
Irish Railway Record
Society
Journal 169 - Infrastructure
CLONSILLA-NAVAN
Clonsilla-Pace Work on the Clonsilla-Pace has commenced and
earthmovers have cleared the line. Work then started on bridges:
·
UB284 at
610m Royal Canal – preparatory work for a new bridge span
·
OB286 at
1,689m Barnhill Road Bridge -Containment/strengthening measures only. The road
across the bridge was closed and a new temporary road was brought into use
directly across the trackbed. Cable trunking was laid in the approach ramps to
the bridge
·
OB286a at
2,450m Hilltown Stud Accommodation Bridge – a new private crossing bridge was
under construction
·
OB287 at
3,050m Stirling Road Bridge - replace deck and provide containment. The road was
closed and traffic diverted.
On 21 May,
the Taoiseach said ‘Irish Rail is making good progress constructing the
Clonsilla to Dunboyne section and it remains on target to open for services in
autumn next year’.
Pace-Navan
The Taoiseach said: ‘Irish Rail recently submitted the feasibility study to
Government. It examined two possible routes in great detail - an option A which
runs along the original railway alignment and an option B which is a new route
to the east of Dunshaughlin. On the basis of the detailed analysis carried out
by Irish Rail the preferred option has emerged as option A or the original
railway alignment’.
‘The
chosen option A of the original railway alignment had a number of advantages as
it: provides a better economic rate of return for the State's investment; can be
provided at significantly lower cost; was the preferred option from the public
consultation carried out by Irish Rail - with over 80% indicating a preference
for option A; has a shorter journey time to Dublin of 59 minutes as opposed to
62 minutes for option B.
‘On
the basis of this analysis we will now be asking Irish Rail to proceed with the
necessary preparations for a Railway Order application’.
CORK
- MIDLETON / COBH
All track
has now been laid between Glounthaune and Midleton. Concrete sleepers were
delivered by road and laid using road-rail equipment. Long Welded Rail (LWR)
trains operated from Portlaoise and most were hauled by 147+162. They visited
the line on Friday 9 January and on a snowy Tuesday 3 February they dropped rail
for the section between Waterrock level crossing and Midleton. The final LWR
train on Thursday 17 February dropped rail for the ‘dynamic loop’ at
Carrigtwohill. Ballast tamper 741 commenced working on the line on Monday 9
March. Four-barrier CCTV type level crossings were in place by March at
Waterrock and Mill Rd.
Station
work also progressed well. Platforms and fittings have been largely completed.
Disability access footbridges have been installed in Midleton and Carrigtwohill.
Of particular note is the fine job of restoring the former signalbox at
Midleton.
A new
€5m bridge OB409A at 166 miles 150 yards Cork-Cobh to replace level crossing
XC241 was craned into place during a line closure from 20:00 Holy Thursday 9
April to 10:00 on Holy Saturday (See JOURNAL 168). The new bridge is a ‘Bow
String’ type made of steel with a concrete deck. It is 30m long and weighs 240
tonnes. It was designed by Roughan O'Donovan Consulting and was pre-fabricated
by Thompsons of Carlow. The crane used was 600-tonne capacity and was situated
on the main N8 road, which was also closed. The crane took 16 hours to assemble
using other cranes.
Signalling
work continues on both Glounthaune-Midleton and Cork-Cobh lines. Signals on the
Glounthaune-Midleton line were lit but not in use by end of April. New equipment
buildings have been installed in Glounthaune and Cobh Stations to house
signalling equipment. Signal numbers on both lines will be prefixed CE (Cork
East).
KILDARE
ROUTE PROJECT
The
project nears completion with most work still taking place without interruptions
to services. Train cancellations were largely confined to late Saturday evening
and early Sunday morning trains as described in previous JOURNALS. Commissioning
of the new track and new signalling from Inchicore to Kildare is expected to
take place over a 6-month period, commencing this summer.
Ballast
tamper / dynamic track stabiliser 741 finished its work on the two new tracks
and was removed by temporarily slewing track at the Dublin end. It went to the
Glounthaune-Midleton line in March. The connections to existing up line at both
Inchicore and Hazelhatch ends were ready for installation and this will be done
in conjunction with commissioning of the new signalling.
The
new Newcastle-Celbridge Rd Bridge OB25 was opened and double track wide OB23
east of Hazelhatch & Celbridge station was demolished in February. It was
replaced by a new 4-track wide steel footbridge, which was lifted in to position
on Wednesday 8 April. This permitted the final sections of track to be laid east
of the station. West of the station, the new up fast and up slow tracks are laid
on standard ballast but over a concrete slab as it is a boggy area. In early
May, track was again temporarily slewed to allow tamper 743 access the new track
and it went to work in the Hazelhatch & Celbridge station area.
Hazelhatch
& Celbridge station itself was complete with new footbridge and booking
office in use in April. It was officially opened on Friday 8 May by the Minister
for Transport.
The
newly re-built Cloverhill Rd Bridge OB11 at Clondalkin re-opened on 15 April.
Most
signals are in place to Cherryville Junction. Signals numbers are prefixed HK
for Heuston-Kildare line.
WESTERN
RAIL CORRIDOR (WRC)
Ennis-Athenry
Track Re-laying
continued throughout the winter and spring. All track had been laid by April,
with the exception of a section between Tubber station and nearby Gortavogher
level crossing where pile driving was taking place during April. Welding of rail
had also just commenced. Track consists of UIC54 rail on concrete sleepers.
Engineering
trains have been routed via Ennis. Ennis yard was used as a base, but trains
were also based in the Ennis-Athenry section near the work site as required. A
ballast train of 15 wagons and two plough vans operated out of Crusheen using
locomotive 171 in March and 152 in April.
The main and
loop platforms tracks in Gort station were in place and lined by Easter.
Expansion joints were also in place.
Craughwell
Station
The 4-car long platform is just to the south of the former station buildings at
MP55. It features a single ‘bus shelter’, a concrete equipment room at one
end and a car park. The station was substantially complete by Easter, with the
exception of surfacing of the car park, lighting and CCTV security cameras.
Ardrahan
Station
The 4-car long platform is about 100m to the south of the former station and has
a new entrance from a different road. Its facilities are the same as Craughwell,
but it was effectively complete by Easter.
Gort
Station
Following granting of planning permission, work commenced in earnest on building
a new station immediately to the north of the former station. Two new platforms
were under construction. The former signal cabin has been demolished and the
water tower structure was being re-built back from the track. New concrete
equipment rooms have been constructed at the north end.
Ennis-Athenry
Signalling Alterations
took place at Athenry on 25 January to facilitate future passenger train
operation to/from the WRC. Both Dublin-Galway line down main and loop starting
signals were changed to a three-aspect red-yellow-green signal with a new
position 1 route indicator to read towards Ennis. Both locally controlled trap
points installed on the Ennis line during the Galway line Mini-CTC scheme were
removed. A new advance starter reading towards Ennis was installed, but only
displays a red aspect and a ‘Stop and Obtain Instructions from the Per Way
Inspector’ sign until final signalling commissioning in future. The branch
down direction is from Limerick towards Athenry. Three-aspect red-yellow-green
down branch outer home and home signals and a two-aspect down branch distant are
provided. Shunt signals read to/from the former cement siding and a new set of
trap points is installed on the siding.
Changes
have also been made to remove ‘approach control’ for trains arriving in the
station in both directions on the Dublin-Galway line. This involved lowering the
overall speed limit through the station to 50-mph, with a 40-mph speed limit
applying on diverging routes. The down outer home signal reading from Dublin was
changed from a three-aspect to a four-aspect signal. The up distant signal
reading from Galway was changed to a three aspect yellow-green-yellow signal.
Thus a train can get a clear run into a platform with the driver seeing a double
yellow on the distant, a yellow on the home and a red on the platform starter.
All above
changes were made to the Galway line SSI (Solid State Interlocking). By March,
the SSI and ECP (Emergency Control Panel) had been moved from Athlone relay room
at the former MGWR station to Athlone Level Crossing Control Centre at the
existing Athlone station. A new SSI has been added and the two SSIs making up
the Galway Line SSI are now designated as BEGY (Ballinasloe-Galway) and LKGT
(Limerick-Gort). However, the system is seen as a single system to the
signalman. These were under test in March.
Colour
light signals are in place at the new loop in Gort, in Ennis and at level
crossings. Radio masts and associated equipment rooms were also in place at
stations and along the line, including a new mast was at MP331/2.
On Sunday
26 April, all semaphore signals in Ennis were removed and new motorised points
and colour-light signalling were commissioned. New turnouts were installed at
both north and south ends of the loop and also to connect the yard.
From that
date the new SSI and Galway line ECP in Athlone were permanently switched in and
control Athlone-Galway, as well as Ennis station. The signalman in Ennis now
issues and collects the Ennis-Limerick staff from trains. He has a Starting
Signal Control Lock key, released from the staff instrument when the staff is
withdrawn. Gort station signals and points were also fully tested in preparation
for commission at a later date. The previous day, 141 operated as a signal test
locomotive at Gort. It operated to/from Athenry. On the Sunday, 152 operated as
a signal test locomotive at Ennis.
Full
details will be in a future JOURNAL.
Ennis-Athenry
Level Crossings To
facilitate upgrading of Kiltartan level crossing (XE136) at 44 miles 1,320 yards
from Automatic Half Barrier (AHB) to 4-barrier CCTV type, the main
Limerick-Galway N18 road was closed at nights between Sunday 1 and Monday 16
February. Traffic was diverted over the ‘old road’, which has a narrow
bridge over the line and a Stop-Go system was used. The new barrier crossing was
commissioned on Tuesday 24 February and is locally operated.
Similarly,
the N18 was closed at Ardrahan (XE156) at night from Tuesday 17 February to
Tuesday 3 March to allow conversion of the AHB to 4-barrier CCTV type. Traffic
diversions were also required. The new barrier crossing was commissioned on
Tuesday 10 March and is also locally operated for now.
Other
unattended crossings have been converted to 4-barrier CCTV type but were not
commissioned. These are Castletown (XE131) just south of Kiltartan at 44 miles
350 yards, Gortavogher (XE98) at 36 miles 183 yards south of Tubber and
Chipfield (XE71) at 30 miles 520 yards and Curravorin (XE61) at 25 miles 1,555
yards near Ennis.
Signals
and equipment room were in place at Craughwell AHB (XE194) on the main
Dublin-Galway N6 route, but it had not received its 4-barriers by mid April.
Ennis-Athenry
Bridges Significant
work has taken place to many overbridges. This includes pointing as required and
raising abutments. New anti-slip road surfaces have been installed as have crash
barriers on approaches on both sides. In April, IÉ applied for planning
permission to erect a new overbridge to allow closure of level crossings XE74
and XE75 at Cloonagowan, Crusheen. Underbridge renewal has been complete for
some time.
Limerick-Ennis
Atterbury
bridge, the single-track stone-arch overbridge at the Limerick end of the former
Sixmilebridge station, was partially demolished over the weekend of 27 March.
The top part of the arch was replaced with new concrete sections with increased
vertical clearance above rail height. This will facilitate the construction of a
new platform at the station. The Clare
Champion reported that IÉ plan an unmanned station with a platform, CCTV, a
ticket machine, station furniture, ‘signalling and additional trackwork’.
Programme
The
Minister for Transport told the WRC conference in May: ‘In September 2006 we
in Government made a decision in principle to support funding for the
development of Phase 2 of the Corridor between Athenry and Tuam. This approval
is subject to completion by IÉ of a fuller appraisal of this section. IÉ is
planning to conduct further studies in 2009 to ascertain more reliable costings
for Phases 2 and 3. I understand that they will also be looking at usage of
Phase 1 after its opening, and at its effect on overall patronage of public
transport in the area. The timescales for the delivery of Phases 2 and 3 are
under review in the light of the capital allocation available.