<
Irish Railway Record
Society

Athlone
Level Crossing Control Centre
OLIVER
DOYLE
OPERATIONS
SCHEMES DEVELOPMENT MANAGER, IÉ
From
the time when railways were first built in Ireland and Great Britain, it was
recognised that at places where the railway crossed public highways at the same
level, trains must be given the right of way because of their inability to stop
in a short distance, owing to their weight and the low coefficient of friction
between the steel rails and steel wheels. Consequently by the Railways Clauses
Consolidation Act, 1845, Parliament imposed rigorous rules to ensure the safety
of the public on the highways, and required that all public level crossings
should be both manned and gated, with ‘good and sufficient’ gates kept
normally closed against the road, so as to fence the railways in. But the Act
allowed directions to be given by the President of the Board of Trade that the
gates should normally be open to the road and closed across the railway; and,
over many years, as the volume of road traffic increased, so that the crossings
were used more frequently by road than rail traffic, such directions were issued
for nearly every busy level crossing. However, at such crossings, protecting
signals interlocked with the gates had to be provided to ensure trains were
stopped in good time if the gates were open for road traffic.
As
time progressed, directions were given for level crossings which were not busy
to be normally closed against the railway without protecting signals. This led
to entries being made against each level crossing stating whether they had
protecting signals or not. In some cases protecting signals were provided in one
direction only depending on visibility. Today no such arrangement exists on
Irish Rail. In early days the protecting signals were normally worked by a small
lever frame, but in later years a simple mechanical mechanism was devised
whereby the closing of the second gate against the road cleared the protecting
signals. Some little-used level crossings over public highways, where there was
a reasonable alternative route, continued to have the gates closed to the road
at night with no provision to call a gatekeeper to operate the gates. In
addition to being labour intensive, the gates tended to be closed for long
periods, particularly where two goods trains were approaching on opposite lines.
This could be as much as 12 minutes.
Where
level crossings existed at stations they were normally worked by the signalman,
usually by means of a wheel linked mechanically to the gates or by the signalman
simply working each gate manually. In
Ireland
, where the level of rail traffic was much lower than in
Great Britain
, some gates were operated by the wives of permanent way workers, some being
paid a sum per week while others received an annual payment. In most cases the
rate of pay for level crossing keepers took into account that they had a
rent-free house. In the first years of my railway career, I recollect paying a
gatekeeper £1 (€1.27) each Christmas as the annual payment.
As
horse movements through level crossings almost disappeared with the expansion of
motor traffic, the gates were simplified from a strong rectangular cross-braced
frame to a boom with wire-mesh skirting.
The
next development in crossing gate design was to replace the gate with a lifting
barrier. In 1954, the gates at Warthill Level Crossing, British Railways North
Eastern Region, were replaced by barriers on an experimental basis to quantify
the effects before presenting legislation before Parliament. The statutory rules
for level crossings remained substantially unchanged from 1845 to 1954, 112
years, when the British Transport Commission Act of that year permitted the use
of lifting barriers at manned crossings. This development had no impact on the
labour costs though it did reduce the delay slightly to road users. Coupled with
the development of automatic level crossings in Western Europe and the
increasing volumes of road traffic, the Ministry of Transport was under
increasing pressure to implement changes to the method of operation of
Britain
’s railway level crossings. In September 1956, Colonel D. McMullen of the
Ministry of Transport Railway Inspectorate went to France Belgium and
Holland
to evaluate automatic half-barriers in operation. At the time
France
had 700 such crossings. However, there was a fundamental difference between the
road users in Western Europe and
Britain
in that in the latter level crossings were protected by robust gates with
protecting signals while on the European mainland crossings were traditionally
open with mainly flashing lights warning of approaching trains and users there
were aware of the correct use of such crossings.
Section
6 of the British Transport Commission Act, 1957, permitted the use of Automatic
Half Barrier Level Crossings but it was not until 15 April 1959 that BR (London
Midland Region) applied for permission to install the first Automatic Half
Barrier crossing. The first such crossing was commissioned at Spath,
Staffordshire, on the
Churnet
Valley
line of the former North Staffordshire Railway between Uttoxeter North Junction
and Rocester. The crossing was monitored by the Uttoxeter North Junction signal
box where the position of the barriers and state of the power supply was
indicated. A two-way telephone allowed communication between the signalman and
the crossing users in the event of the barriers being down for an undue length
of time. There was much discussion regarding the length of time between a train
activating the level crossing and the passing of the train. While the line speed
was 45mph, it was suggested the barriers be timed for 60mph and this eventually
was settled at 55mph on the basis that the line was used by express freight
trains hauled by steam locomotives not necessarily fitted with speedometers. On
2 February 1961, the crossing was inspected and tested by Col. McMullen,
Railways Inspecting Officer, using a locomotive and saloon, who appeared
satisfied and approved the crossing being brought into use. Finally, on 5
February 1961, Spath was commissioned, becoming the first AHB installation in
Britain
or
Ireland
.
It
was not long before motorists disregarded the road signals and the first such
offender, a local man, was fined £8 (€12) a considerable sum in 1961. After a
further seven people were brought before
Uttoxeter Court
, the Clerk of the Court felt compelled to write to the railway regarding the
road signage. Not being responsible for road signage the railway forwarded the
correspondence to the Ministry. There was, it seemed, a widespread feeling that
the signage was inadequate and the red flashing lights too dim. A long debate
ensued as the provision of an amber warning light in advance for road traffic
but this was rejected out of hand by the Ministry which put the problem down to
the wilful disobedience of the road signals by motorists.
After
commissioning, the Ministry insisted on attendance at the crossing to monitor
its operation. As the roadway through the crossing led to the popular tourist
attraction at
Alton
Towers
, road traffic proved heavy on occasions and with a T-junction 100 yards from
the crossing, tailbacks were inevitable – even in 1961. When the railway
wanted to withdraw attendance in June 1961, the Ministry was not satisfied and
required the attendance to continue and the tailbacks to be monitored. Given
that the person doing the monitoring was a railway employee – the LMR reported
in September that there had been no further occurrences and they could not
understand why anyone had thought there was a problem in the first place. On 26
September 1961, Colonel W. P. Reed, Railways Inspecting Officer, agreed to the
attendance being withdrawn on condition that road signs be erected “Do not
stop on crossing”. This was to be of significance some seven years later. He
also required attendance during the winter to monitor the crossing’s operation
during high winds and snow - however, neither were a problem. The line closed in
1965 and so the first AHB level crossing had a rather short life. Meanwhile
other AHBs were commissioned and CIÉ,
anxious to effect economies, installed its first such crossing at Grange, MP 105
Dublin-Cork line, two miles north of Limerick Junction station.
The
remainder of this article appears in IRRS Journal number 162, published February
2007.

Copyright © 2007 by Irish
Railway Record Society Limited
Revised: February 03, 2007
.