<
Irish Railway Record
Society
Tralee
Line Mini-CTC
OLIVER DOYLE
The
original mechanical signalling system installed in the latter part of the 19th
century had 10 block posts between Killarney Junction (Mallow) and
Tralee
- all with Railway Signal Co. lever frames. However, with
the closure of the smaller stations, Lombardstown, Rathcoole (not a block post),
Headford Junction, Ballybrack and Gortatlea on
9 September 1963
, the opportunity was taken to reduce the number of block
posts. Also three of the four branches, Kanturk, Kenmare and Farranfore had
closed leaving only Castleisland remaining. For more than a quarter of a century
there have only been seven operational block posts on the line with one,
Millstreet, switched out most of the time since 1988. The Mallow-Tralee line has
nineteen mid-section level crossings operated by gate keepers, four level
crossings at stations and one 4-barrier CCTV-monitored crossing.
The
Tralee Line mini-CTC was commissioned at
17:20
on
25 February 2005
and covers the railway from
Tralee
to Banteer inclusive. At Banteer it interfaces with the
existing mainline CTC controlled from Dublin Connolly. All signals and points
have their number prefixed with TL – Tralee Line. This is the third in an
ongoing series of mini-CTC projects
to be completed and represents an investment of
€11.5m.
The
Tralee Line Emergency Control Panel is located in the former Mallow South signal
cabin beside the Mallow ECP which covers the area of Mallow station and the line
as far as the Banteer down home signal. The system is currently being worked
from its ECP but will be eventually transferred to Connolly CTC. Thereafter the
ECP will only be used in event of a failure. The system was designed, installed
and implemented by IE’s own staff. The points, crossings and track were
installed by the local permanent way staff.
All
the station layouts were modified except
Tralee
and an important design consideration was the provision of
space for most platforms to be extended to 174 metres. This is the standard for
an 8-car railcar set of vehicles of 21 metres such as 2800 or 2900 classes. This
is, of course, more than adequate for the new railcars
just ordered, which are
maximum of six vehicles, each 23 metres in length. A second capital project is
dealing with the platform extensions and
these should be complete by the end of 2005.
A
major infrastructure renewal took place in
Tralee
in 1979 when the platforms were extended
and the
layout rationalised.
The points
at the eastern end and signals were converted to electric operation controlled
from the existing mechanical frame in the signal cabin. The original
Westinghouse-63 points machines, by now over 25 years old, were removed and
replaced by the same model of the latest design.
At
Farranfore, the Kerry Co-op siding on the up side, disused since 2001, was
removed and the station now has simply a mainline with a loop, sharply
contrasting to the 1918 layout when it was an important junction with 15
turnouts.
There
were two closures to allow final installation of track and signals prior to the
commissioning. The line from Killarney to
Tralee
was closed after passage of the 09.15 Tralee-Cork on
Thursday 10 February to allow installation of a new turnout at the Killarney end
of Farranfore station and pre-commissioning of points and signals.
Tralee
and Farranfore signal cabins closed as block posts and the
line from Killarney to
Tralee
became a permanent way possession under the control of the
Killarney signalman. The bay platform in Killarney was closed after the
departure of the
09:15
Tralee-Cork on Saturday 12 February for re-laying and
extension of the platform to accommodate 174m trains. The main platform as a
result is 275m long.
The
remaining section of the line from Mallow to Killarney was closed after the
passage of the
07:00
Tralee-Dublin on Monday 14 February. A possession was taken
of the line between the up stop signal MW813 at Killarney Junction (Mallow) and
Tralee
. Mallow ECP was switched in for the duration of the closure.
KILLARNEY
The
original station at Killarney, opened on
15 July 1853
, by the Killarney Junction Railway had a simple layout with
one short platform under the overall roof. However, with the opening of the
Tralee & Killarney Railway on
18 July 1859
the layout was altered to allow trains to and from
Tralee
propel from and to the main station. Today this is an
important commercial consideration as the station, the busiest by far on the
route, is close to the town. Many of the passengers arrive and leave the station
on foot.
In
the early years of the last century, ‘day excursions’ from
London
to Killarney became popular both via the London & North
Western Railways Holyhead-Kingstown route and via the Great Western Railway’s
new route via Fishguard-Rosslare opened on
30 August 1906
. The excursionists travelled on Friday evenings to the
respective Welsh port where they joined the steamer for
Ireland
at
02:30
or
03:00
and on arrival at
Kingstown
(
Dun Laoghaire
) or
Rosslare
Harbour
were taken by special train to Killarney and returning
Saturday evening to arrive back in
London
Sunday morning.
In
1907, Killarney main platform was extended to 200ft and the bay platform
repositioned to be on the opposite face (South side) of the extended main
platform. Previously the bay platform was on the same side as the main platform.
The
signal cabin was extended to 36 levers of which 3 were spare. On
23 August 1907
, Colonel von Donop inspected the new arrangements for the
Board of Trade and was unhappy with the arrangements for reversing trains to and
from the ‘Check Platform’. He wrote, “These cannot be regarded as entirely
satisfactory as they entail the backing of passenger trains and it is regretted
that the company has not seen its way to alter these arrangements”.
Ninety-eight years later and without any recorded incident the layout is
perpetuated but with the advent of railcars and push-pulls propelling of trains
will be eliminated as the drivers change ends for the movement. When the new
InterCity railcars are introduced in 2007, von Donop’s concern will be
eliminated 100 years on!
Prior
to the mini-CTC, Killarney, had the finest array of semaphore signals remaining
in
Ireland
– an honour which probably now falls to Rosslare Strand.
The opportunity was taken to extend the bay platform to 174 metres by moving the
turnout nearer Rathmore. During the closure for the mini-CTC commissioning the
platform and the adjacent mainline platform were extended by the platform
contractor, working long hours. The two relatively sharp crossovers – facing
and trailing – between the Mallow and
Tralee
lines were renewed with much longer crossovers allowing the
diverging speed to increase. Because of their increased length these crossovers
shortened the ‘
Check Road
’ and it was
necessary to extend this towards Rathmore. The title of this piece of track
dates back to non-corridor passenger stock when trains were stopped here and
ticket checkers boarded each compartment to ensure passengers were in possession
of a valid ticket. Some remains of the platform used by those early ticket
checkers are still visible. There was also a ‘check’ platform on the down
side and some scant remnants of this were uncovered during excavations for
signal bases and equipment boxes.
The
renewal of the plain track, two crossovers and
three turnouts on the approach to Killarney station needed careful planning to
ensure it could be replaced in seven days. The former station master’s field,
a long linear piece of ground parallel with the main line was levelled and
reduced in height to allow pre-assembly of the two crossovers and three
turnouts. When the line closed for commissioning of the mini-CTC two road
cranes, a 200-tonne and 400-tonne lift capacity, were brought in through the
shopping centre car-park and positioned as required. The cranes were used to
first lift out the old points and crossovers after they were cut into manageable
pieces and dumped out of the way. The new crossovers were then placed in
position. Any plain track was laid using rail-mounted earth-moving machines with
a spreader carrying four concrete sleepers at a time and positioning them in
place. The rail was then place in position and a total of some 200 welds as well
as insulated joints were required to complete the track work so the signalling
could be commissioned.
The
signals in Killarney station area were not pre-erected to ensure they did not
hamper the lifting in of the points and crossings.
Such
a major relaying project required a considerable quantity of ballast. A train
load was pre-positioned and worked in from Mallow. The train then went sometimes
Mallow and other times to Millstreet to where a large ‘ballast dump’ was
used to load the train using earth moving machines. Some ballast for Killarney
Yard was delivered by road and spread by earth moving machines.
A
feature of the Killarney layout for more than a century is the ground-frame
worked engine release at the buffer stop end of the main platform. This is
retained in the new layout worked by an electric panel located close by. It is
released by the Tralee Line signalman at either the Mallow ECP or the Connolly
Mainline CTC. The release can be given if the main platform track is clear or
has been occupied for at least 90 seconds. The turnout and traps, on the
adjacent line, were both renewed during the close down. This turnout was
pre-assembled on the main platform.
Before
the closure a locomotive was pre-positioned in
Tralee
and was used initially to test the signalling in
Tralee
before going to Farranfore and on to the outskirts of
Killarney to ‘prove’ that section. A second locomotive was used to test the
Mallow-Banteer section initially while the permanent way staff were installing
the points blades at Millstreet. The turnouts (without points blades) and traps
at both ends of Millstreet were pre-installed and the loop laid beforehand. The
test locomotive was then able to run to the Rathmore home signal. There was
a
major re-alignment and lengthening of the loop at Rathmore to facilitate an
almost straight platform extension. The complex layout at Killarney with, nine
points ends, nine running signals and four shunt signals was last to be tested
before commissioning.
EQUIPMENT
The
Tralee Line mini-CTC is worked by two Solid State Interlockings coded MWMS and
RETL. These operate as a single system and appear as one to the signalman. MWMS
interfaces with the existing Mallow signalling as well as working the Banteer
and Millstreet station areas. RETL controls Rathmore to
Tralee
inclusive.
While
the Tralee Line is an SSI based system, the engineering of the distant signals
is by relays. The SSIs consist of separate signal and points modules capable of
controlling two signals of up to four aspects. To avoid having to install a
signal module at distant signals use was made of the ability of the signalling
modules to operate relays. Relays were installed to operate the distant signal
aspects remotely from the module, which directly operates the associated stop
signal.
All
points are operated by Westinghouse Type 63 point machines. Automatic
normalising is provided for points from sidings at Banteer, Rathmore, Killarney
and
Tralee
. This means that if these points are in the reverse
direction for entry or exit from the sidings the points automatically revert to
the normal position after passage of the train or if the route has been set over
them in reverse and is subsequently cancelled by the signalman.
Three
aspect (green and double yellow) distant signals are provided except on the
approach to the terminal stations at Killarney and
Tralee
. At Millstreet, which had only a platform on the down side,
there is a 2-aspect distant signal in the up direction as it will be rare to
cross trains here in a ‘passenger only’ railway and trains would normally be
signalled through to Banteer. In the down direction the inclusion of Doneen
level crossing within ‘station limits’ made a 3-aspect distant practical.
Three-aspect distant signals were first used in the Waterford Line mini-CTC
project at Carlow and Bagenalstown and proved popular with drivers and offer a
saving on journey-time with less approach release signals. See JOURNAL 154.
Secure
train radio is provided from commissioning of the new signals. The train driver
is able to talk directly to the Tralee Line ECP signalman in Mallow. Line-side
telephones are also provided at signals and level crossings.
STATION LEVEL CROSSINGS
Four
of the six stations on the
Tralee
line have level crossings, Banteer and Rathmore were worked
by the signalmen as the signal cabins were adjacent to the crossings. Millstreet
level crossing is worked by gatekeepers as it was a block post which was
normally switched out, while Farranfore had automatic half barriers. On 13
February Farranfore was commissioned as a 4-barrier CCTV-monitored level
crossing, worked locally initially, until control is transferred to a central
location. A week later, Banteer was converted to 4-barrier CCTV monitored worked
locally. Millstreet will be converted shortly to a 4-barrier CCTV monitored
crossing when the road layout in the vicinity is modified. A 4-barrier CCTV
monitored level crossing could not be installed at Rathmore until after the
commissioning of the mini-CTC as the signal cabin was in use and has to be
demolished and the road alignment straightened to allow motorists improved
visibility.
MID-SECTION LEVEL CROSSINGS
Between
Banteer and
Tralee
there are 16 level crossings worked locally by gatekeepers.
Many of these were equipped with ‘Braker Point Marker Boards’. During the
installation of the mini-CTC a separate project was in progress providing all
these level crossings with standard colour light signals - stop signals 200
metres back from the crossings and distant signals a minimum of 1,000 metres in
advance of the stop signals. This eliminated the need for the Braker Point
Marker Boards and all these have been removed.
Gatekeepers
are advised of the approach of trains by the sounding of a buzzer. The timing of
the buzzer is usually based on the time a train enters the section and allows
time for a train to travel to the approach to the crossing. Where a mid-section
crossing is close to the station in rear, then alternative timing reference
points are used such as the trains approach to the station from the previous
section. Timing of crossings is simplified by the fact that most trains on the
line are stopping passenger trains travelling to the same line speed of 70mph.
Three
stations, Millstreet, Farranfore and
Tralee
, have mid-section level crossings close to the station and
the signalling for these is inter-worked with the station signalling. Doneen
level crossing, east of Millstreet, is incorporated into that stations
signalling. Approaching Farranfore from the Killarney side there are two
crossings close to the station, Dromore and Ballybane, and both have these have
been linked to the station
signalling. There
are two
level
crossings close to
Tralee
station, Clash and Rathass, both have high road usage and it
was essential that their closure to road traffic was optimised. To achieve this
and ensure drivers leaving
Tralee
are given a green aspect starting from the platform, a self
normal-ising key switch was installed on the platform at
Tralee
. When a train is about to depart the station the Depot
Controller activates the switch, which indicated to the mini-CTC system that a
train is about to depart
Tralee
. The audible initiation
is then
given to
the two
level
crossings so the gatekeepers can close the gates and the advance starting signal
from Tralee, which is also the protecting signal for the gates, can display a
green aspect and, consequently, the starting signal from the platform give a
green aspect. If both level crossings are not closed to the road traffic a train
would leave
Tralee
platforms on a yellow aspect and be prepared to stop at the
advance starting signal thereby losing time.
The
4-barrier CCTV-monitored crossing at Minish, near Killarney, continues to be
temporarily monitored from Killarney former signal cabin pending transfer to a
central location.
There
are now no semaphore signals between Mallow and
Tralee
.

Copyright © 2005 by Irish
Railway Record Society Limited
Revised: August 16, 2005
.