
Irish Railway Record
Society
Journal 168 - Infrastructure
CLONSILLA-NAVAN
Clonsilla-Pace Work on the Clonsilla-Pace section was officially launched on 10
November. The contract has been awarded to SIAC Construction, who is also
involved in constructing the adjacent M3 motorway. Services are scheduled to
commence in 2010.
Pace-Navan
As part of the route selection process for Phase 2, IÉ held public consultation
meetings on 13 and 14 January. IÉ proposals were an extension of 34km of
double-track from Pace, with stations at Dunshaughlin, Kilmessan, Navan Town
Centre, and a terminus ‘at the north edge of Navan’. Newspapers reported
that IÉ proposals for Navan were either constructing a station on the former
alignment about 1.8km from the town, with a Park & Ride facility or,
alternatively, a station 800m from the town, which would cost more due to land
acquisition costs.
Two route
options were proposed. The first was an alignment largely along the former MGWR
Clonsilla-Navan line, with minor alterations to avoid buildings constructed
since line closure, and a second which would run closer to the town of
Dunshaughlin.
CORK
- MIDLETON / COBH
The
complete line closure between Cork and Cobh from Tuesday 13 October to Friday 21
November (See JOURNAL 167) facilitated many engineering projects. These included
initial work on replacing level crossing XC241 with a new overbridge at 166
miles 150 yards. This user operated crossing has been subject to a 10-mph speed
restriction for many years due to poor sighting distances and the possibility of
vehicles stopping on the track while attempting to enter the busy N8 Dublin
road. A temporary A-type (Attended) level crossing has been installed nearby and
will be in place until May. The proposed new bridge is a very substantial
structure over both railway and adjacent road and required pile-driving for new
support structures in the River Lee. During the course of this work a section of
the river wall collapsed into the river on Wednesday 29 October, resulting in
closure of the road for the rest of the day and partial closure until next day.
A substantial base of rock has been placed in the river for construction of the
approach to the bridge. A large scaffold structure was located on the track to
facilitate construction of the abutments for this bridge.
During the
closure, temporary buffer stops were erected on the Cork side of Myrtlehill
level crossing. Four new barriers have been installed at the crossing and signal
posts were in place as part of preparation for its conversion to CCTV monitored
type.
Eleven
miles of cable ducting was installed along the line and the facing crossover and
turnout and traps connecting to North Esk freight yard were removed completely.
Little Island signal cabin was permanently closed and all signals removed. The
block sections are now Cork-Glounthaune-Cobh, with Glounthaune switched in as
required. A new Relocatable Equipment Building (REB) was installed at Myrtlehill
and another in Cobh on the up side opposite the former shed. Coastal protection
has been improved at various locations including near Slatty Viaduct.
Platforms
at Little Island, Glounthaune, Fota, Carrigaloe, Rushbooke and Cobh were
resurfaced, raised, new coping stones, drains, shelters and lighting installed.
A new down platform at Fota has been built on the Cobh side of the level
crossing opposite the up platform and the old one on the Cork side taken out of
use. All upgraded platforms are 92m long, which is shorter than some were
previously. Consequently, trains will now be limited to 4-car length.
On Monday 13 October, the Long Welded Rail (LWR) train hauled by
171+162 followed the 10:00 Cork-Cobh, arriving in Glounthaune at 10:20. It then
proceeded onto the Midleton line, ran around its train using the temporary
crossovers on the branch and propelled towards Carrigtwohill to off-load rail.
It departed Glounthaune at 17:30. On Wednesday 26 November, 073 worked the LWR train from Portlaoise
to the Midleton line. On Tuesday 2 December, 162+147 + LWR train
offloaded rails near Carrigtwohill.
By end of
November, long welded UIC54 rail on concrete sleepers had been installed from
Glounthaune to the new station in Carrigtwohill in the Glounthaune-Midleton.
Trackbed was in place to Waterrock level crossing (5 miles 25 chains), which
also had new barriers installed. Concrete sleepers for the project, from
Germany, were stockpiled at Cork Port and other locations such as Waterrock.
At
Carrigtwohill, both platforms and the structural steel for the lift shafts were
largely complete by the end of November. The car park was under construction.
Restoration of the former station building at Midleton was nearly complete and
fitting out was taking place. Both platforms were nearly complete and the former
signal cabin was undergoing refurbishment.
KILDARE
ROUTE PROJECT
Clondalkin
down platform was taken out of use on Saturday 27 September to allow for track
re-alignment. Clondalkin station closed completely on Sunday 12 October and was
replaced by a new station called ‘Clondalkin / Fonthill’, situated to the
south at MP43/4.
The latter station was officially opened next day by the Minister for Transport,
Mr Dempsey. The new station buildings are located above the platforms. The up
and down platforms were opened and are 175m long. Two additional platforms will
be brought into use on the new tracks at a later date. The
new station offers extra facilities, particularly improved accessibility for
mobility impaired passengers. It also has a 200 space car park. The old station
was subsequently demolished and removed.
Work on
installing the two additional tracks between Le Fanu Rd and Hazelhatch continued
with very little disruption to rail traffic. Line closures have normally been
confined to late Saturday night and early Sunday mornings.
During
an overnight possession on the weekend of 9 November, the existing up line was
temporarily slewed to allow ballast tamper / dynamic track stabiliser 741
position onto the new track. Ballast continued to be delivered by road and
deposited by road-rail vehicles. By end of 2008, two additional tracks had been
laid throughout with the exception of through the new platforms at Hazelhatch
and 741 was at work tamping and lining.
A
new long turnout on timber bearers (sleepers) from the proposed up slow to the
up fast was installed at the site of the former Cherry Orchard station near Le
Fanu Rd i.e. going from 4 to 3 tracks.
Replacement
OB11 at Cloverhill (Inchicore side of former Clondalkin station) was largely
complete, but there has been a delay in its re-opening due to property issues
associated with approach roads. It was due to re-open in November, but is now
expected to re-open in ‘late March or early April 2009’.
The
new station building at Kishoge was nearly finished at the end of 2008. It has 3
platforms; down slow, up slow and up fast.
At
Hazelhatch, a new turnout on concrete bearers was installed the Dublin end. At
the Sallins end, a new long turnout on wooden bearers (sleepers) from proposed
up fast to up slow was in place. The station building was also complete and was
being fitted out. The new bay platform is No. 3, the up slow is No. 4 and the up
fast is No. 5. The existing up platform No. 2 has also been extended at the
Sallins end and cut back at the Dublin end. The existing down platform No. 1 has
been extended at the Sallins end, but this extension was not in use at end of
2008. A substantial new footbridge with lifts for mobility impaired access has
been installed, but the original metal footbridge remained still in use.
WESTERN
RAIL CORRIDOR (WRC)
Ennis-Athenry
Re-laying continued through the autumn and winter using IÉs track
re-laying gantries and new long welded rail on concrete sleepers. IÉ also used
a mobile road-rail mounted flash-butt welding plant to weld rail on a two-week
trial. Deliveries of ballast and sleepers were generally by road to 4 - 5
stockpiles on the route, with ballast then loaded onto a train for spreading.
Rail was delivered by train from Portlaoise, more recently via Limerick and
Ennis. German manufactured concrete sleepers were road-hauled from Cork docks.
By end of 2008, re-laying was completed from Athenry (MP597/8)
to 32 miles 600 yards at Crusheen. Preparation was well in hand for re-laying
the remaining distance to Ennis (MP243/4
miles). All bridge excavations had also been completed. Platform construction
work was well advanced at Ardrahan and Craughwell.
In
January, local newspapers reported that an appeal against granting of planning
permission for the new station at Gort had been dropped following an agreement
between IÉ and Coen Holdings Ltd. It was also reported that Garraun had been
selected for the location of the station at Oranmore instead of the original
station location.
On
Thursday 2 October, a ballast train hauled by 141 loaded at Tubber and
then discharged north of Tubber. It departed for Ardrahan at 12:30, where it
re-loaded and stabled.
Limerick-Ennis
Flooding regularly occurs at Ballycar and the line was closed from 5
February until 27 March 2008. IÉ said ‘As the railway line is not the cause
of the flooding, and it affected a much wider area, the Office of Public Works
(OPW) will need to develop a flood relief scheme. We liaised with them on this
issue during and since the flooding earlier this year, and have offered to share
the costs of an initial study to assess the full requirements of any flood
relief scheme’.
In
November, the OPW said ‘In view of the fact that the railway line was the only
significant beneficiary it has been indicated by the OPW that we will not be
managing or commissioning a study or any proposed works for the area. Resources,
both financial and manpower, are already fully committed for the foreseeable
future to other approved projects in our national priority programme of flood
relief schemes. Our financial allocation for such works has been further eroded
as a result of recent Government announcements in relation to cutbacks and
savings in public expenditure’.
In
response, IÉ advised ‘We are progressing with a study, which we are funding,
to examine all options to address the problem into the future’. However, the
water level at Ballycar again rose during the winter and was being closely
monitored by IÉ.
Ennis
Platform upgrading works in October, November and December meant long
trains could not be handled. Passengers from the Fridays-Only 17:05 Dublin-Ennis
had to transfer in Limerick to a 2700-class railcar instead of having a Mk III
train throughout.
TRACK
Dublin-Cork
Both up and down roads through Ballybrophy station were excavated and
re-laid. Work commenced in late September and continued until mid-December. The
old track was welded rail laid on timber sleepers as the station area is boggy.
Additional pile driving was required to stabilise the platforms faces on up and
down main lines and very substantial machinery was used. Temporary buffer stops
protected the worksite. Access was via a temporary road across the branch line
tracks and all branch trains operated to/from Roscrea with bus connections.
During the work, Dublin-Cork line trains in both directions operated via the
loop. The new track is welded rail on concrete sleepers. The south ground-frame
on the up side, generally used by permanent way machines, was removed.
On 7
December, the trailing crossover operated by ground frame, which connects the
Infrastructure Depot at Kildare with the down Dublin-Cork line, was renewed. The
new crossover is powered by Westinghouse Type 63 point machines operated from a
local panel released by CTC in Dublin. New axle counters are provided for
detection on the crossover and associated headshunt. These are superimposed over
but not connected to the existing down mainline track circuits.
IÉ
awarded a contract to BKS Surveys Limited, Coleraine, for a detailed ground and
aerial survey of the Dublin-Cork line. ‘As a minimum, this topographical
survey shall extend either side of the railway embankment as far as it is
necessary for the further design [sic] and obtain ground details adequate for
performing cross sections at 25 m interval’.
Mallow-Tralee
The Mallow Beet Factory ground frame was removed on 30 November,
eliminating access to the Beet Factory Siding. However, a large number of bogie
flat wagons were left in the sidings.
Athlone-Galway To facilitate installation of CWR with derailment protection on the
Shannon Bridge, the up loop at Athlone Midland was taken out of service for the
month of November.
Dublin-Rosslare Europort
In November, Dún Laoghaire Rathdown County Council sought ‘submissions
or observations with respect to a proposal for
the construction of a New Metals Walkway, including a deck over the DART rail
line, adjacent to Queen's Road and Upgrade of Marine Road, Crofton Road, and
Queen's Road, Dun Laoghaire’.
Dublin-Belfast The up and down junction points at Howth
Junction were renewed like-for-like over three weekends. The first two weekends
were 8/9 and 15/16 November with the line closed from 22:15 Saturday until 10:00
Sunday. DART and outer suburban trains were replaced by buses north of Connolly.
The down turnout was renewed the first weekend and the up turnout the following
weekend.
The third closure was from 21:30 on Friday 28
November, all day Saturday and Sunday. This was for the renewal of the moving
switch-diamonds. The up line was closed for the entire period while the down
road was handed back for the 09:35 Dublin-Belfast on Saturday. All DART services
were cancelled north of Connolly, while outer suburban services additionally
called at stations Malahide-Connolly. Outer suburban trains ran to/from Connolly
rather than Pearse. The 06:50 Belfast-Dublin and 07:35 Dublin-Belfast on
Saturday were substituted by bus between Drogheda and Dublin Connolly. The
latter was particularly busy due to shopper traffic. The line was handed back
with the crossover fully ballasted and welded up.
Limerick-Waterford Re-laying work between Clonmel
and Carrick-on-Suir took place in November and December. The 08:50 and 11:45
Limerick Junction-Waterford and 09:35 and 12:30 Waterford-Limerick Junction were
replaced by buses, but there was also periods of complete cancellations and
cancellations between Limerick Junction and Carrick-on-Suir.
Waterford-Rosslare Europort
There was further re-laying between Wellingtonbridge and Rosslare Strand
at the end of October.
Limerick-Ballybrophy
Further re-laying took place in October and November between MP383/4-407/8.
The 10:10 Ballybrophy-Limerick was cancelled for periods in October and November
for the work.
Procurement
In December, IÉ advertised for 100 hollow steel sleepers for 2009
that can be used for conveying and protecting cables across plain track. It
included an option to purchase a similar quantity in 2010 and 2011. IÉ also
advertised for a 1-year contract with an option to extend to 2 years for mobile
flash butt welding services using a road-rail vehicle.
ELECTRIFICATION
From
Monday 13 October until Tuesday 16 December, there were alterations to Rosslare
line services to facilitate Overhead Line Equipment (OHLE) inspection and
repair. Sections between Dublin and Greystones were closed at night, preventing
empty Rosslare line trains running. The 16:52 Maynooth-Enniscorthy operated
through to Rosslare and the 19:23 Gorey-Dublin Connolly, 20:05
Enniscorthy-Dublin Connolly and 05:44 Arklow-Rosslare Europort were replaced by
buses. The 16:40 Dublin Connolly-Gorey remained in Gorey to form the 06:00 to
Connolly next morning.
SIGNALLING
ECP
The Galway line CTC
Emergency Control Panel (ECP) was re-located from the relay room at Athlone
Midland to the Level Crossing Control Centre located in the former goods store
at Athlone Southern on 8 November. It is now sited adjacent to the Mayo line
ECP.
Tullamore
On 3 December, the up main starting signal was moved 21m towards
Galway, shortening the standing room available for crossing trains to 262m.
BRIDGES
AND TUNNELS
Replacement
of UB777 at 147 miles 1,188 yards Manulla Junction-Castlebar resulted in the
closure of the line from 18:35 Saturday 15 November until 12:00 next day.
Saturday’s 17:45 Dublin-Westport and Sunday’s 07:45 Westport-Dublin operated
to/from Claremorris, with bus connections to/from Castlebar and Westport and
2600-class railcar Claremorris-Ballina.
UB158 at
115 miles 1,254 yards Athenry-Galway was renewed with a pre-cast concrete deck
on the weekend of 29/30 November. Saturday’s 19:15 Dublin-Galway operated to
Athenry only. On Sunday, the 08:25 Galway-Dublin started from Athenry. Bus
connections operated Athenry-Galway.
UB251 at 0
miles 1,625 yards Wexford South line (Wexford-Rosslare Strand) was renewed on
the weekend of the 5/6 December under a complete line closure. A new underpass
was installed at Martin’s level crossing on the Dublin side of Rathdrum and
the face of the up platform at Arklow was cut back using a large concrete saw.
All trains were replaced by buses south of Wicklow on both days.
Preparation
work continues on UB7 under planned weekend possessions for deck renewal
programmed for September 2009. This is the bridge on the former GS&WR Amiens
St-Glasnevin Junction line over the former MGWR line and Royal Canal at 0 miles
630 yards at West Road.
LEVEL
CROSSINGS
Barriers
The programme of converting manually operated level crossings to four-barrier
type continues. Streamstown in the Claremorris - Manulla Junction section was
converted on 2 October.
Ballymurry
Automatic Half Barrier (AHB) in the Knockcroghery-Roscommon section was
converted a 4-barrier CCTV type on 16 October. New colour light distant and
(stop) home signals were installed, with the new 3-aspect up home acting as a
distant signal for the nearby Curry CD-type level crossing and Curry’s down
home signal converted to 3-aspect to also act as a distant for Ballymurry.
Control of both Streamstown and Ballymurry was transferred to Athlone Level
Crossing Control Centre (LCCC) on 16 October.
Cortober
(Kellegeher’s) level crossing XS087 just south of Carrick-on-Shannon station
was converted from a user operated crossing to a 4-barrier CCTV type controlled
from Athlone LCCC on Thursday 13 November. The loop and main up starting signals
at Carrick-on-Shannon loop (just north of the station) received a third aspect
(yellow) and now additionally act as up distant signal for the level crossing. A
new red-green up stop signal protects the crossing. The down distant for
Carrick-on-Shannon was converted to a 4-aspect signal and additionally acts as
the down stop signal for the level crossing. A new green-yellow down distant
signal is provided 1,900m from the down stop signal.
Garraun
(XG167) Automatic Open Crossing 122 miles 310 yards Athenry-Galway was converted
into a 4-barrier CCTV type on Tuesday 16 December. New distant and stop signals
were installed, with the down stop signal acting as the distant for nearby
Rosshill crossing.
Control
Control of Waterford line CCTV crossings at Ballybay, Gowran,
Highrath, and Mullinavat was transferred to Athlone LCCC between 6 and 10
October. Control of CCTV crossings at Ballinasloe, Woodlawn and Athenry stations
was transferred from Mainline CTC in Dublin Connolly to Athlone LCCC on 11
December.
Closures
New bridges are being constructed to allow further user-worked level
crossing closures at 56 miles 350 yards Geashill-Tullamore, at 79 miles 600
yards and at 82 miles 1,100 yards, Athlone-Ballinasloe, at 16 miles 1,134 yards
to close XT052 (Ballinkeen) and XT053 Banteer-Millstreet.