Irish Railway Record Society

Home Up Operations 160 Stations 160 NIR News 160 Locomotives 160 Track 160 Rolling Stock 160

TRACK

WESTERN RAIL CORRIDOR

  Preliminary work to clear a path between Collooney and Claremorris commenced in February. By March, the line between, and the station areas of Swinford, Kiltimagh and Charlestown had been cleared and work was taking place between Kiltimagh and Claremorris. Hedge cutting also took place between Athenry and Claremorris. Mileposts have been renewed in the Athenry-Limerick section using MGWR style mileposts and level crossings numbered with the prefix XE.

  Mr Eamon O’Cuiv TD, Minister for Community, Rural and Gaeltacht Affairs visited Tubbercurry to view the line and said that he intends to proceed with its preservation. He said ‘Now that Iarnród Éireann have completed the scoping work on the line and have an accurate estimate of the costs involved, it is hoped to finalise arrangements in relation to this funding as speedily as possible’. This work will be undertaken in accordance with the Transport 21 plan where funds of ¤5m will be provided from the Department of Community, Rural and Gaeltacht Affairs to provide for the fencing and preservation of all track and way-leaves from Claremorris to Collooney. Work will be carried out in line with requirements on hedgerow clearance and bird nesting needs, with newspapers stating that it could commence in September.

  The Minister said ‘The preservation of the right of way is vital to the long-term goal of reopening the line from Limerick to Sligo and this work will signify the Government’s clear intention in this regard’. The scheme must be approved by the Board of IÉ and other relevant State interests before the preparatory work can proceed.

  In April, Business & Finance magazine said that IÉ had submitted business plans to the Department of Transport for the first stage of the Western Rail Corridor from Ennis to Athenry. On the subject of line speeds, it quotes an IÉ spokesperson as saying that the section ‘is very dense with level crossings. We have outlined that if you took zero action in terms of level crossings that you would have 40-mph speed restrictions. But you can build that up to 50, 60 or 70-mph depending on what you do with the crossings’. Some crossings that are not used can be extinguished or crossings could be closed by purchasing land, but many will have to either remain or be replaced by bridges or underpasses, increasing the price of the project.

  In April, the Taoiseach Bertie Ahern TD told a delegation from the Border, Midland and Western Regional Assembly of his commitment to progress work on the Western Rail Corridor as quickly as possible and had emphasised this at a recent meeting with the Chairman of IÉ.

TRACK

Limerick-Rosslare Europort   Work continues at various locations. From Monday 13 February to Friday 17 February, Limerick Junction-Waterford trains were replaced by bus between 08:30 and 17:00 to allow tamping and regulating ballast between Tipperary and Clonmel. Re-laying with second-hand concrete sleepers and welded rail took place between Wellingtonbridge and Taylorstown viaduct in February. One mile was re-laid, MP911/2-921/2. In addition, MP805/8-81 was re-laid with second-hand materials.

Ballybrophy-Killonan Junction   Possessions to re-lay and re-habilitate track continue. In late February/early March, the 10:10 Ballybrophy-Limerick was cancelled to allow work between Ballybrophy and Roscrea. The line was also closed from 09:40 Thursday 20 April to 11:40 on Monday 24 April for track excavations. All passenger and Kilmastulla (Birdhill) - Limerick cement factory shale trains were cancelled. MP101/2-11 has been re-laid with second-hand materials.

Dublin-Cork   Preparation work for the platforms for the new station at Adamstown, near the site of the former Lucan South station, has taken place. This included track alterations. Similar preparation work was also in hand for the new Parkwest station between Cherry Orchard and Clondalkin. This work will include slewing and lifting the track.

Athlone-Westport   New points and crossovers are being installed associated with the re-signalling project. A new turnout has been installed at the Ballyhaunis end of Castlerea, but the point blades are being left out until the signalling is ready for commissioning. A new turnout and traps have been installed for the up siding in Roscommon and additional track with concrete sleepers has been installed to extend the loop (up side) at the Dublin end. To suit the alignment over the bridge at the Claremorris end of Ballyhaunis station, the down line will become the main route when the line is re-signalled.

Cork-Cobh   On Sunday 2 April, the crossover (No. 14) at the Little Island end of North Esk was removed and replaced by plain track. The long siding is now shortened and new buffer stop installed.

North Wall   In recent years the track from the ‘Granaries’ to the sidings alongside the River Liffey via Sheriff Street level crossing, through the former Point Depot yard and across the road at the roundabout at the Toll Bridge has been used only for taking delivery of new rolling stock and locomotives. Many pictures have appeared in the JOURNAL of new vehicles being delivered on this track. It was taken out of service after the delivery of a set of 29000-class railcars on Wednesday 21 December. The track was cut and the temporary buffer stop at Sheriff Street level crossing was made permanent. It is understood that the yard at the Point Depot, now used as a car park, is to be developed and this was not conducive to a rail line running through it.

Navan-Kingscourt 

A road-rail excavator was in action in April, clearing drains and removing fences erected across the line. Procurement IÉ awarded VAE of Vienna a contract for the supply and installation of hot axle-box detectors. The IÉ concrete sleeper factory in Portlaoise is currently capable of producing 1,000 sleepers per week, which due to re-laying projects such as the Western Rail Corridor, Glounthaune-Midleton and four-tracking Cherry Orchard-Hazelhatch, is not adequate for future needs. In February, IÉ advertised for the supply and delivery of additional 150,000 stressed concrete sleepers per annum for three years. They will come with rail fixings attached and will have the same 1:40 inclination as those manufactured in Portlaoise. The estimated cost was noted at ¤23m in the European Journal. 

BRIDGES AND TUNNELS 

At the request of Dublin City Council, advertisements have been removed from the Loop Line Bridge over the River Liffey in Dublin. They were first put on the bridge in the 1960s. In return, IÉ received permission to erect advertisements at a number of different locations. The clock was also taken down, but the sign for DART/suburban trains at Tara Street remains. IÉ then sought contractors to paint the bridge; 8 spans from Tara Street to Beresford Place, a total length of 201m. The preparation was specified to be by water jetting, (minor repairs will be carried out by IÉ staff), the application of two-coat epoxy using brush and roller (no spraying allowed). IÉ estimated the value of the contract excluding VAT to range from ¤1.6m to ¤2.2m and work to take about five months. A new overbridge is under construction near MP701/2 between Clara and Clonnydonnin on the Portarlington-Galway line. When completed, it will allow closure of a number of adjacent unattended crossings on a curved section of line. New overbridges are being built at 63/4 and 71/2 miles Dublin-Cork near Lucan South. Major structural repairs are being carried out to span 13 of UB140 Waterford-Rosslare (Barrow Bridge). This repair work will be completed this summer. There were also major repairs carried out to UB186 Dublin-Rosslare (completed in January 06), to UB221 Dublin-Rosslare (completed in February 06) and to UB106 Dublin-Galway (Shannon Bridge at Athlone), which will be completed this summer. UB25 Navan-Drogheda was renewed on 5 May.

 SIGNALLING 

Re-signalling Work on re-signalling the Knockcroghery-Westport and Manulla Junction-Ballina lines continues. Signal bases have been erected at most stations with cables laid in trenches, which were normally dug well away from the running lines near the boundary fence. Signals were evident at Roscommon, Castlerea and Ballyhaunis by March. Work on a separate project to install colour light distant and stop signals at level crossings was also noticeable, with signals, cables, barrier machines and foundations for location cases and Re-locatable Equipment Buildings (REB) in evidence in April at several locations between Knockcroghery and Manulla Junction. 

The re-signalling project on the Dublin-Rosslare Europort line is following the Mayo line. Colour light signals had been erected in Arklow and Rathdrum by March and in Rosslare Strand by April. Cable trenches, cables and foundations for location cases were also noted at these locations and at Enniscorthy. Both Mayo and Rosslare line schemes are scheduled to be commissioned in 2007. Connolly The 'P1 OFF' signal associated with signal CY47 on platform 1 was replaced by a banner repeater on 26 March. 

Howth Junction-Malahide The wrong line signals on the up line at Portmarnock, which were installed temporarily as part of the DART upgrade work, were removed on 12 March. 

LEVEL CROSSINGS

  Level Crossing Control Centres   Work has commenced on converting the former goods store at Athlone (GS&WR) into a Level Crossing Control Centre to monitor CCTV level crossings. A similar centre has been designed for Mallow. These will cater for the increasing number of level crossings now being automated.

  Closures   The programme of closing unattended crossings to reduce the interface between vehicle and farm activity and the railway continues at a steady pace. Closures are achieved by installing underpasses, overpasses, constructing new roadways to nearby roads or bridges or by purchasing the land on one side of the crossing and then closing it. For example, there are now less than a half dozen open unattended crossings between Dublin and Limerick Junction, down from one hundred and forty some years ago.

  In March, IÉ applied for planning permission to Sligo County Council ‘to construct an agricultural overbridge with associated roadworks (170m long), embankments, walls, drainage, fencing, replacement cattle pen and safety barriers at Knockbeg, Collooney, to facilitate the closure of Level Crossing XS144’.

  The last remaining Automatic Half Barrier crossing (AHB) on the Dublin-Dundalk line at Dromiskin is being replaced by a new road, which was under construction in April. It will run parallel to the line towards an existing overbridge.

  Upgrades   In many locations, traditional red-white wooden gates are being replaced with lightweight gates made of red-white composite materials, which are reflective in car headlights.

The remainder of this article appears in IRRS Journal number 160, published June 2006.

Home
Copyright © 2006 by Irish Railway Record Society Ltd.
Revised: August 01, 2006 .