“Note
that independently of the DART Underground Project, IÉ will be responsible for
the procurement and maintenance of any rolling stock required for the operation
of train services on DART Underground and the wider DART network and its drivers
will operate the rolling stock and its signallers will control the trains. Note
also that CIÉ will be responsible for obtaining the Railway Order and the
acquisition of permanent land required for the project.”
IÉ
commissioned UK consultants Colin Buchanan to provide a cost benefit analysis of
the proposed Dart Underground. They found that it would return benefits about
2.5 times greater than its cost.
In March,
it was reported that IÉ were deferring submission of the application for a
Railway Order for DART Underground from March until late June in order to
respond to issues raised by An Bord Pleanála at preplanning meetings. Issues
related to the detailed design and alignment of the route.
Earlier
this year CIÉ advised the NTA that the project completion date would be delayed
from 2015 to 2018 due to “a longer than expected planning and design
process.” The Minister for Transport only heard of this delay on Wednesday 5
May. He told the Dáil “I became aware of this statement around lunchtime ...
Although I met the board of CIÉ earlier this morning, this was not mentioned to
me. I am unaware of any change the company has proposed on this matter. If it
has decided off its own bat to re-order government priorities, it will be
hearing from me.” Until recently, CIÉ reported to the Department of Transport
on a monthly basis but now reports to the NTA. CIÉ said “Obviously there was
a breakdown in communication along the way, which we regret, but we reported
within the system that had been set up for us.”
CLONSILLA-NAVAN
Clonsilla-Pace
Work on installing track took place in the early part of the year. All materials
except rails were delivered by road. On 16 February, tamper 741 was packing
track between Clonsilla and Hansfield. On Wednesday 24 February, 077 arrived in
Dunboyne at 10:45 with the Long Welded Rail (LWR) train to drop rails between
Dunboyne and Pace. This was the first train in Dunboyne for 47 years, causing
quite a stir with the local population. It had earlier run round in Clonsilla
and propelled towards Dunboyne. The empty train departed Dunboyne for Portlaoise
at 13:00. At this time track was only installed on the down line through
Dunboyne. The up line was laid to Pace in the following week.
On
Wednesday 3 March, points and crossing tamper 751, was packing a newly installed
crossover just to the south of Pace station. On Saturday 6 March, tampers 741
and 751 were noted between the Royal Canal Bridge and Hansfield. On Wednesday 10
March, 087 worked the final LWR train to the Dunboyne branch dropping the last
of the welded rails at Pace station and the siding beyond it at the Navan end.
Next day, 087 worked the empty LWR train back to Portlaoise. A total of four LWR
trains visited the branch, two in December 2009 and the two noted above.
Track work
had been substantially completed by March, except for the second turnout at
Clonsilla. This will be installed before the new signalling is commissioned.
Clonsilla-Dunboyne-Pace is expected to re-open for traffic in the autumn.
Pace-Navan
In March, IÉ said work would start on preparing for a Railway Order for the
Pace-Navan section following allocation of €15.5m
in funding. IÉ said that the Railway Order would be made by mid-2011 with the
line scheduled for completion in 2015, subject to the phasing of funding.
WESTERN
RAIL CORRIDOR (WRC)
Ennis-Athenry
In late February, driver training was interrupted
for a period after damage was discovered to the Upper Fergus Bridge, north of
Ennis. Further work continued on the line. UB153 at Craughwell was stitched and
pointed. On 13/14 March, culverts UB97a, 101b and 105 were renewed. Crew
training continued throughout February and March. On Friday 4 February, 147+162
and 2701/02 were used between Ennis and Athenry. In March, training included
operating to the timetable schedules. These proved very generous with trains
‘waiting for time’.
On Monday
29 March, the line was officially re-opened to passenger services. A special
train consisting of 2709/2710 + 2708/2707 operated from Limerick to Galway at
10:30 with the Minister for Transport, four other Government Ministers, eight
Mayors, politicians, railway officials and guests. It stopped at all stations en
route where large crowds welcomed the re-opening of the line. It returned to
Limerick at 15:45. A special train, 3-car 22012, operated at 16:05 from Galway
to Dublin Heuston to return guests to Dublin.
The
Minister for Transport said: "I believe this Western Corridor is
particularly important as it connects the two gateways of Limerick and Galway
with the hub of Ennis. Long-term strategic planning is even more important today
to ensure that we learn from the lessons of the past. The next step will be for
Iarnród Éireann to undertake a detailed evaluation of phases two and three
with a view to arriving at precise costs to undertake the works. I know there
have been calls for work on these phases to commence immediately. However, we
all have to face the reality that the current funding environment is very
difficult and it will not be possible to progress all projects in Transport 21
in accordance with the ambitious timescale envisaged at its launch."
There was
some criticism of the slow journey time, which is about 30 minutes slower that
the existing road and will be even slower when a new motorway opens. The fastest
journey time of 58 minutes between Ennis and Athenry compares with 55 minutes in
1963 on jointed track. The line speed is 60-mph, but there are numerable speed
restrictions associated with sighting for unattended level crossings. There were
143 crossings, but 102 have been closed with 14 more planned by end of year.
The
project represents an investment of €106m,
covering new track, bridges (over 100 repaired and improved), signals, level
crossings and stations at Sixmilebridge, Gort, Ardrahan and Craughwell. Gort has
two 90m long platforms connected by a wheelchair accessible footbridge, while
the other stations each have a single 90m platform. All the stations are
equipped with ticket vending machines, CCTV and car parking. There was an
indication of the possible provision of stations at Oranmore and Crusheen at the
re-opening ceremony.
Timetabled
services began next day, with 5 trains each way per weekday and four on a
Sunday. Early indications were that traffic was good and the two-car 2700-class
was inadequate on many occasions and had to be replaced by a four-car set. The
09:35 Limerick-Galway and 17:25 Galway–Limerick are particularly good loaders.
On Tuesday 6 April, there were more than 230 passengers departing Galway on the
17:25 Galway-Limerick. On Thursday 22 April, there were 107 passengers departing
Galway in the two-car set on the 17:25 Galway-Limerick. On Saturday, 24 April
there were approximately 165 passengers on the four-car 17:25 Galway-Limerick
departing Galway, with about 120 continuing onwards from Athenry. This was much
more than on the 15:30 Dublin-Galway, which arrived into Athenry shortly
afterwards.
On 30
April, IÉ issued a statement “The first month’s operations have exceeded
expectations, with significant demand experienced from day one. The 16,000
passenger journeys recorded are on top of the existing 14,400 monthly journeys
on the Limerick-Ennis service, meaning the through route has seen over 30,000
passenger journeys in its first month... This is a strong and encouraging start
for this new service. While the initial interest was a great start, we are now
seeing daily demand being sustained. There is little doubt that as summer
approaches, new demand – in the form of domestic and overseas tourists –
will also see new rail customers taking to the line. It is clear that the
support which existed from the community for this line to reopen is translating
into passenger demand.”
Limerick-Ennis
Dr Martin Mansergh, Minister of State at the
Department of Finance with special responsibility for the Office of Public
Works, advised that the OPW's environmental consultants for the Ennis Flood
Relief Scheme were requested to submit a proposal for a flood study of the area
at Ballycar. The Minister said that “A proposal and quotation to undertake a
flood alleviation study of the flooding at Ballycar was subsequently received
from the consultants and that the OPW have referred the consultant's study
proposals to IÉ for their consideration”.
IÉ
subsequently told Clare County Council that funding had been made available by
the Department of Transport for a study to see if flooding can be prevented at
Ballycar, but that cost will be a considerable factor in any decision on what
will be done.
Future
In April IÉ released a press statement “Further
investment is planned for the Western Rail Corridor, including: