
Irish Railway Record
Society
TRACK
Dublin-Dundalk-Border
Plasser
& Theurer ballast cleaner No. 780 has largely been used on the Dublin-Cork
line in recent years and was usually based in Portarlington when not in use.
However in January, it was used during weeknight possessions in the Mosney area.
Limerick-Rosslare
Europort
The Limerick Junction-Waterford line was closed for six weeks commencing
on Monday 18 April to allow re-laying of six miles with second-hand materials.
All passenger trains were cancelled and substituted by bus, although the line
re-opened for a Waterford-Claremorris Knock special, 072 + EGV + 8 Mk III, on
Sunday 1 May and the RPSI steam tour on 15 May. There are no scheduled freight
trains on the line outside the beet season. The cancellations also included the
17:15
Limerick Junction-Rosslare Europort and
20:30
Rosslare Europort-Waterford, but not the
07:00
Rosslare Europort-Waterford and the
17:25
return. By early May, 12/3 miles
between Cahir and Nicholastown level crossing MP381/2-431/4
had been re-laid. There had previously been a line closure between
08:00
on Wednesday 2 to 17:00 on Monday 7 February.
There
were mid-morning closures on Tuesday-Thursday between Limerick-Limerick Junction
during late April and early May for tamping and loading rails.
Ballybrophy-Killonan
Junction
The line was closed completely on several occasions during the winter and
spring to allow approximately two miles of re-laying with second-hand jointed
track and other work take place, particularly between Birdhill and Killonan
Junction. Work between
08:30
on Friday 28 and
16:00
on Monday 31 January included tamping and levelling track at
Lisnagry level crossing, which is on the main N7 Dublin-Limerick road. All
trains were cancelled, including the Kilmastulla-Limerick cement factory shale
trains.
To
allow re-laying with second-hand materials between Nenagh and Silvermines
Junction the
09:45
Ballybrophy-Limerick and
15:00
Limerick-Ballybrophy were substituted by bus from Tuesday 15
until Thursday 17 February and from Tuesday 1 until Thursday 3 March. There was
a complete line closure from
08:30
Tuesday 8 until
17:00
Thursday 10 March. Re-laying with second-hand materials has
taken place between MP311/2-321/2.
The
track through Cloughjordan (MP20) has been re-laid with second hand jointed
flat-bottomed rail on timber sleepers.
Dublin-Sligo
Track work continues in advance of the commissioning of Mini-CTC, including
installation of a new crossing loop to the north of the existing platform at
Carrick-on-Shannon.
Cork-Cobh
The line was closed completely between Glounthaune (Cobh Junction) and
Cobh
from Thursday 21 April until
16:00
Tuesday 26 April for yard rationalisation and to renew No.
19 crossover in
Cobh
. The connection to the goods store siding (No. 16) and
associated disc signals were removed.
Dublin-Galway
In
Athlone, the turnout to the Moate line was renewed in an overnight possession on
Thursday 10/Friday 11 March.
Drogheda
(Platin)-Navan
Approximately two miles of track has been re-laid with second-hand
materials between MP83/4-12.
Cork-Midleton
Some vegetation clearing has taken place. It started at Midleton and was
working towards Glounthaune.
Weedspray
The annual weedspray season started on Thursday 14 April when locomotive
No. 172 hauled the spray train from its base in Portlaoise to
Cobh
. Athenry-Ennis was sprayed on 26 April and Drogheda-Navan on
10 May.
BRIDGES
AND TUNNELS
Following
major repairs as noted in JOURNAL 156, further strengthening work on Slatty
viaduct (UB421 at 172 miles 316 yards) between Glounthaune (Cobh Junction) and
Cobh
took place at night commencing 31 January. Initially the
last two trains in either direction were substituted by bus between Glounthaune
and
Cobh
, but from 21 February the
20:00
Cork-Cobh and
20:30
Cobh-Cork were also substituted by bus. The major repair
work was completed on the 11 April. The bridge now has a concrete deck with the
rails embedded in rubber.
UB37
on the Portarlington-Athlone line over the
Grand Canal
at Tullamore received major upgrading including a new deck
during a line closure from
08:00
on Tuesday 15 to 03:00 on Friday 18 February. The new deck
includes a concrete floor similar to that installed in the rebuilt Cahir bridge.
The line closure was during a quiet period for mainline passenger traffic, with
passenger trains substituted by bus between Portarlington and Athlone. Freight
trains were cancelled completely. The rock cutting on the Portarlington side of
Tullamore was also excavated during the line closure.
UB41
at 25 miles 888 yards on the Nenagh branch was renewed on the 19 April with
pre-cast concrete units.
Major
repairs are being carried out to span No. 12 of the
Barrow
Bridge
(UB140 Waterford-Rosslare). This work is due for completion
in early June when the span will then be painted.
A
new 79-metre long four-span underbridge for the M1 motorway was installed at
Ballynahatten (MP563/4-57) on the Wellington Bank north of
Dundalk
during a full line closure over Easter Weekend. The line was
closed from
22:15
on Holy Thursday 24 March until
05:00
on Tuesday 28 March. Construction of the concrete structure
for the new bridge began in November 2004 adjacent to the line. Following the
closure, the first task was the removal of the existing Harp Lager / Dundalk
Town Council water main embedded in the embankment. This was replaced by a new
main.
Then
track and ballast were removed along with a 100-metre section of the embankment
totalling approximately 20,000m3. The 7,500-tonne concrete structure
was then slid 44-metres into place at a speed of 6 metres per hour. The bridge
had been built on a guide raft, which provided directional support and anchorage
from which hydraulic jacks could pull the bridge into place. During the slide a
mixer injected a bentonite mix (inclusive of micro balls and additive) between
the bottom of the bridge and the guide raft. This construction method, known as
the 'Autoripage' slide technique was chosen to minimise disruption to rail
traffic. The four spans are 17-metres, 23-metres, 23-metres and 16-metres long.
When
the bridge was pulled into place concrete grout was then pumped or poured
between the inclined walls of the bridge and the slope. Grouting of the base
slab then took place followed by placing of precast transition slab units. The
embankment, ballast and rails were subsequently replaced and the line re-opened
with a 25-mph speed restriction.
Two
permanent way trains were at the site on Easter Sunday 27 March in conjunction
with re-instatement of the line. Locomotives Nos. 124+162 were on one track,
while 185 was on the other. This was the first appearance of a 121-class north
of
Dundalk
for some time.
The
remainder of this article appears in IRRS Journal number 157, published June 2005.

Copyright © 2005 by Irish Railway Record Society Ltd.
Revised: August 23, 2005
.