the An Bord Pleanála (the Planning Board) inspector recommended that a Railway Order providing the RPA with the necessary powers to construct, operate and maintain Line A1 (Belgard to Saggart) be made. An Bord Pleanála made the order on 16 June 2008. To allow for any legal challenges to the granting of the order, there was a two month wait before it came into force. Area
19 (Cookstown-Fortunestown) The line will cross
the new outer ring road at grade a short distance to the east of the
Cheeverstown stop. In order to avoid disrupting road traffic at a later stage,
the line’s two tracks were installed when the road was being constructed. Line B1 (Sandyford-Bride’s Glen) Work is well advanced along the length of Line B1: Sandyford Depot Site clearance work, in preparation for the laying of additional stabling sidings, is well advanced, as is the construction of foundations for new overhead contact system (OCS) support masts. Sandyford A facing crossover, to allow arriving trams use the inbound platform, has been installed to the north of the Sandyford stop. Upgrading work on the outbound platform commenced in July and this will be followed work on the inbound one. To facilitate this work, trams operated between Balally and the city centre only for approximately three hours at the start of services on some Saturdays and Sundays during June, July and August. Area 13 (Sandyford-Murphystown Rd) Formation clearance and boundary wall realignment works have taken place alongside Blackthorn Ave. Construction of the reinforced concrete trackbed has commenced at the junction of Blackthorn Ave and Burton Hall Rd. Construction
of the trackbed on the approach ramp to and across the bridge spanning the
roundabout at the Work
on the trackbed along the edge of the Area 14 (Murphystown Rd-Ballyogan
Wood) Clonlea House has been demolished and
formation clearance work through the site is well advanced. Formation clearance
along Area
15 (Ballyogan Wood-Bride’s Glen) Work on the
Carrickmines bridge over the M50 and its approach ramps is substantially
complete. Following the completion of bridge works, Formation clearance between Carrickmines and Brennanstown is to start during September. Work on the Cherrywood viaduct has been completed. Line
C1 (Connolly Station-Point Depot) To facilitate
the construction of the delta junction between Busaras, Connolly and
Harbourmaster Place, services in the Abbey St-Connolly section were suspended
from 16 June. Preparatory works, including the widening of the inbound platform
at the Abbey St stop and the installation of bollards alongside the line between
the Area
16 (Store St-Connolly-Mayor Sq)
Work on the breaking out of the original trackwork between the crossovers at
Connolly and the Turnouts
were installed at the eastern end of the Busaras platform and immediately south
of the Connolly crossovers. Short sections of line leading from these turnouts
towards Mayor St Lower were also completed. To accommodate the new turnouts at
Busaras, the platform there was moved slightly away from The
first trams to operate into Connolly after the closure ran as gauging trials on
the afternoon of Saturday 6 September. Public services recommenced the following
day. To mark the re-opening of the line, complimentary bars of chocolate were
distributed to passengers at the stops on Monday 8 September. Area
17 (Mayor Sq-Point Depot) Work on the new bridge
over the Trackbed
works in Mayor St Upper started in May. Track laying is currently underway on
the section immediately east of Utility Diversions It is expected that all utility diversion works will be completed by mid-September. The work undertaken involved the diversion of 2,000m of drainage systems, 1,800m of gas pipes, 1,500m of water pipes and 15,000m of communications and power ducting. Additionally, 210 manholes and chambers had to be built. STOCK
Modifications
The programme to extend the Red Line tram fleet from 30m to 40m length was
completed on 26 May. The occasion was marked by a ceremony at the Red Cow Depot
at which the Minister for Transport ‘launched’
3020, the final tram to be lengthened. Repair
& Maintenance Contract On 17 June the RPA
awarded Alstom
Copyright © 2008 by Irish
Railway Record Society Limited
|