These
correspond to where existing crossovers are located.
Limerick
Junction
Preparation work for re-signalling continues. A new longer higher speed trailing
crossover (No. 23) was installed between up and down Cork lines over the weekend
of 6/7 September during the line closure for installing the river bridge at
Multeen between Thurles and Limerick Junction (see below). The crossover is used
by trains departing towards
Cork
from the main platform (No. 1) to rejoin the down main line. It had been
fabricated in the yard opposite the station and to allow it be moved into place
the up direction home semaphore signal (Nos.
4/6) was re-located from the down side to the up side.
Cork-Cobh
The line speed limit has been altered. The differential speed limit boards for
‘Railcars’ and ‘All other Trains’ have been removed and all trains can
now operate at 50 mph. This had been one of the few locations on IÉ with
differential speed limits, which are a very common method used in the
UK
and other countries to allow lighter railcars operate at higher speeds than
locomotives.
Dublin-Rosslare Europort
The facing and trailing pair of crossovers between Merrion Gates and Booterstown
are life expired. A 25-mph speed limit has been in force for some time. The
point blades were removed during weekend night time possessions at the end of
July, with the remainder of the crossovers subsequently removed. In September,
the 25-mph speed limit remained in force as the replacement track awaited
welding.
Dublin-Belfast A programme of renewing points and crossovers
in Connolly is underway. Work takes place at night at weekends.
Limerick-Waterford.
Continuous welded rail (CWR) on concrete sleepers has been installed
between MP431/4-441/4,
MP603/4-63,
MP641/2-651/8.
CWR has now been installed on approximately 42%
of the Limerick Junction-Waterford section, with the Limerick Junction-Tipperary
complete. Ballast
trains associated with re-laying have been operating from a base in Clonmel
during the summer
Waterford-Rosslare Europort
Re-laying with CWR on hardwood timber sleepers took place in June between MP931/2-971/8
in the
Wellingtonbridge-Rosslare Strand section. On Thursday 19 June, 080 was in charge
of the Donnelli gantry re-laying train at the scene. The train off-loaded the
old track panels at the site of the former Duncormick station, where they were
scrapped. CWR is now in place on approximately 12%
of the line, mostly east of Wellingtonbridge station.
Limerick-Ballybrophy
Further re-laying work took place during the summer months, with 21/3 miles re-laid this year to the end of August.
At
this stage, CWR on concrete sleepers had been installed continuously from
Killonan Junction (MP521/2) to Kilmastulla shale sidings (MP407/8),
with the exception of the Birdhill station area. However, there were
considerable lengths of rail clamped awaiting Thermit welding. CWR is also
installed between MP6-63/4
Ballybrophy-Roscrea. The remainder of the line is jointed track.
Wagons
In July, IÉ sought
‘expressions of interest from relevant companies for the design, manufacture,
supply, delivery, commissioning and testing of up to 24 Rail Mounted High
capacity versatile railway stone ballast delivery wagons... The wagons will be
required to operate in tandem with an overall modern ballast cleaning system’.
The contract was estimated at between €15m
and €16m.
Track
Machines In July, IÉ advertised for ‘the
design, manufacture, supply, delivery, commissioning and testing of one rail
mounted high output ballast cleaning machine... The machine will be required to
operate in tandem with an overall modern ballast cleaning system and with new
ballast wagons and/or spoil discharge wagons. The contact value was estimated at
between €6m
and €7m.
IÉ
already owns one elderly Plasser & Thuerer ballast cleaner, No. 780
delivered in July 1979, but this has been out of service for some time. It has
been undergoing major refurbishment in Mullingar. New bogies have been purchased
and they were fitted on 28 June. The cleaner was towed to
Dublin
by 077 on Thursday 11 September.
IÉ also
advertised for ‘the design, manufacture, supply, delivery, commissioning and
testing of one Rail Mounted High Output Track Tamping Machine... The contact
value was estimated at between €5m
and €6m.
Procurement
IÉ has placed a contract with PDM Ltd,
Oldmilltown, Kill, Co. Kildare for the supply of ‘an estimated 20,000 softwood
treated timber sleepers over the course of the next three years ... to be
produced from North European Redwood or Maritime Pine. Other varieties of
species will be considered’.
In August,
IÉ has advertised for framework agreements lasting 3 years for the supply of:
Weedspray
Despite commissioning of a new spray train last
year, no weedspray train operated this year. However, road-rail vehicles were
used in many locations.
SIGNALLING
Train
Radio IÉ
intends to implement a GSM-R
mobile communications system over sections of the rail network. This will be
phased and implemented on a prioritised basis over a number of years. IÉ
advertised for ‘a consultant to progress the first phase of the project to
tender stage. The initial implementation of GSM-R
will be for “voice” services; however the design will take cognisance of
possible future application of ETCS while not necessarily providing the required
signal field strengths and redundancy requirement in this initial phase. The
first phase of the project will cover the DART electrified line and the fitting
of GSM-R
mobiles to the electric fleet. It is intended that the infrastructure provided
in this first phase will have sufficient capacity to cater for all trains on
this route and be expandable to cover the entire rail network in the future’.
Hot
Axle Box Detectors A new detector was commissioned
on 7 July near MP98 in the Ballinasloe-Woodlawn section on the
Galway
line. It is monitored by CTC in
Dublin
.
Signal
Heads A programme of replacing all signals on the
Howth branch with LED type took place in September.
BRIDGES
AND TUNNELS
Shannon
Bridge
In
July, IÉ advertised for ‘applications ... from experienced Steel Fabricators
who wish to be included on a tender list for the fabrication of a 4-span railway
bridge over the River Shannon near Drumsna, Co. Leitrim. The bridge carries the
single-track Mullingar-Sligo railway line. The renewal of the existing 6-span
bridge is scheduled to take place early in 2009. The scope of the Works for
which applications are now invited is for the supply, fabrication, painting and
delivery to site of all 4-spans. Delivery will be to an area beside the railway
near the
village
of
Drumsna
. The new bridge will have 4-spans, 2 x 25m, 2 x 22.5m. All four spans will be
of similar construction, consisting of a pair of
Warren
trusses supporting cross beams and plated deck. The overall width of the bridge
spans is 5.08m. A walkway will also be fabricated, which will be bolted to the
outside of the trusses, on one side of the bridge.
Multeen
River
Bridge
(UB247) During the summer, a substantial new
bridge was constructed in a field adjacent to the Dublin-Cork line to replace
the existing structure at 99 miles 692 yards. The old bridge was a three span
steel bridge, while the new one has three pre-cast concrete units. A 1,000 tonne
crane was used, with the maximum lift of 120 tonnes.
The old
bridge was removed and the new bridge was installed in a complete line closure
from 20:30 Friday 5 until 10:00 Sunday 7 September. During this period, all
services were cancelled between Thurles and Mallow. Substitute buses services
operated and a revised timetable also applied.
On
Saturday, the following trains were cancelled: Dublin-Cork 08:00, 10:00, 12:00,
14:00, 16:00, 18:00, 20:00 and Cork-Dublin 05:15, 09:30, 11:30, 13:30, 15:30,
17:30, 19:30. The 07:00, 09:00, 11:00, 13:00, 15:00, 17:00, 19:00, 21:00
Dublin-Cork operated to Thurles, with substitute buses onwards to Cork and
Mallow for the Tralee line. The 06:30, 07:30, 08:30, 10:30, 12:30, 14:30, 16:30,
18:30, 20:30 Cork-Dublin operated from Thurles, with substitute buses departing
from Cork up to 45 minutes earlier. The 18:35 Dublin-Tralee was substituted by
bus between Thurles and Mallow, as was the 06:30 Tralee-Dublin.
Dublin-Limerick
services operated at 10:25, 12:25, 13:25, 15:25, 17:25 and were substituted by
bus between Thurles and
Limerick
. Limerick-Dublin was served by a 05:45 bus to Thurles and by trains via the
Nenagh line at 06:44 regular, 07:35 special, 12:15 special, 14:15 special and
16:45 regular. Specials ran non-stop from
Limerick
to Ballybrophy, returning empty at 08:38, 15:15 and 16:05. All Nenagh line
trains were 2-car 2700-class. Line capacity did not allow Dublin-Limerick
specials to operate via Nenagh and most passengers had to put up with bus
connections from Thurles to
Limerick
.
There were
also alterations to Limerick-Ennis and Waterford-Limerick Junction services.
On Sunday,
the 08:10 Dublin-Tralee and 10:00 Dublin-Cork were substituted by bus between
Thurles and Mallow as were the 08:30, 10:30 Cork-Dublin and 08:35, 10:35
Limerick-Dublin. No additional services operated via Nenagh and there were
alterations to
Tralee
and Limerick Junction-Limerick services in the morning. All other services
operated normally.
Maintenance
Structural repairs to Span 15 of the
Barrow
Bridge
(UB140 at 81 miles 1,494 yards Waterford-Rosslare) were completed in July and
this span was subsequently painted. Structural repairs to the signal cabin
supports were also carried out.
Preparation
work is continuing to UB7 at 0 miles 630 yards Connolly-Ossory Road Junction,
under planned weekend possessions for the deck renewal which is programmed for
September 2009.
Emergency
repairs were carried out to the cast iron fascia panels on Balbriggan Viaduct
(UB56 at 21 miles 1,109 yards) following storm damage to this 11-span viaduct on
25 May. Following bridge strikes, repairs were carried out to UB117 at 82 miles
1,628 yards and UB170 at 126 miles 630 yards Dublin-Galway.
New
Bridges New road building in the
Waterford
area is resulting in construction of many new bridges over railway lines. New
bridges are being constructed at 74 miles 1,755 yards and 75 miles 950 yards in
the Carrick-on-Suir-Waterford section, at 56 miles 391 yards and 47 miles 1,467
yards Ballyhale-Waterford, at 33 miles 783 yards Lavistown-Ballyhale, at 76
miles 704 yards and 70 miles 332 yards in the Muine Bheag-Lavistown section.
A new
overbridge is under construction at the sharp curve at former Wicklow Junction
at the Murrough, Wicklow, as part of a new road scheme. This will permit closure
of Chemical Yard level crossing, which is subject to a 5 mph speed restriction.
LEVEL
CROSSINGS
Barriers
The programme of converting manually operated level crossings to four-barrier
type continues. Keelogues in the Manulla Junction-Ballina section was converted
on 22 May. Ahane No. 2 in the Farranfore-Tralee section was converted on 28 May.
Islandeady in the Manulla Junction-Westport section was converted on 29 May.
Lisaniska in the Manulla Junction-Ballina section was converted on 6 June.
Culleen in the Athlone-Knockcroghery section was converted on 19 June. Holywell
and Hazelhill in the Ballyhaunis-Claremorris section were converted on 27 June.
Headford in the Mallow-Tralee section was converted on 25 July. In the Muine
Bheag-Kilkenny section, Gowran was converted on 8 August and Highrath on 15
August. Mullinavat in the Ballyhale-Waterford section was converted on 29
August.
Control
using CCTV of the six Mayo line crossings noted above plus Rockfield in the
Manulla Junction-Westport section was transferred to Athlone Level Crossing
Control Centre between 30 June and 4 July. Control of eight
Tralee
line crossings was transferred to Mallow Level Crossing Control centre between
11 and 15 August. They were Rathcoole No. 3, Freemount, Headford,
Killeen
, Ballyhar, Ballinelane, Ahane No. 2 and Bealagrellagh.
Closures
In June, IÉ applied for permission to South
Tipperary County Council to build a 569m long local road to allow closure of
Bishopwood level crossing XC128 at MP981/4.
Bishopwood is currently the first open public level crossing on the Dublin-Cork
line after leaving
Dublin
. If it is closed the first open crossing will then be Grange at MP1033/4.
This is to be converted from an AHB to a full-barrier type. It will have new
protecting signals installed as part of the Limerick Junction re-signalling
scheme.
In July
following legal advice, South Tipperary County councillors voted to accept the
recommendation of an independent Inspector who agreed with IÉs request to
extinguish the right-of-way through Kyle and Milltown level crossings near
Limerick Junction and allow them to be closed. Kyle is on the Dublin-Cork line
just north of Limerick Junction and Milltown is at the
Limerick
end of Limerick Junction Loop (Direct Curve). IÉ has been granted planning
permission to build 1 km of new road to provide alternative access. IÉ made the
application in November 2006 and the issue caused upset among some councillors.
They were advised that following an oral hearing the Inspector recommended
closure on safety grounds and they could be held liable if they refused the
application and a safety incident occurred.
Overbridge
OB008D is under construction at MP44 Portarlington-Athlone to allow closure of
level crossing XA007. OB20F is under construction to allow closure of crossing
XL43 Linfield at 12 miles 1,220 yards Dromkeen-Limerick Junction.