Irish Railway Record Society

Home News 163 Claytons Moyvalley 1919 Mayo Line Modernisation

Mayo Line Modernisation

OLIVER DOYLE, Operations Schemes Development Manager, Irish Rail

At one time or another, there were some 16 block posts between Athlone West Junction and Westport Quay 1 While not all of these were required for passenger services, which even today amount to only three in each direction on weekdays, they were needed for goods trains and cattle specials, which formed an important part of the MGWR's business. The earliest rationalisation of signal cabins was in 1941 when the three at Claremorris and a substantial ground frame were amalgamated. The closure of many intermediate stations led to the subsequent closure of some block posts, while the growth of CTC in the 1970s saw the end of mechanical signals between Athlone and Knockcroghery.

It was the derailment mid-section near Knockcroghery, on the Mayo line, on 8 November 1997 that led to major investment in the IÉ system, including the Mayo line. This included track re-laying, an extensive program of station layout renewal and a re-signalling programme. In addition to the track and signalling renewals, all platforms are being brought up to current standards and the attended level crossings on the route are being converted to 4-barrier CCTV-type, remotely monitored from the Athlone Level Crossing Control Centre (LCCC). When these works are complete, the new 22000-class InterCity railcars will replace the locomotive-hauled stock currently in use and service frequencies will also increase.

CLOSURE

The line between Athlone West Junction, Westport and Ballina was closed from Monday morning 16 April to Friday afternoon 4 May to facilitate the completion of the track work and the installation and testing of the signals. The opportunity was taken to carry out extensive platform works at Castlerea and Manulla Junction working long days. The platform work at Manulla was critical on the Branch Bay as there was a total repositioning of the track and a minimum of 42m of usable platform was required for the re-opening.

There were three train movements on the morning of the closure. The 2600-class railcar on the Ballina Branch departed at 05:25 for Athlone and later onward to Drogheda. At 06:20 the spare train locomotive in Westport, No. 220, worked to Athlone and finally the 07:00 Westport-Dublin scheduled service (226 + 8 Mk IIIa + EGV), with Driver Colm O’Reilly, became the last train to operate on the ETS/mechanical signalling system on the Mayo line – an historic occasion. After the train passed Claremorris, the signalman at Manulla Junction withdrew a train staff for each section, Westport, Ballina and Claremorris and handed them to District Traffic Executive John Butler, Athlone, who then proceeded to Castlerea by road where he collected a staff for the Claremorris (Long Section) and Roscommon sections from the signalman. Driving directly to Knockcroghery, he then collected a Knockcroghery-Roscommon staff from the signalman at 09:15, formally closing the line to Westport and Ballina. At 09:45, the Knockcroghery signalman granted the Divisional Engineer, Athlone, possession of the railway between the Knockcroghery Down Home signals and Westport and Ballina buffer stops. At 09:46, the signalman granted possession of the section to Athlone West Junction.

The 1051/4 miles from Athlone to Westport and Manulla Junction to Ballina is the longest of the re-signalling systems to be completed in one job, the Sligo Line having been commissioned in two sections.

By mid-morning on Monday 16 April, the scene at Castlerea was impressive. Two earth moving machines and a tamper were working on the new layout at the Athlone end of the station. A large tracked earth moving machine had worked its way into the disused goods store and removed the roof in the process. By noon the wooden trusses were removed, broken into manageable pieces loaded in a skip. The walls were demolished later in the day and the rubble was taken away for sorting - the cut stone for re-use and the fill and broken slates for disposal. Two mini-diggers were working! One on each platform, removing the existing coping stones and platform surface and loading the spoil into a rail-mounted dumper on each track. The level crossing gates and piers were removed by a machine by 10:00 and by noon the same machine had erected the two down starting signals. The other major work site on the closure day was Manulla Junction where earth moving machines were removing the old junction turnout, slewing the branch track to create the new bay platform track, and finalising the new Westport line to Ballina branch connection. A tamping machine was also in attendance to maximise track quality.

STATION LAYOUTS

The track layout at each station was reviewed and redesigned to suit the proposed passenger train timetable post the introduction of the 22000-class railcars in 2008. To maximise station approach speed, the main route through Roscommon, Castlerea, and Claremorris was engineered to be through the main platform with the relevant passenger facilities. Loops are adjacent to the second platform. Each of the locations has a turnout leading to one or more sidings. Due to the geography of Ballyhaunis, this was not possible.

The layout at the Knockcroghery end of Roscommon was altered on 1 April when the Long siding, a remnant of the former Up line, was lifted. This allowed a new loop turnout to be installed in advance without interfering with the existing loop turnout. The old turnout was removed after the closure and the new one connected, thereby increasing the loop length somewhat.

Prior to the closure of the line on Monday 16 April, much permanent way work had been carried out. Considerable track slewing was needed at Castlerea, and the majority of this was carried out in an overnight possession on Saturday night/Sunday morning 15/16 April. However, it was not possible to signal the loop, so no trains could cross at Castlerea on Sunday. The 13:05 Heuston-Westport (226 + 6 hauled P/P coaches) was deferred to leave Roscommon 40 minutes later than advertised, having crossed the 14:25 Westport-Heuston (078 + 7 Mk IId) service there. Ballyhaunis cabin, which normally opened only on Fridays, was specially switched in to permit the 13:05 cross the 15:30 ex-Westport (213 + 8 Refurbished Mk IId). The 13:05 arrived at Westport 20 minutes late, passengers having been pre-advised of the deferred arrival. Locomotive No. 076 was then attached to the rear to work the set back as the 17:55 to Heuston. At 17:00 Ballyhaunis cabin switched out for the final time. This was the last IÉ signal cabin to regularly use ETS switching out apparatus, the facility at Gorey being rarely used these days.

The new layout at Claremorris was completed by the end of March with the removal of the freight sidings, latterly only used by Guinness traffic, before it was finally withdrawn. The former Kiltimagh siding, a stub of the closed line to Sligo, is no longer connected. In the event of the line being re-opened, this could be easily re-connected by the installation of a turnout.

The layout at Westport was altered to suit the side loading of timber trains without the need to divide the train as heretofore. The disused locomotive fuelling facility was demolished to lengthen the loading area. The crossover between the Quay sidings was moved towards the former Quay Station to allow locomotives run around timber trains while the main passenger platform is occupied. To facilitate a total redesign of the western end of the station, the area was given to the engineers on Wednesday 11 April and as a result no locomotive run round was possible. To assist, a spare locomotive was allocated to Westport, and as each train arrived, the spare engine was placed on the rear of the arrived train leaving it ready for departure. Westport Cattle Bank siding was removed on 31 January.

Manulla Junction was redesigned to allow trains arrive simultaneously from Westport and Ballina, and at the same time have through running possible between Ballina and Athlone. The new connection from the Westport line to the Ballina line was completed by 30 March. At Ballina, the modern freight layout was retained, while on the passenger side the locomotive release was abandoned, as, in a railcar only environment, it is no longer required. However, run round facilities are available in the freight yard and will be used by the 16:20 Fridays Only Heuston-Ballina.

PLATFORMS

The platforms on the route will be 174m except Castlerea Down, Ballyhaunis Down and the Ballina branch platforms. Manulla Junction bay platform and Foxford will be 90m and Ballina will remain at 106m. Castlerea and Ballyhaunis Down platforms will be 90m – allowing a 3-car and a 6-car InterCity railcar train to cross. These lengths are sufficient for the projected timetables using a combination of 6- and 3-car 22000-class InterCity railcars with commuter type units on the Ballina branch. All platforms are being finished in black tarmacadam except where there is an extension of an existing cobble lock surface in which case the extension will be also cobble lock. At Castlerea the former goods store had to be demolished to permit the platform extension to be constructed, there being no space at the Westport end due to the level crossing.

At Claremorris, the Island platform Nos. 2 & 3, will have coping and tactile on both faces and this will facilitate the possible re-opening of the line to Athenry in the future. However, this track had also coping on the Ballinrobe side platform and this was removed in March to give clearance for the storage of Mk II and Mk III carriages, the former normally working the 16:20 Heuston-Ballina, Fridays Only, since the withdrawal of the Cravens carriages. The reverse curve on this platform is being improved.

Work on the Manulla Junction platforms started at the Westport end on Thursday 12 April. However, the Permanent Way had previously cleared an area on the non-platform side of the Ballina line to allow the track be slewed as soon as the line closed. A gabion wall was constructed to act as a retaining wall since the adjacent lands are some 3m higher than the track. Such was the progress made during the closure with the contractor working long days, that the full length Bay platform was available from the re-opening.

SIGNALLING

The new signalling system is controlled by a Westinghouse Solid State Interlocking (SSI) similar to those used in the Galway, Waterford, Tralee and Sligo line projects. Because of the number of stations involved there are two SSIs working in tandem – one controls Athlone to Ballyhaunis inclusive and the second Claremorris to Westport and Ballina. To the signalman they appear as a single system. This is IÉ’s first major re-signalling scheme with no track-circuits. The station areas, as well as the sections between the stations, are all worked by axle counters, whereas previous schemes had track circuits in the station areas. In addition the 32 manned level crossings on the route were all converted to colour light signalling, again using axle counters to monitor train movements. The five existing AHBs continue to use track circuits, while the Athlone-Knockcroghery section, heretofore worked by track circuits, was converted to axle counters. Distant signals are of the now standard 3-aspect type, except Roscommon down. All signals on the line have the prefix ML (Mayo Line). At Ballina, the freight area had all power points worked from the signal cabin, a safety requirement from the days of the Asahi Acrylonitrile transport. It was decided to retain these, operated from simple switches on the ground near each points motor, worked by the shunters.

Trap points are provided on the main platform lines at both Westport and Ballina to allow the safe stabling of trains overnight. The signalling does not have CAWS as is also the case on the other lightly used lines recently re-signalled.

The control console is located temporarily in the Athlone LCCC and has three screen displays to cover the line. The area of control is from the Down Home signals at Knockcroghery to Westport and Ballina.

Culleen level crossing, which previously was within Knockcroghery Station area, is now a mid-section level crossing. The station level crossings at Roscommon, and Castlerea, were converted to 4-barrier CCTV-monitored type, with remote monitoring from the Athlone LCCC. The station level crossing at Knockcroghery was already a 4-barrier level crossing worked by the adjacent signalman and this was taken over by the Athlone LCCC upon re-opening of the line. In addition, seven mid-section level crossings had already been converted to the 4-barrier CCTV-monitored type and control of these was transferred to the Athlone LCCC during the closure – Kiltoom, Fuerty, Corrastoona, Carrick, Garryredmond, Mossbrook and Foxford. Three other crossings, also 4-barrier CCTV-monitored type, which are close to stations and incorporated into the station signalling, were transferred to Athlone LCCC upon commissioning of the signalling system – Ballymartin, Lisnolan, and Barrackland.

The closure of the eight Mayo line signal cabins, three electric and five mechanical, reduced the number of signal cabins on IÉ by nearly 25%. There now remain 21 mechanical and 6 electric cabins as well as one emergency frame at Rosslare Europort.

REOPENING

At 16:45 on Friday 4 May 2007, the signalman at Knockcroghery cancelled the possessions between Athlone and Knockcroghery and Knockcroghery-Westport-Ballina and handed over control to the Mayo Line signalman at Athlone, thereby permanently closing Knockcroghery cabin. At 17:29, the new signalling on the Mayo Line was signed in, worked by signalman Paul Kelly. The first train was the 16:15 Heuston-Ballina which left Athlone at 18:08 (081 + 8 Mk lld). This was followed by the empty Ballina branch railcar set (2611/12) which left at 18:30 and ran to Manulla Junction where it propelled to the new Bay platform to await arrival of the 17:50 from Heuston to Westport.

1 Athlone West Junction, Kiltoom, Knockcroghery, Roscommon, Donamon, Ballymoe, Castlerea, Ballinlough, Ballyhaunis, Claremorris (South), Claremorris (North), Balla, Manulla Junction, Castlebar, Westport, Westport Quay. In addition there were signal cabins at Claremorris (Ballinrobe Cabin), Ballyvary, Foxford and Ballina.

 

 

 

  The remainder of this article appears in IRRS Journal number 163, published June 2007.

Copyright © 2007 by Irish Railway Record Society Limited
Revised: August 12, 2007 .

Home