|
<
Irish Railway Record Society Journal
170 - LUAS SYSTEM
EXTENSIONS
Line
A1 (Belgard-Citywest) Cookstown Rd has been realigned at its junction
with Cookstown Way as part of the Embankment Rd extension scheme and in
preparation for the construction of Line A1. Site clearance work is progressing
along the length of the alignment. The
RPA is currently procuring contractors for its element of the project works. Line
B1 (Sandyford-Bride’s Glen) The additional sidings at Sandyford
Depot are complete and are in use. There are three new through sidings, while
the former stub siding at the northern boundary of the site has been converted
to a through siding. The total length of sidings has increased from 600m to
1,600m. Area
13 (Sandyford-Murphystown Rd) The inbound platform at Sandyford is to
become an island platform with a new track being laid between it and the road.
Inbound trams will normally use the new track, while outbound services will stop
at the existing outbound platform. The centre track, the existing inbound line,
will become a bi-directional line. The
junction connecting the existing line between the Sandyford stop and the depot
with the B1 extension has been installed. It consists of a crossover just south
of the stop connecting the outbound track to the centre track and then a facing
turnout to the outbound track on the extension. On the inbound track there is a
crossover south of Sandyford stop allowing trams from the extension go either to
the new inbound platform or to the centre track. The new inbound track will
connect to the existing line just north of platform. The
line from the junction at Sandyford to the top of the Brewery Rd Bridge has been
completed and overhead line equipment (OHLE) support masts have been erected.
With the exception of a short section through the site of the Central Park stop,
track laying is complete along the southern edge of the Central Park site and
over the bridge across the M50 adjacent to the Leopardstown interchange. Work
on the underground electrical sub-station at Glencairn is progressing steadily. Area
14 (Murphystown Rd-Ballyogan Wood) A new boundary wall, separating
the alignment from Glencairn Heath has been completed. Track laying alongside
Ballyogan Rd, between Glencairn Crescent and Ballyogan Wood is largely complete
and the erection of OHLE support masts is underway. The structure of the
electrical sub-station at Leopardstown Abbey is complete. Platforms
construction at The Gallops and Leopardstown Valley stops is well advanced. Area 15 (Ballyogan Wood-Bride’s Glen)
Track and OHLE masts have been installed across the M50 bridge adjacent to the
Carrickmines interchange. Trackbed works are continuing from the eastern end of
the bridge to the Carrickmines stop. Track
laying has been completed from just south of the Carrickmines stop to Bride’s
Glen. Erection of OHLE support masts is continuing. Work at the Brennanstown and
Laughanstown stops is well advanced, while at Ballyogan Wood, Racecourse,
Carrickmines, Cherrywood and Bride’s Glen good progress is being made. Line BXD (St Stephen’s Green-Broombridge)
At its meeting on 13 July, An Bord Pleanála considered the Inspector's report
and other submissions in respect of Dublin City Council's application for
planning approval for the proposed Marlborough Street Public Transport Priority
Bridge linking Eden Quay at Marlborough St with Burgh Quay at Hawkins St. The
Bord was of the opinion that the bridge, not having a significant adverse effect
on the environment, would be in accordance with the proper planning and
sustainable development of the area and approved the development. However,
the Department of Transport, which will fund the project, said work on the new
bridge would only begin once Metro North gets planning permission and the
Cabinet decides to approve the multi-billion euro system. Line C1 (Connolly Station-Point Depot)
Good progress has been made over recent months, with a number of significant
milestones being achieved. Area 16 (Store St/Connolly-Mayor Sq)
Work on the delta junction at Harbourmaster Pl was completed by the end of July.
On two Sundays, 19 and 26 July, services on the Red Line were suspended between
Abbey St and Connolly until 09:15 for the erection of OHLE support poles at the
junction. Over the August Bank Holiday weekend the line between Abbey St and
Connolly was closed from end of services on Friday 31 July until start of
services on the Tuesday 4 August. This was to allow the installation of the OHLE
contact wire on the two new sides of the delta junction and for a short distance
into Harbourmaster place. From 1 August all OHLE contact wires installed on Line
C1 are considered to be live. Track
laying is progressing well through the area, By early August just two short
sections of the eastbound line had to be completed. The erection of OHLE support
poles and head span wires was well advanced. Construction of the westbound
platform at the George’s Dock stop is well advanced and the installation of
platform furniture has commenced. Area 17 (Mayor Sq-Point Depot) Work
on the stop at Mayor Sq is progressing apace with surfacing work underway.
Platform construction and fitting out works are also well advanced at the
Spencer Dock and Point stops. Track laying is complete and OHLE support poles
and head span wires/cantilevers have been erected along much of this part of the
line. Installation of the contact wire has started at the Point Stop. Spencer Dock Bridge The
construction of the bridge over Spencer Dock proved to be a complex undertaking.
Firstly, the Royal Canal was pumped dry to facilitate the construction of 72
foundation piles and the bridge's two central piers. Temporary falsework was
also constructed on the bed of the canal to support the formwork used to
construct the bridge deck. The formwork for the underside of the bridge deck
consisted of a carefully assembled arrangement of 250 individually profiled
expanded polystyrene blocks, which, when assembled allowed the bridge's
undulating curved surface be formed. In
September 2008, with all the blocks and steel reinforcement in place, the bridge
spine was cast using 80 trucks of concrete. These were poured in one day,
resulting in a smooth finish on the underside of the bridge deck. To give the
bridge its strength, 500 ‘post tensioning’ steel cables were fixed into the
bridge deck. After
the bridge's spine had been cast, the footpaths and viewing galleries were
constructed as 28 individual reinforced structural concrete elements. When all
the concrete in the bridge deck had cured, the 500 steel cables were tensioned
and grouted. The parapet system on the bridge is made up out of 34 unique
precast units, which were manufactured from specially designed individual
expanded polystyrene moulds. All the formwork was milled directly from 3D
parametric computer models. To date, this innovative use of cut polystyrene is
the largest application of the material to be used in this way. The light
coloured finish of the concrete provides high visibility against the dark water
of the canal and at night the structure will be lit from below. The
installation of the track proved to be particularly challenging. The four rails
were suspended from special frames to allow the completion of reinforced
concrete deck around the track. A 'floating track' system was used across the
bridge, in which the rails were separated from the bridge structure by a special
rubber mat system to minimise noise and vibration impacts. Finally the bridge
received a special surfacing layer whose main component is special stone
aggregate material called carborundum, which has reflective properties that
sparkle in the sunlight. There
will be no OHLE support poles on the bridge. Instead the contact wires will be
suspended from span wires, which in turn are attached to four support poles
positioned on the canal banks at each corner of the bridge. The
bridge was opened to westbound traffic on 16 June. STOCK
New Trams Delivery of new Type 402
trams to Sandyford depot is on-going: No.
Delivered 5003.............
22 May 5004............
12 June 5005...............
6 July 5006.............
24 July 5007..........
3 August 5008.........
10 August Trial
running and driver training is continuing. It is planned that the first of the
new trams will enter traffic during September. Once a sufficient level of
in-service reliability has been achieved the transfer of Type 401 trams
(4001-14) to the Red Line will commence. IKEA Trams 3025 on the Red Line and
4014 on the Green Line are carrying internal advertising, including new seat
covers, for IKEA whose first store in the Republic opened on 27 July. TENDERS Park+Ride The RPA has sought
tenders from companies wishing to operate Park+Ride sites on both the existing
lines and on the extensions to Saggart and Bride’s Glen
Copyright © 2009 by Irish
Railway Record Society Limited
|