
Irish Railway Record
Society
TRACK
Limerick-Rosslare
Europort
Renewal of crossover 73 and points 74B in Limerick station took place
during Saturday 10 and Sunday 11 December. Limerick Junction and Ennis line
trains were substituted by bus on Saturday and on Sunday morning.
In 2005, the
following sections were re-laid with second-hand materials: MP385/8-433/4,
MP463/4-473/4, MP531/4-551/2,
MP56-571/4, MP797/8-801/2
and MP863/4-871/2.
Ballybrophy-Killonan
Junction
The line was closed completely from Thursday 29 September until 18:30 on
Monday 3 October and from Sunday 6 November until Sunday 27 November for track
re-laying in the Killonan-Birdhill section. All passenger and Kilmastulla
(Birdhill) - Limerick cement factory shale trains were cancelled completely. The
line was also closed for track repairs between Ballybrophy and Roscrea from
08:55 on Tuesday 13 until 18:00 on Thursday 15 December. In 2005 the following
sections were re-laid with second-hand materials: MP311/2-32.51/2,
MP421/2-441/2 and MP467/8-483/4.
Dublin-Cork
The manganese steel level crossing that
takes the single track Limerick-Waterford line across the double track
Dublin-Cork line at Limerick Junction was renewed on Sunday 11 December. To keep
Dublin-Cork line trains operating an interesting arrangement was employed. Early
morning trains were formed by push-pulls or railcars in both directions. Up
trains ran via Platform 1, departed towards Limerick, reversed and ran via the
Loop (Direct Curve) towards Dublin. Down trains ran via the Loop (Direct Curve)
where they reversed and resumed their journey via platform 1.
Athlone-Westport
At Castlerea, the up siding was removed on 5 October. It was used in
recent years for loading ballast. The track layout is now just a main and loop
track. A new turnout was installed in December.
Cork-Cobh The Cork-Cobh line was closed from 20:00 on
Saturday 12 until 11:00 on Sunday 13 November to allow renewal of the middle
turnout from the up line to the depot at North Esk. Trailing crossover No. 14 at
the Cobh end of North Esk was removed in December.
Glounthaune-Midleton
Extensive scrub and undergrowth clearance work has taken place on the
line using tracked and road-rail excavators. Midleton was reached on 13 December
and the machines spent a week clearing the station and former goods yard area.
Athenry-Tuam In November a contractor was used to clear the
line of overgrowth between Athenry and Tuam.
North
Strand Junction-Church Road
Both tracks on this line to the North Wall, generally known as ‘the
dip’, have been excavated and re-laid using second hand bull-head track. Two
tracks in North Wall from under the former West Road cabin to Church Road have
also been re-laid.
Drogheda-Navan In 2005, 5 miles of track was re-laid with second-hand
materials, including MP83/4-12.
Foynes
The
line remains out of use. The Working Timetable introduced on 11 December
states ‘Line not opened to
Traffic. No trains may proceed beyond Ballingrane due to structural condition of
Robertstown viaduct. Engineer’s trains are subject to maximum 25 mph but are
not permitted beyond Ballingrane…’
Datum
Plates IÉ
has advertised for the supply of 9,000 datum plates over 3 years to cover the
network. These plates are placed on structures such as poles, platform faces,
tunnel walls, etc., adjacent to the track and provide data about the track. Each
plate incorporates an adjustable slider to show the level of the nearest rail
and is approximately 150 mm x 200 mm with 25 mm digits and shows:
EM50
IÉ has advertised for the ‘supply, installation, commissioning and
operator training of an attended contactless track geometry recording system …
and an attended contactless rail head profile measuring system providing the
profile of each gauge face and rail head as a minimum; coupled to a user
interface & analysis system which can provide graphical display of
information, quality audit function and assist in planning track maintenance’.
The primary option under consideration is to fit the system onto the existing
Plasser & Theurer EM50 track-recording vehicle (No. 700), constructed in
1974.
Weedspray
IÉ has advertised for a new weedspray train, specifically new mixing and
spraying equipment to be fitted to an existing BR-type heating van (GSV). It is
proposed to run with the existing train of five 15,000-litre tankers.
Procurement In December, IÉ advertised for ‘Professional
and technical advice regarding the design and construction of developments in
close proximity to the railway line e.g. Lansdowne Road stadium development’.
BRIDGES
AND TUNNELS
Construction
of a new underbridge for the Carlow Inner Relief Road UB70C at 57 miles 880
yards in the Carlow-Muine Bheag section resulted in complete closure of the line
from Monday 17 October until 15:30 on Friday 21 October. Passenger trains ran
between Dublin and Carlow only with onwards bus transfers. Freight trains were
cancelled.
With
an increasing number of bridges being struck by high lorries, IÉ has increased
the installation of Bash Beams at bridges. Typically, these consist of a goal
post steel girder erected in front of the bridge. New beams were installed at
UB146 at 51 miles 384 yards (Portlaoise) and UB218 at 80 miles 1,56 yards on the
Dublin-Cork line in December and October respectively. The increasing nature of
this problem was highlighted by the fact that the Portlaoise Beam was struck by
lorries four times on the day following installation despite many road warning
signs.
Sidings
have been temporarily shortened to allow OB21 Bond Bridge at 15 miles 330 yards
just west of Maynooth station to be re-built and an adjacent culvert to be
renewed.
UB53
at 29 miles 24 yards on the Nenagh Branch was renewed on 15 December with a
composite deck structure. This was the last remaining way-beam bridge in the
Limerick Junction Division
The
remainder of this article appears in IRRS Journal number 159, published February
2006.

Copyright © 2006 by Irish Railway Record Society Ltd.
Revised: May 22, 2006
.