During
the initial design programme for the extension of the M1 motorway, the
National Roads Authority approached Iarnród Éireann in 1997 and asked them
to carry out a feasibility study of a possible overbridge crossing of the new
road about two miles north of Dundalk. The site of the proposed crossing is
about half a mile west of the intersection of the original N1 Dublin to
Belfast road with the R173 Ballymascanlon to Carlingford road at milepost 563/4.
A
number of different types of construction were examined bearing in mind that a
long-term interruption of rail services was not an acceptable option to Iarnród
Éireann. The first one would be a traditional, in-situ bridge, which would
involve either a temporary or permanent diversion of the railway line. The
second was an off site constructed deck with in-situ support piers constructed
under the existing line while traffic was allowed to continue. Lastly another
proposal was to use the JMB Methodes patented bridge construction system,
which involved the building of a monolithic concrete deck, support piers and
raft foundation structure adjacent to the eventual bridge site and sliding it
into place during a short possession. The outcome of the study was that the
last mentioned method was considered to be the most suitable from a cost and
operational point of view and was, therefore, selected as the preferred
option.
The
construction system involved was devised by one Jean-Marie Beauthier, a French
engineer, in 1992 and patented by him using his company, JMB Methodes. The
idea was devised particularly for the replacement of existing railway under
bridges or new bridges, which were required to cross projected roads. The name
given to the system was ‘Autoripage’ and it had been used on a significant
number of projects prior to the Dundalk Western By-Pass. Messrs. VSL, which is
a large international French contracting company seem to have been involved in
most of the earliest projects on the continent, with an English company
Messrs. Osbornes being appointed for those in the UK. The bridge at Dundalk
was, at 7,500 tonnes, the largest up to that date but this has since been
surpassed in August of this year by one at Boissy, Ile-de-France, for RER line
A, which weighed in at 12,500 tonnes. Another example was recently completed
at Shortlands Junction in southeast London also in August of this year but
this one was only 4500 tonnes. It was, however, interesting in so far as it
involved two railway lines.
A
bridge agreement was finalised in October 2003 between Iarnród Éireann, the
National Roads Authority and Louth County Council setting out the legal
conditions for allowing the bridge to be constructed on railway property.
This, in turn, involved an agreement for the design and construction of the
new bridge between the NRA and Celtic Roads Group Ltd., who were the Public
Private Partnership company. The main contractor was Dundalk Joint Venture and
their sub-contractors consisted of design consultants, Mott McDonald EPO
together with the patent holder, JMB Methodes and their construction sub
contractor, VSL as well as the earth moving sub contractor, Logan Earth Moving
Ltd. Iarnród Éireann were supported by Roughan & O’Donovan
(structural), AGEC (geotechnical) and Geoffrey Osbournes Ltd (Autoripage
system). The design was completed in July 2004. Work commenced on site in
November 2004, with the possession scheduled for the Easter weekend in March
2005. This was an ambitious schedule considering the time of year and the
complexity of the work to be undertaken.