
Irish Railway Record
Society
Journal
164 TRACK
Dublin-Cork
The track in platform 1 at Limerick Junction, the main platform used
by down Dublin-Cork trains and most up Cork-Dublin trains, was excavated and
renewed on Saturday evening 23 and Sunday morning 24 June. Single line working
over the down road from Thurles to Charleville took place from 17:40 on the
Saturday. Saturday’s 18:00 Dublin-Cork, 20:00 Dublin-Cork, 18:40
Dublin-Thurles, 17:30 Cork-Dublin, 19:30 Cork-Dublin and 21:10 Thurles-Dublin
were cancelled. Other services were altered to make Limerick connections at
Thurles.
Dublin-Rosslare
Europort IÉ agreed
to two line closures to facilitate the demolition of the West Stand at Lansdowne
Road stadium, which is constructed over the Dublin-Rosslare line (See photograph
on Page 119, JOURNAL 163). The first closure was from Saturday 4 to Monday 6
August inclusive. Approximately 2,000 tonnes of stand and another 2,000 tonnes
of terracing were demolished in 62 hours. In comparison, the East Stand took a
month to demolish.
IÉ
had to remove overhead line equipment from the stand and erect new portal masts
to support it. The pair of crossovers under the Stand had been temporarily taken
out of use before the demolition. IÉ also took the opportunity to work on the
new eastern entrance at Pearse station - see details later.
DART
services were substituted by bus between Tara Street and Sydney Parade. Maynooth
and Northern line trains operated to and from Connolly instead of Pearse and
Rosslare services were substituted by bus between Dublin and Greystones. Rail
services resumed on schedule on Tuesday morning.
On Friday 3 August, locomotives 190+152 were
on a materials train in North Wall waiting for the possession to commence at
Pearse. The train was on the down road in Pearse unloading materials next day.
On Tuesday 7 August, 190+152 + the empty materials train + 18 laden Barytes
wagons of spoil departed Heuston Goods at 11:55 for Portlaoise. Due to its
length it fouled the passenger lines at Heuston and it had to depart ahead of
the 12:00 Heuston-Cork, which then overtook it in The Gullet between Heuston and
Inchicore. It passed Cherry Orchard at 12:35.
There
will be another closure during the October public holiday weekend when it is
planned to construct a large underpass under the line. The underpass will allow
alternative pedestrian access to the level crossing.
Dublin-Belfast
A small section on both lines between Connolly and Ossory Road Junction
has been re-laid using hardwood sleepers. However, a further small section
between Ossory Road and East Wall Junctions remains to be re-laid and the line
is subject to a 20-mph speed restriction that significantly reduces capacity in
the Connolly area.
Dublin-Sligo
Lack of a suitable refuge siding at Clonsilla causes some
Docklands-Clonsilla trains to run Clonsilla-Maynooth-Clonsilla. In order to
eliminate these movements a new turn-back siding has been installed on the up
side in Clonsilla near the start of the former Navan line.
On
Sunday 29 July the down starting signal and associated shunt signal was moved
back towards Dublin by 47m. Late Saturday night and early Sunday morning trains
on 11/12 August were cancelled between Dublin and Maynooth to allow installation
of points. On Friday
10 August, 149+166 + 1 bogie of new track panels + 18 empty (Barytes) spoil
wagons arrived in North Wall in preparation work at Clonsilla.
Entry
and exit from the new siding is via shunt signals. The facing crossover was
moved 205-metres towards Dublin. A new four-aspect up stop signal protects the
turnout and traps from the siding. A banner repeater is situated 148-metres from
this signal.
Points
and signals were commissioned during an overnight closure on Saturday/Sunday
25/26 August. The existing Westinghouse Westrace signalling was extended to
control the new installation.
Portarlington-Athlone
The former beet loading sidings on the up side at Tullamore were taken
out of use and associated signals and points removed on Sunday 10 June. On the
same day the points for the loop at the Athlone end were renewed and moved 49m
towards Athlone. Prior to this renewal it was not possible to cross two 18-bogie
container trains in Tullamore if they contained any 47’ 6” wagons. The
cement silo siding on the down side remains out of use with cement being brought
in and out by road.
Athlone-Westport
The speed limit through Knockcroghery has been raised from 10-mph to
50-mph following installation of CTC.
Limerick-Rosslare Europort
Beam re-laying between Limerick Junction and Tipperary (MP213/4-243/4)
resulted in substitution by bus of the 07:00 Rosslare Europort-Limerick Junction
from Waterford, the 09:50 Limerick Junction-Waterford, 11:47 Waterford-Limerick
Junction and 16:35 Limerick Junction-Waterford during weekdays in May. Other
short lengths of track re-laid were in the following sections: MP30-301/2,
MP501/2-521/2, MP72-733/4
and MP751/2 -761/2.
Ballybrophy-Killonan
Junction The
Killonan-Birdhill section was closed from 08:00 on Saturday 24 June to 17:00
next day to allow gantry re-laying with second hand materials. Trains were
substituted by bus. The same section was closed between 09:35 to 15:15 from
Monday 2 July to Saturday 8 July. The re-laid was between MP44-453/4.
Small lengths of track have also been re-laid in the following sections: MP371/2-38,
MP493/4-513/4.
Platin
(Drogheda)-Navan Re-laying
with second hand materials has taken place between MP12-123/4
and of Platin yard loop.
On
Friday 8 June, 190+152 + 8 bogies of track panels + Donnelli re-laying gantries
departed North Wall for the Navan branch. At 12:30 on Friday 20 July, 171+134
arrived in North Wall with a track relaying train and departed at 13:25 for the
Navan branch behind the 13:20 Connolly-Belfast Enterprise.
Next day, the train was observed at MP12 west of Beauparc where track was being
re-laid. The train departed Navan for North Wall at 13:00 on Sunday and worked
North Wall-Portlaoise next day.
Ennis-Athenry
Work
on re-laying the track commenced during the summer, starting from the Athenry
end. Excavations have been made under overbridges to lower the trackbed for new
track, which will be laid with concrete sleepers. Old track panels have been
removed and new drains installed. Excavations have also been made at cuttings to
improve views at level crossings and the excavated materials were used for side
filling at embankments. Other work included fencing, weedspraying and drainage.
Mullingar-Athlone
An inspection car traversed the line on Thursday 16 August.
The
remainder of this article appears in IRRS Journal number 164, published October
2007.

Copyright © 2007 by Irish Railway Record Society Ltd.
Revised: December 16, 2007
.