
Irish Railway Record
Society
Collapse
and Reconstruction of Malahide Viaduct
LIAM
MEAGHER, PROGRAMME MANAGER (STRUCTURES), IARNRÓD ÉIREANN
THE
INCIDENT
At about
18:30 on Friday 21 August 2009, two spans on the 12-span viaduct at Malahide
collapsed. The collapse of the structure was due to scouring of a pier by tidal
action.
The line
was immediately closed to rail services and placed under Engineer’s
possession. Following reconstruction works, possession was handed back at 18:00
on Friday 13 November, 12-weeks after the incident and the line was re-opened to
early morning traffic on Monday 16 November.
This paper
will describe: the actions taken immediately after the collapse; the initial
proposals for bridge reconstruction; how the uncovering of a previously written
paper changed the initial proposals; why the bridge failed; the development of
the final design; and execution of the works.
LOCATION
Malahide
Station is located nine miles north of Connolly Station, the terminal station on
the Dublin-Belfast line, and Malahide Viaduct is located half a mile north of
the station. The line is double track, the track comprising 54kg/m continuously
welded rails on concrete sleepers, and the maximum line speed is 90mph
(145km/h). The line is electrified from Connolly Station to Malahide Station and
the over-head line equipment (OHLE) extends beyond the station but stops short
of the southern abutment of the viaduct.
Trains are
controlled by colour light signals, and continuous automatic warning system
(CAWS) and train detection is by track circuits. The signalling is controlled
through solid state interlocking. Operationally the signalling is monitored and
controlled from a control panel at Central Traffic Control (CTC) at Connolly
Station.
The
viaduct and the approach causeways to the north and south of the bridge cross
the Broadmeadow Estuary at Malahide. The construction of the railway created an
inner estuary, measuring approximately 2-square miles in area, which retains
water permanently throughout the tidal cycle. The bridge has 12-spans, 8-spans
of 15.85m and 2-spans at each end of the viaduct of 12.25m, giving a total
length of 175.8m.
Broadmeadow
Estuary is protected by extensive environmental legislation. It is a candidate
site for designation as a Special Area of Conservation (SAC); it is also a
proposed site for designation as a National Heritage Area (NHA); it is
designated a Special Protection Area (SPA) site; and it is a designated site
under the Ramsar Wetlands Convention. Any works in that area consequently must
adhere to the environmental conservation requirements. A particular requirement
for the viaduct works was that the mud-flat exposure areas at the western end of
Broadmeadow estuary not be changed. This is to ensure that bird populations, in
particular winter migrating birds, are not diminished through loss of feeding
grounds. The mud-flat areas have a very gentle gradient towards deeper water
consequently small variations in water level have a significant impact on mud-flat
exposure areas.
IMMEDIATE
ACTIONS
Aerial
photographs taken by the Irish Coast Guard Service early on Saturday morning 22
August show the extent of the damage. The collapsed pier, Pier No. 4 counting
from the northern end, was completely washed away and the 12-precast beams
spanning on to the pier, six on each span Nos. 4 and 5, are seen to be collapsed
into the sea. During the course of the subsequent works, no trace was ever found
of the remnants of Pier No. 4. It is believed that it broke up on collapse and,
such was the force of the water, the masonry blocks were scattered a
considerable distance from the bridge.
On the
evening of the incident, a decision was taken that a main contractor and other
contractors could be engaged immediately under emergency procurement procedures
and the main contractor attended site that evening. Other contractors commenced
work over the next few days: for the provision of topographical surveys,
hydrographical surveys and bridge monitoring; the provision of Engineer-Divers
to inspect the bridge piers and scour damage; and the provision of mobile cranes
and piling equipment.
Within a
few days of the incident, an independent Geotechnical Consulting Engineer, Dr
Eric Farrell, was engaged to advise on all geotechnical matters; Dr Eamon
McKeogh, Hydrology Dept., University College Cork (UCC), was engaged to advise
in regard to the hydrology of Malahide; his colleague from UCC, Mr Michael
O’Sullivan, was engaged to advise in regard to the environmental issues; and
Roughan O’Donovan Consulting Engineers were engaged to carry out a peer review
of all design proposals prepared by Iarnród Éireann directly and the
geotechnical and hydraulic designs carried out by the other independent
Consultants.
It was
known by the Engineers who attended site on the evening of the collapse that the
deck comprised of precast post-tensioned beams had been renewed sometime in the
late 1960s and that the beams were simply supported and were not attached to
each other. There was ballasted track over the viaduct and each track was
supported by two beams. There were also two outer beams incorporating ballast
retaining upstands and steel handrails.
Former US
Secretary of Defence Donald Rumsfeld is quoted as stating ‘There
are known knowns; there are things we know we know. We also know there are known
unknowns; that is to say we know there are some things we do not know. But there
are also unknown unknowns; the ones we don’t know we don’t know’. In
the months following this incident, it became clear that other railway
administrations do not always have construction details of their bridges, in
particular bridge foundation depth and foundation construction details. In the
first few days after the incident, Iarnród Éireann engineers were operating in
a position of ‘unknown unknowns’; the remaining piers and bridge spans
appeared to be in a robust and stable condition and it was assumed at that time
that all piers and abutments were supported on solid foundations bearing on good
ground or rock.
Initial
thoughts were that the reconstruction activities should be carried out working
from the existing bridge, with two independent work sites; one on span No. 3, to
the north of the collapsed spans; and the other on span No. 6, to the south of
the collapsed spans. This was to avoid marine works which it was thought would
have necessitated specialist equipment with possible delays in procuring a
suitable contractor. It was also thought that marine based works would take
considerably longer to complete.
The
initial design concept was that 4 No. pile clusters would be installed alongside
each of spans Nos. 3 and 6 in order to support crane out-riggers for cranes
positioned on these spans. The cranes were initially to remove the suspended
track and the collapsed beams. At that stage piling rigs were to be used to
install bored-pile foundations to the front of Pier Nos. 3 and 5. The intention
was that the collapsed Pier No. 4 would not be replaced but that precast
pre-stressed beams with a concrete cast in-situ deck would span from Pier No. 3
to Pier No. 5.
Given the
importance of the Dublin-Belfast line, a significant element of the national
transport infrastructure, there was an expectation at the highest levels that
the line would be re-opened as soon as possible. Having discussed the initial
design concept with the main contractor, the Department of Transport was advised
on the day after the incident that the line would be re-opened within three
months.
In
the days following the incident monitoring equipment was installed to detect
possible movement and/or settlement at any point on the entire viaduct. Survey
monitoring targets were attached to each end of the outer beams on each
remaining span. The x, y and z position of each target was measured daily to
determine the three dimensional movement at the top of every pier and abutment.
Tilt monitors were installed at Pier Nos. 2, 3, 5 and 6 to measure north-south
and east-west rotations and vibration monitors were installed at Pier Nos. 3 and
5 and read-outs were available continuously.
Engineer-Divers
commenced an underwater survey on Sunday 23 August. Their first
priority was to survey the remaining piers, Pier Nos. 1 to 3 and 5 to 11, and
the abutments for scour damage. The second priority was to determine the depth
of scour erosion between Pier Nos. 3 and 5.
On Monday
morning, the Engineer-Divers were able to confirm that there was no immediate
risk to the remaining piers and abutments. Some scouring had occurred to the
east of spans 9 and 10 but the scour did not pose an immediate risk to Pier Nos.
8, 9 and 10. They also reported that almost 66%
of the entire ebb flow, then in spring tide, was passing between Pier Nos. 3 and
5 with a velocity of approximately 4.5 to 5.0 m/sec.
SITE
ACCESS
A problem
familiar to all railway infrastructure staff is that of access and in particular
access to incident sites. In this case access to the southern abutment was
easily achieved by arrangement with the owners of the adjacent Malahide Marina
and boat-yard, located on the Up side of the line beside the southern abutment.
To the north of the viaduct, public road access was approximately 2 km from the
bridge and necessitated access through private lands. It was possible to make
use of an access road previously constructed across these lands to facilitate
previous railway works.
By Monday
24 August, ballast was being drawn in to the site to create a ballast bed over
the track in anticipation of bringing in heavy-lift cranes and piling rigs.
HISTORIC
PAPER
On Monday
evening a copy of a paper published in JOURNAL No. 143 of the Irish Railway
Record Society, October 2000, written by Mr Oliver Doyle, Manager Resources
& Central Traffic Control at that time, was turned up. It described the
history of the viaduct and contained information which was of considerable
significance to the works then planned to commence on site.
When
constructing the railway line from Dublin to Belfast, a very direct route out of
Dublin city had been taken, hugging the coast as far as Laytown Station. To
achieve this route it was necessary to construct causeways across a number of
estuaries, including Fairview, Malahide and Rogerstown.
The map
extract, page 384 above, shows the causeway at Malahide. The inner estuary to
the west of the railway measures approximately 1-mile north-south and 2-miles
east-west. Prior to the construction of the railway, the tidal waters flowed in
and out of the estuary unimpeded. With the construction of the causeway and
viaduct, all of the flow was concentrated into a narrow channel.
The
original viaduct was constructed in 1843. It had 11 spans of 52 feet (15.85m)
with a total length of 572 feet (174.4m). The abutments were of masonry
construction, supported on timber piles. The piers and bridge deck were of
timber construction also supported on timber piles.
The
obstruction to the natural tidal flow caused a very powerful current through the
bridge spans and within a very short time after the railway coming into
operation, it became clear that erosion of the soil into which the timber piles
were driven was causing settlement. To address the problem approximately 90,000
tons of stone was placed beneath the bridge, encapsulating the timber piers. The
stone formed a rip-rap weir, extending between the north and south abutments.
The purpose of this weir was twofold, to protect the seabed against further
erosion and to reduce the volume and velocity of water flowing through the
bridge spans. The weir was 130 feet (40m) wide at its base and 30 feet (9.2m)
high with steeply sloping sides.
The
settlement of the deck was dealt with by packing up the rails, by up to 3 feet
(0.92m) in places. By 1859 however it became clear that the timber was suffering
decay and a decision was taken to renew the bridge. The construction
requirements were quite onerous in that it was necessary not to disrupt rail
traffic during the course of the works.
Having
considered a number of options, it was decided that the new structure would have
wrought iron spans supported on masonry piers. The piers were to be supported
directly on top of the stone weir. Given the concerns in regard to the condition
and stability of the original timber piles, it was decided not to disturb the
original piers and to retain the original abutments. It was also decided to
minimise obstruction of the waterway and to construct the bridge in three
stages: to construct three piers at the northern end, renew the first three
spans on both the up and down lines, take down the original piers for those
spans and clear and level the waterway; then construct four more piers and spans
in a similar manner; and finally complete the last four piers and spans.
One of the
options that had been considered was to use cast-iron girders with
cross-spanning brick arches (jack-arch construction) and having a track laid on
ballast. It was known that the cast-iron would have been more durable in the
marine environment; however the board of directors were mindful of the risk that
cast-iron could fail suddenly with catastrophic consequences and it was directed
that a wrought iron structure be used instead.
It is
worth noting how the piers were constructed. The piers were initially built-up
dry at Dublin Terminus, now known as Connolly Station. Each stone was marked up,
the piers disassembled and the stone delivered to site. There the piers were
again built-up dry alongside the causeway, but this time the piers were built
upside down.
The weir
had to be prepared in order to receive the new piers. At low tide, the water in
the outer estuary can fall to a level approximately 3.0m below top of weir
level. It was possible to restrict the flow of water from the inner estuary by
damming one span at a time. Sections of track were laid on top of the weir,
spanning from pier to pier, having convex plan-curvature towards the western
face, filled with sods and pitched with stone on both faces. While the dam did
not prevent all of the water from passing through it allowed the masons to
construct the pier foundations under a shallow depth of water.
To prepare
the pier formation level, loose stones were first removed to a depth of 15
inches (0.45m) below the general level. Around the hole thus formed round stones
were laid on edge without cement. Then stone fragments, gravel and iron turnings
were placed in the hole and rammed with a 5 cwt (260kg) block of iron. When a
firm level base was achieved, a framework of rails, having the profile of the
base of the pier, was laid down and adjusted to the correct level using blocks
of stone, the intermediate rails being packed with flat stones. The interior
space was then filled with flat stones and grouted-in. At this stage, the first
layer of ashlar was laid and the remaining stonework for the pier carried on
from there. It only took 5 months from the laying of the first stone on the
first pier to the completion of the last pier, during which time seven deck
spans had also been completed.
The
information contained in the historic paper was of significant importance to the
Engineers in drawing attention to facts not known to them at that time; that the
bridge piers and abutments were founded directly on top of the weir.
THE
NEW PRIORITY
Diving
conditions during the spring tides were particularly hazardous between Pier Nos.
3 and 5 because of the potential for instability of the fallen beams and the
velocity of water flowing around them. It was necessary to restrict diving in
that area to that brief period between tides when the incoming tide just reached
the same level as the out-flowing waters.
On Tuesday
morning, the Engineer-Divers reported on the depth of scour between Pier Nos. 3
and 5. The maximum scour was measured to be approximately 3.6m below the general
top of weir level and occurred where Pier No. 4 had been.
Knowing
then the pier construction details and the importance of the weir to the
stability of the entire structure, it was clear that unless the weir could be
secured against further erosion and scour effects, there was a significant risk
that the scour hole at Pier No. 4 would spread and undermine Pier Nos. 3 and 5
and potentially undermine others as well.
At that
time, there was only a narrow strip of weir remaining intact between the scour
hole and the inner estuary. There was concern that a full breach of the weir,
with a scoured channel running from inner to outer estuary, could cause
significant environmental damage because tidal flows would be dramatically
changed; the ebb tide would flow from the inner estuary for a longer period; the
head of water would be much higher; and consequently further erosion and scour
could develop very quickly.
The
primary concern at that stage switched from reconstructing the bridge to
stabilising the weir and all efforts were directed to that end. The Hydrology
Dept., University College Cork was engaged with a first priority to advise in
regard to plugging the scour and reducing the volume and velocity of water
discharging between Pier Nos. 3 and 5. It was decided to construct a haul road
on the eastern side of the viaduct, with access through Malahide Marina, in
order to fill the scour hole with stone.
THE
WEIR
The haul
road was constructed on top of the eastern side of the weir with a top surface
about 500mm higher than the general weir level. It was recognised that the weir
would need to be substantially strengthened on both the eastern and western
sides and a total of 25,000 tonnes of stone was laid to construct the haul road.
The contractor placed 1.2m diameter steel pipes east-west in the middle of each
span, a metre below haul road level, to assist in accommodating tidal flows.
Heavy boulders, 15 to 20-tonne weight, were placed along the eastern slope of
the weir with smaller boulders and stone placed on top. Special permission was
granted by the local authorities and the Gardaí (police) to permit the
contracted quarries to operate continuously and for the boulders and stone to be
delivered to site throughout day-light hours seven days a week. By Sunday 30,
the flow through Pier Nos. 3 and 5 had been arrested. The haul road acted as a
buffer, preventing the water from flowing through the scour hole, and the high
tide flow over the haul road was seen to be equalised through each span.
TIDES
The high
and low spring tides extend from +2.22m OD to -2.38m OD, a range of 4.6m. The
weir level prior to collapse was approximately +0.5m OD.
Spring
tides at high water cause a significant volume of water to enter the inner
estuary where it is retained. On the ebb tide, the water in the outer estuary
falls below to a low water level almost 3.0m below top of weir level. The high
water retained in the inner estuary cannot fully discharge before the tide turns
again and the incoming tide replenishes the inner estuary once more. It was
found that during spring tides, there was always a flow of water across the weir
to a depth of at least 600mm. In order to allow works to continue unimpeded
during spring tides, it was necessary for elevated stone platforms to be formed
to allow construction equipment operate in dry conditions.
The high
water during neap tides sometimes only exceeds the weir height by approximately
400mm. This causes a lower volume of water to enter the inner estuary and the
water retained can fully discharge to top of weir level during the ebb tide
before the tide turns and the incoming tide replenishes the inner estuary once
more. Some of the works had to be restricted to neap tide periods: pouring
concrete to the pile cap on Pier No. 4; installing the micro-piles; and some
other works.
THE
CAUSE OF THE COLLAPSE
On Sunday
23 August, a chance encounter with a Scout Leader of the Malahide Sea Scouts led
to copies of their photographic records of flow conditions through the weir
being made available to the Engineers. The Sea Scouts have for many years used
the weir as a training ground on their kayak courses. The ebb flow over the weir
created conditions suitable for training those who then progressed on to white
water rapids elsewhere. The Scout Leaders had often taken photographs of
participants and had thereby captured the weir flow conditions in the
background.
It is now
clear that general erosion had been taking place for some time over the entire
length of the weir. In the past stone had been placed on the weir following
storms but no replenishment had taken place since the mid-1990s. It appears that
the top level of the weir had been slowly eroding with a loss of stone over
time.
From the
Sea Scout records we could establish that the scour which caused the collapse of
Pier No. 4 was not evident in March 2009. By July however it is clear that spans
Nos. 4 and 5 had suffered significant scouring with deep channels having been
formed in the middle of each span. As the erosion developed these channels
became deeper and wider and consequently more water was drawn into the channels
exacerbating the problem. In the days leading up to the collapse, more stones
were scoured away, deepening the channel until finally the pier foundation was
undermined and the pier collapsed.
The sketch
by the Engineer-Divers shows the development of two areas of scour to the east
of spans 9 and 10. The eastern crest of the weir was locally eroded away
progressively until in plan the weir crest was ‘horse-shoe’ shaped. On the
ebb flow, the water passing over the weir crest gathers momentum and the flow
becomes turbulent. This can cause erosion along the crest and the side slopes of
the weir. In the case of the ‘horse-shoe’ shaped crest the turbulence occurs
within the weir, around the ‘horse-shoe’ crest, and causes erosion which
draws more water into that area exacerbating the problem.
In spans
Nos. 4 and 5 similar erosion had occurred but in that case the weir crest was
eroded away until the ‘horse-shoe’ shaped crest progressively grew and
eroded the weir directly beneath the bridge and then beyond the western edge of
the bridge until it had almost broken a channel through the entire width of the
weir. At that stage the increase in water volume and velocity caused
progressively more destructive forces to undermine the weir and ultimately
undermine the pier foundation causing the pier to collapse.
In
1967/68, the wrought iron spans were renewed. At that time the construction
details of the bridge were known and the importance of the weir was well
understood. When re-constructing the wrought iron spans it was recognised that
the previous practice of removing deck timbers and unloading stone from ballast
wagons to replenish the weir would no longer be possible and would be difficult
by alternative means. A decision was taken to grout the top level of stone in
the weir to a depth of 1.5m over the entire length of the weir. The grouting was
successfully carried out and the weir was stable for many years. Over time
however, the grout broke down and was itself eroded. Unfortunately having
‘fixed’ the problem, the knowledge of the weir’s importance faded, and
with the passage of time there was a loss of corporate memory and the structural
importance of the weir was not appreciated. This was found to be the underlying
cause of the incident.
THE
WORKS
Having
constructed the haul road and equalised the flow through each span, it was
realised that despite the initial reluctance to ‘get our feet wet’, a new
opportunity presented itself. It was realised that cranes could be brought along
the haul road to remove the collapsed bridge beams, and other works, including
the re-construction of Pier No. 4, could now be carried out relatively easily.
It was decided to abandon the design work then underway and develop a new
design, to re-instate Pier No. 4 and construct two new spans in a style similar
to the original but using precast pre-stressed beams and an in-situ deck.
Tracked
crawler cranes were used to tandem lift-out the tracks which were then cut into
15m lengths and placed on span 3, immediately behind Pier No. 3. Then the
collapsed beams were removed and transported to the railway gantry-yard in
Mullingar. The signalling cables on the up side of the line were-routed to the
down side and all were supported by catenary wire spanning from Pier No. 3 to
Pier No. 5. The cables remained in use for the duration of the works. Having
cleared the site, the scoured hole was then filled with 150mm stone, that size
being chosen in order to facilitate the installation of driven steel piles.
A second
haul road was constructed from Bissets Strand Road, alongside the western side
of the southern causeway, as far as the southern abutment. This facilitated the
importation of stone to be laid on the western side of the weir for
strengthening purposes. The importation of stone from the northern side of the
bridge was discontinued once the decision had been taken that Pier No. 4 could
be re-instated, working from the haul road on the eastern side of the bridge.
In
Mullingar, six of the eight larger bridge beams were load tested to confirm
their load carrying capacity. Having completed the load tests, the beams were
cut into sections in order to examine the condition of the post-tensioning
tendons and to confirm that the grouting had completely filled the tendon ducts.
The tests confirmed that the beams can safely take the loads to which they are
subjected to in service. The level of corrosion on the tendons was quite small
and no loss of grout was observed.
No site
investigations had been carried out before completion of the haul road, but
because there was little time available, it was decided to drive 273mm diameter
tubular piles for the foundation of Pier No. 4 and thereby determine the depth
to rock. Fortunately the main contractor was at that time constructing the
Clonmore Bridge on the M52 Link Road near Mullingar where
such piles were being used and a sufficient number was immediately
made available for this project. 22 No. piles were driven at Pier No. 4 and rock
was found at approximately 25m below top of weir level.
Site
investigations did proceed as soon as the haul road was completed. Boreholes
were taken to the east and west of each pier and thereby informed decisions in
regard to the piling and micro-piling.
A decision
was taken that while the works were underway, micro-piles would be installed
below all the other piers and the abutments. 15 No. raking micro-piles, using
50mm diameter Dywidag hollow bars, were installed at every pier, and an
additional 8 No. vertical piles, using 75mm diameter Dywidag hollow bars, were
installed at Pier Nos. 3 and 5. The micro-piles were designed as friction piles
and were not taken to rock level but were terminated approximately 15m below top
of weir level. These micro-piles do not carry the entire applied load but were
installed to give supplemental support to the piers.
When the
micro-piling started and the vertical piles were being installed at Pier No. 5,
it was noted that some settlement was taking place. At that time, the piling
contractor was drilling a steel casing through the stone rip-rap beneath the
pier, the rig sitting on the bridge deck and the drill passing through vertical
holes previously cored down through the masonry pier. When the figures showed
that there had been settlement of 20mm at the eastern side of the pier and 7mm
on the western side, a cross-level of 13mm, the micro-piling was stopped. It was
concluded that the method of installing the steel casing by percussive drilling,
using high air pressure at the toe of the casing to drive the drill head, had
led to the disturbance of the sand/silt layer beneath the weir rip-rap which
caused voids to develop, with the consequent effect of pier settlement.
At that
stage the installation of the 76mm diameter Dywidag hollow bar was to be carried
out in three stages: core a 200 mm diameter vertical hole through the masonry
pier; drill and install a 168mm diameter steel casing from the base of the
masonry pier through the stone rip-rap to the sub-strata sand/silt layer; and
drill the 76mm diameter Dywidag hollow bar to the required depth and grout.
Following
consideration of the problem it was decided to stop the casing installation 1m
before the bottom of the rip-rap layer. At that stage the casing was filled with
grout which was allowed to permeate into the rip-rap and the underlying
sand/silt. The grout was then allowed to set overnight before the installation
of the 76mm diameter Dywidag hollow bar which was then drilled through the grout
and in to the sand/silt layer.
Subsequent
monitoring showed the process to have been successful.
Pier No. 4
was completed by the 9 October and the new spans were completed two weeks later.
The track was re-instated by the 10 November and all micro-piling was completed
by Wednesday 11 November.
At that
stage, load testing of the bridge was carried out over two days using an
071-class locomotive and laden Tara mines wagons with axle weights of 18.5
tonnes. It was found that the loading had no effect on the bridge piers and no
settlement occurred.
Possession
was handed back to the Operating Dept at 18:00 on Friday 13 November, twelve
weeks after the bridge collapse. Train testing of track circuits was carried out
over the weekend and trains were positioned for passenger services which
commenced on Monday morning 16 November.
Since the
line re-opened, further works have been carried out to strengthen the north east
causeway and finish off the weir. A total of 112,000 tonnes of stone, including
the 25,000 tonnes used to form the haul road, was used to widen and strengthen
the weir. The
top of the weir was profiled, with V-shaped channels formed between the piers
extending from the eastern to western crest. The effect of these channels is to
draw the main flow of turbulent water away from the piers and thereby further
mitigate the risk of scour at the piers.