|
| |
< 
Irish Railway Record
Society

Mallow-Banteer-Newmarket
J. O’MEARA
Since
previously writing on the Mallow-Fermoy-Mitchelstown railway, a few additions
have since come to mind.
In June 2001, a new footbridge
incorporating a lift was opened at the South end of the Mallow platforms,
replacing an old structure which catered for foot passengers only.
Previously, people with disabilities, or those with heavy luggage, had to
walk across the tracks to the island platform accompanied by a staff member.
During the week ending
15 September 2002
, the
Fermoy
Bay
was shortened by 100 metres.
A temporary buffer stop was erected to facilitate the casting of a
concrete buffer stop. A new
engineer’s siding, 138 metres long, was constructed off the Down Long siding,
which has two turnouts.
A important structure south of
Mallow was the Blackwater masonry viaduct, known locally as the ten arches. It
was destroyed by explosives during the Civil War 1922/23.
Partial services were maintained with
Cork
, albeit with many delays.
A temporary Mallow South station, with an 8-lever signal cabin, was in
use during the bridge’s reconstruction.
The heavy expenditure involved in
this work resulted in the Company issuing an ultimatum to the Government that
unless financial assistance was forthcoming the suspension of rail services
throughout the system was inevitable. The
Government, conscious of the need for a viable railway system, did not allow
such drastic action to take place. In
addition to money for the viaduct, large amounts were allocated for the
restoration of many bridges, and for the repair or restoration of damaged or
destroyed signal cabins. Finance was also forthcoming for repair of many
locomotives, which were either damaged or derailed.
Several attempts were made at Mallow locomotive shed to derail engines by
driving them into the well of the turntable, but the sudden appearance of units
of the regular army thwarted such actions.
Between May and July 1922, several
attempts to blow up the viaduct failed as many of those involved were killed,
and others arrested and tried in court. However,
later in the year, two of the ten arches were destroyed in an attack.
Local clergy and other dignitaries
appealed to those intent on further damage to desist, but to no avail, as a few
days later the viaduct was totally destroyed, leaving no direct rail connection
from Mallow to
Cork
and Kerry.
Thousands
of people in the
Cork
area found themselves out of work due to the dislocation of
services, particularly as food supplies and raw materials could not get through
over the north Kerry line.
The GS&WR considered the
destruction of this major bridge to be, by far, a serious obstacle to a quick
restoration of services to Cork and parts of Kerry.
The estimated cost of the damage was £135,000 (€171,415).
Telegraph and telephone lines, south of Mallow, were restored after seven
days.
General Michael Collins, visited
Mallow on
26 August 1922
, and said he hoped that attempts would be made to remove
debris from the bridge, and that all other transport matters in the Mallow area
would be dealt with speedily. Unfortunately,
he died in an ambush a few days later.
The GS&WR was instructed to
start work immediately and have the bridge re-opened as soon as possible.
Before work could begin, rubble had to be removed from the public roadway
and from the riverbed directly underneath. With
the help of a contractor and army trucks, the job took four days to complete.
The erection of scaffolding proved an onerous task due to the large
amount required to cover both sides of the viaduct.
With no direct rail connection to
Cork
food supplies were getting low.
At the request of the Provisional Government, a new daily passenger and
cargo service, by sea, was introduced towards the end of August 1923, between
Dublin
and
Cork
. The first
sailing carried 104 passengers, 80 tons of assorted food and 590 bags of mail.
Ships involved were Lady Kerry
and Brandon.
Rail services from
Dublin
terminated at Mallow and passengers for
Cork
had to make their own way, mostly on foot, to the temporary
Mallow station from which a local service connected with
Cork
. During reconstruction the surrounding area was under a
24-hour military protection. To save
time the bridge was replaced by steel, even though the cost was £5,000 higher.
After building was completed on
16 October 1923
, rigorous testing took place for a week before it was
declared fit for traffic.
A headline in the Irish Times of
17 October 1923
reads: “General rejoicing!
Bridge again open for traffic.” It
continued by saying that the commercial community of
Cork
and the South of Ireland rejoiced today at the reopening of
the River Blackwater railway bridge near Mallow.
The President and his party
travelled by special train from
Dublin
. It was composed
of four saloon coaches hauled by locomotive No. 405 and averaged 64mph.
With the President were Government Ministers, the Postmaster General,
members of the GS&WR Board, and Operating and Engineering staff.
After a short delay at the platform, the train moved forward to the new
bridge decorated with flags and bunting, and on which a military guard of honour
was placed. President Cosgrave then
drove the train over the new 517ft bridge. The
contractors were Sir William Armstrong-Whitworth of
Glasgow
; and for the removal of debris, T. J. Moran and Co.,
Cork
.
Shortly after the line reopened, a
member of the permanent way staff, while carrying out minor repairs between
Mallow and Lombards-town, was shot dead. Other
members were warned that, if they continued to work, they would receive the same
treatment.
By mid-December the Government had
not honoured its commitment to reimburse the GS&WR for repairs to the
viaduct which had cost £140,000, £5,000 more than the original estimate.
A reminder of this claim was reactivated, plus further claims for damage
to Mallow North and South cabins, cost £350; damage to Telegraph and general
offices: £2,000. That was not the
end of the destruction, for on
30 October 1923
, the entire station, including the stationmaster’s house,
were completely gutted, giving rise to an additional claim of £5,000.
All claims were eventually settled in January 1924.
Apart from regular maintenance and
painting, the bridge never needed any repair until
5 March 1995
when work began on replacing its decking.
This caused very little disruption to traffic - a tribute to the
Company’s infrastructure staff.
Single line working was in operation
while each side was being repaired. The down side being done first and for this
trains to
Cork
were routed along the up line from the station, through
Killarney Junction and over a new crossover to the down track.
Work was completed on
23 April 1995
.
Stage two started immediately by
slewing part of the up to the down to cross the viaduct and re-join the up a few
yards north of the bridge. Signalling
remained the same throughout. A
25mph speed restriction operated while the project was in progress.
Work was completed by
9am
on
Sunday, 11 June 1995
. Immediately the
job of restoring signalling and track work began.
Temporary buffer stops, telephones, a route indicator and speed
restriction signs were salvaged. While
the decking renewal was taking place, Mallow Emergency Control Panel was
switched in and controlled traffic in the area Charleville/Rathpeacon and
Killarney Junction/ Banteer.
Mallow beet siding, at M.P. 2¼, was a hive of activity during beet
campaigns up to 1978, when the carriage of sugar beet in loose-coupled wagons
was terminated. During that period
the signal cabin, with a switch out apparatus, was manned continuously for 13
weeks, with part Sunday working. On
other occasions it switched in for the despatch of wagons of pulp and sugar.
Entrance to the siding was via turnouts at both ends of the yard.
In the late 1970s, when the CTC was
extended the beet sidings were connected by a facing turnout at the Mallow end
worked by a ground frame released by the CTC.
A 55ft turntable was available. During
the beet campaigns of 1939 to 1945, eleven steam specials served the factory.
Lombardstown, at M.P. 5½, was the
scene of an accident on
5 August 1912
, when an excursion, returning from Killarney to
Dublin
, derailed after it entered the up loop.
It resulted in the death of one passenger, and, of the 256 who travelled,
98 sustained severe injuries. This was fully described in JOURNAL No. 82.
The station had a signal cabin at
the Killarney end of the station with 16 levers (2 spare).
Close by was the station level crossing worked by the signalman.
A single platform, 275 feet long, was south of the station and housed the
stationmaster’s premises, lamp room, and offices.
A goods loop was 375 feet long. The
station was protected by home and working distant signals.
Entrance to the loop was signalled by disc, whilst that at east, or
Mallow end was governed by a ground frame which was controlled by the releasing
of a “King Lever” in the signal box. The
goods yard, with a loading and a cattle bank, had a small goods store, entered
from each end of the main line.
Banteer, at M.P. 10¾, was the junction for the Newmarket Branch.
The line, which opened in 1889, was constructed under the Kanturk and
Newmarket Light Railway Act of 1881, and was a baronial guaranteed enterprise,
with a capital of £40,000 at an annual interest of 4%, payable in perpetuity.
It diverged at the west end of Banteer, and extended in a northerly
direction for approx. 3½ miles to Kanturk, and thence, in a north-westerly
direction to
Newmarket
. The branch was
8¾ miles. It crossed the River
Blackwater just outside Banteer, from which point it was on a rising gradient
almost throughout to
Newmarket
. The ruling
gradient was 1 in 60 on leaving Banteer. Curves
were relatively easy, the sharpest, two of 20 chains radius.
There were twelve bridges of which seven were under and of steel
structure. The remainder were
masonry. The Blackwater bridge had
five steel spans, each of 63 feet. A
lattice girder bridge over the River Duala, near Kanturk, had one span of 70
feet. The
Duala
, from this point, flowed downwards parallel with the line to
Banteer, and into the Blackwater. A
driver with whom I travelled told me he poached many a salmon there.
There were seven public road
crossings. One was on the main road
between Mallow and Killarney, and signalled both ways.
Apart from one at Kanturk which was operated by the station staff, all
others were operated by female gatekeepers at a wage of 70s (€4.44) week each.
The line was laid with 74lbs rails in 1889, except for a ½ mile of track
outside Banteer which had been re-laid in 1920 with second-hand 83lbs rails.
In 1953, when the branch was under
threat of closure, the Secretary of the Branch Lines Tribunal Committee
requested Brendan McGrath, Solicitor CIE, to confirm the point that the branch
of 8 miles, 5 furlongs, and 9 chains, wholly situated in the County of Cork,
commenced at a point 160 yards from Newmarket Demesne, ran along its southern
wall and terminated by a junction with the Killarney branch at the GS&WR
opposite the east end of Kanturk platform. This
request baffled the Solicitor as no mention was made in legal terms, as far as
he knew, of any changes in title. He
was unable to trace any Act or Order relative thereto.
The Cork District Engineer, S.
Harmans, responding to the Chief Engineer’s request to clear up what appeared
to confuse many Company Executives, stated that on old maps and documents
relating to the Mallow-Killarney line, Banteer station was called Kanturk prior
to the construction of the Newmarket Branch.
This accounted for the name of Kanturk, instead of Banteer, in the
Kanturk and Newmarket Railway Act of 1887. In
1892 the name of Kanturk was changed to Banteer, with Kanturk going to its
proper location. It remained a
station in its own right until its closure on
2 February 1963
.
From date of opening on
1 April 1889
, the Kanturk & Newmarket Co. operated the line for three
years, using a locomotive aptly named
Newmarket
, which was borrowed from
Worthington
, the Contractor for the line.
In 1892 the GS&WR purchased the line, which was in a bad state of
repair for £58,000.
The carriage of freight and
livestock peaked in 1928; so too did the number of passengers carried.
By 1931, due to an inordinate slump in the export of livestock, and a
trade war with
Britain
, the GS&WR found itself in a very serious financial
crisis. In 1931, a severe pruning of
rail services on many branch lines was suggested - strangely, the
Newmarket
branch was not included, even though in the same year losses
were £1,343 (€1,705). Road
transport, which had been developing rapidly since 1929, hit hard at the rail
transportation of general merchandise and livestock.
To
cut costs a Sentinel-Cammell steam railcar was introduced, but because of its
unpopularity with public and staff, was withdrawn after a few weeks
and steam traction took over.
Passenger carriages were a six-wheel
compo, a small third and a six-wheel guard’s van.
On the weekend
18 August 1928
, the GS&WR issued a memo as follows: ‘Bogie stock over
50 feet in length are not allowed to work on the
Newmarket
Branch’. To my
knowledge this order was never rescinded. The
locomotive was either a small
4-4-0
or the ubiquitous 0-6-0 J15, which had the maximum axle load
of 14½ tons.
Cork
was the supplier, with Mallow attending to minor repairs.
The next suggestion of a passenger
withdrawal was investigated in 1934, but it was recommended that the proposal be
withdrawn as the Dept. of Local and Public Health, in a letter to the Bus
Department, stated that owing to the condition of sections of the public roadway
between Roskeen Bridge and Kanturk, the road, at that time, could not be
approved for use by buses. Another effort was made in 1935, but again withdrawn,
as the cost of an extra bus was prohibitive and road conditions had not improved
from the previous year. The Board
decided that further investigation be made regarding the improvement, if any, of
the roads, and if it was really necessary to replace rail services by road
transport.
By 1938, finances had greatly
improved, but not to Management’s satisfaction; again feeding rumours that the
branch, and many others were due for closure.
In February 1939 such rumours were quickly scotched as the threatened war
in
Europe
seemed so imminent that talk of line closures was set aside.
When hostilities broke out in
September 1939, services on the branch line were, a 7am Mallow to
Newmarket
goods, returning at
12.35pm
after working the first passenger to and from Banteer.
Other workings: departure
Newmarket
at
1.50pm
,
3.25pm
and
5.10pm
, returning at
2.30pm
,
4.10pm
and
8pm
. In between
trips a light engine ran, as required, from Banteer to Kanturk to shunt the yard
due to the large number of wagons requiring placement for loading and unloading
– for this 40 minutes was allowed. This occurred frequently, particularly when
specials of maize ran from
Cork
, and whose engine returned to Mallow in the interim.
A fuel crisis then developed and
from
2 June 1940
, services were drastically curtailed, leaving one mixed and
two passengers to cater for the public, Monday to Saturday, with an extra
working from Mallow to
Newmarket
and back on Thursdays and Saturdays.
Times from Banteer were
9.25am
,
12 noon
, and
4pm
, returning at 11.20am, 3,15pm and
10pm
. All services
were then worked by the Mallow-Newmarket goods engine which ran over the branch
as mixed, due to the absence of a crew being based in
Newmarket
.
Another year passed and yet another
fuel crisis occurred. Stocks had
dwindled to an all time low with no prospects of replenishment.
This resulted in one goods and one passenger providing a service.
Worse was to come when coal was unavailable and skeleton services, which
were still in operation, were withdrawn on and from
24 April 1944
.
When hostilities ceased in June
1945, the shortage of coal supplies eased, but it was not until the middle of
the following November that the CIE announced that a partial service would
resume on
17 December 1945
on many branch lines, including the
Newmarket
. It was one of
the lucky ones, as many others did not re-open.
A major fuel crisis in
Britain
during January/February 1947 was caused by severe weather
conditions which resulted in coal not being mined in
England
or
Wales
. Services on all
branch lines were cancelled, and those on other lines were severely curtailed.
When British coal again became
available the timetable gradually improved on main and secondary lines.
The General Manager of C.I.E. stated that restoration of services on
small branches was being considered. Towards
the end of August 1947 the worst fears were realised when it was announced that
there would be no passenger or freight trains running on many branches,
including
Newmarket
. This statement
was greeted with anger and dismay by local traders, livestock dealers,
exporters, and factory owners. The
Company announced, after Government pressure had been brought to bear, that
arrangements would be in place to serve the livestock fairs at Kanturk and
Newmarket
, in addition to the carriage of maize from
Cork
to Kanturk. Sporting
occasions were to be catered for as were passenger specials.
Under the Transport Act of 1950, CIE
applied, in April 1952, for the following exemption orders:
 |
To
exempt the Board from its obligation to operate all special services of
trains for merchandise on the
Newmarket
which were in operation immediately before the 1st
day of June 1950. |
 |
Exempting
the Board from the obligation to restore all or any services which were
temporarily discontinued as and from 27th day of January 1947,
under and by virtue of Emergency Powers – Reduction of Railway Services
Order 1944. |
These requests were made on
1 October 1952
. Again, strong
objections to these proposals were made by many supporters of the Railway.
In the event of the Tribunal refusing such requests, the Deputy Chief
Engineer, Mr. Somerville-Large, requested the Cork District Engineer to forward
the maintenance cost in case of the 1939 timetable being restored, as well as
the total cost which would be required to enable its restoration.
£180 (€228) and £402 (€510) were the respective figures quoted.
The Tribunal sought all documents
relative to the Company’s application and a report was filed after a six
months study. The Board was worried
about the length of time it took for conclusion, as the Government intimated
that on
31 March 1955
it would allow the Supply and Services (Temporary Provisions
Act 1946) and Reduction of Railway Services Order 1944, No. 35, to lapse.
This posed the possibility that if challenged in court the Board would be
compelled to restore a service on many branches that existed in 1944.
The
engineer, in a further report, stated that the sleepers had been maintained by
patching, and generally they, along with rails, were in reasonably good
condition. However, some rails would
need to be replaced before the line could be re-opened to regular passenger
traffic. He also stated that the
steel bridges were sound, but badly in need of painting, and due to a settlement
the
Blackwater
Bridge
, which bore a 5mph limit, should continue with such a
restriction. He further intimated
that as far as his Department was concerned the closure of the branch would be a
small economy, estimated at £300 (€381) per annum, and that no further
savings could be made until the line was abandoned.
The withdrawal of train services
would not eliminate all the expenditure on the maintenance of way and works as
statutory liabilities had to be maintained.
£200 (€254) was the figure quoted.
From 1949 to 1953, and in 1959,
special excursions ran as follows:
 |
9 September 1949
–
Newmarket
to
Cork
, sporting, 681 passengers off branch. |
 |
13 October 1950
– to Killarney, sporting, 501 travelled. |
 |
29 June 1952
and
24 August 1952
– to Banteer, field sports, 493 and 389 passengers
respectively. |
Figures
quoted were in stark contrast to 1939, when 9,246 were carried by regular
services in addition to 1,067 who travelled to Youghal,
Cobh
, Killarney and Banteer.
The week ending
Saturday 27 June 1959
, a party of 30 IRRS members did a three day tour of the
Foynes, Fenit, Castleisland and
Newmarket
branches. For
the Saturday outing to
Newmarket
, the
10am
goods from Banteer was mixed, worked by a DE with altered
running.
|
|
Arr |
Dept |
|
Banteer |
|
11.35 |
|
Kanturk |
11.50 |
12.00 |
|
Newmarket
|
12.30 |
2.15 |
|
Kanturk |
2.45 |
3.00 |
|
Banteer |
|
3.15 |
A
DE, bogie coach and van left Mallow for Banteer at
10am
and returned at
4pm
. I can safely
say that this was the last mixed train to travel over the Branch.
The weed sprayer paid its annual
visit from 1948 to 1953, and from 1956 to 1961.
Apart from ash specials from Mallow, stone ballast trains have never been
recorded as visitors.
On the 2 and
3 February 1954
the Transport Tribunal convened meetings at Kanturk to hear
objections to the branch’s closure. The
objections were lodged by Cork County Council, Kanturk and Newmarket Parish
Councils, RGDATA (Grower’s Association) and 19 individuals.
Banteer, in the event of total
closure, would need alterations to the goods yard at an estimated £3,000
(€3,809). Figures showing the cost
of operating the branch for four months in 1953 and 1954 showed losses of £141
(€179) and £163 (€207) respectively.
On
5 February 1954
the Secretary of the Tribunal requested the Board to furnish
the following particulars:
 |
The
capital cost of providing the cheapest and most suitable type of a dual
purpose Diesel unit for use on the branch. |
 |
An
estimate of the cost of operating a Diesel unit to handle livestock and
merchandise. |
 |
An
estimate of the rail receipts accruing to the line as a result. |
In answer they
were £5,500 (€6,984), £6,500 (€8,253)
and £2,388 (€3,032) respectively.
On 16 October, the Tribunal issued
its findings. It granted CIE an
exemption from the obligation to operate the services of passenger trains as
specified in Part 1 of the Schedule. It
was also exempted from the obligation to operate all or any of the services of
passengers and merchandise as specified in Part 2 of the schedule.
It exempted the Company from the carriage on all services of special
trains for merchandise on the railway between Banteer and
Newmarket
which were in operation immediately before
1 June 1950
, except the running of specials on the said line for
conveyance of cattle from Kanturk and
Newmarket
livestock fairs.
The Board of CIE was not pleased
with this limited order, and it was challenged by the General Manager, Mr. Frank
Lemass, who requested a meeting with the Secretary of the Tribunal and the
Company’s Solicitor to discuss whether there was a limitation order on the
period of operation. However, the
Traffic Manager, Mr. D. Stewart, stated that he was against such a suggestion,
and said that the matter should not be proceeded with, as it would be difficult
to make assertions that the order was not reasonable, since the Tribunal had
been considering the evidence of both the Board and the objectors over a long
period, thereby making its decision on the weight of evidence produced.
The Board then decided that the
branch should be served by a lesser-powered diesel, thereby keeping the line
open for all types of freight and livestock traffic.
The type of locomotive power suitable to handle wagon loads but not
suitable for passenger trains was the ideal choice.
In January 1955, it was decided to purchase a 130hp Deutz costing £5,500
(€6,984). It was geared for a
maximum speed of 15mph hauling 8 wagons and a 10 ton brake van.
Allocation of staff to be in place on opening day was: Banteer –
stationmaster, three signalmen and one porter.
Kanturk – halt keeper and one porter.
Newmarket
– halt keeper.
At the re-opening, traffic at
Kanturk was so heavy, both inwards and outwards, that it was decided to upgrade
the station by putting a stationmaster in charge.
On
14 March 1955
, a Parliamentary question was raised as to when it was
proposed to reopen the branch. In
reply, the traffic manager stated that he was not in a position to specify any
date, as the Chief Mechanical Engineer could not give a definite time of
delivery of the Deutz locomotive and, he added, pending such delivery it was not
proposed to reopen the line with other type of locomotive power.
An interim timetable for one goods each way was proposed; - Banteer
depart
9.30am
, Kanturk 9.55/10.15,
Newmarket
arr.
4.10pm
. During its
four-hour stay in
Newmarket
the engine and van often returned to Banteer to clear any
overload left behind off the earlier service.
There was no engine shed for
overnight stabling in Banteer, so the Deutz was parked as near as possible to a
sheltered area close to the signal cabin, where it was also under secure
observation.
Newmarket
was also suggested as its base, but to keep running mileage
at a minimum, Banteer was chosen.
The Operating Department said it was
not prepared to agree to the closure of Kanturk Signal Cabin because of the
station’s heavy traffic, particularly from ‘maize’ specials from
Cork
, and livestock fairs. It
proposed to work the two sections by the Train Staff and Ticket system, and to
close Newmarket Signal Cabin.
The first of the three Deutz
locomotives arrived in
Dublin
in October 1955. It
was not until the following May – 7.5 months later – that G601 was sent to
undergo trials and driver training on the branch.
These proved successful and the line was re-opened on
Friday 1 June 1956
.
The new timetable showed a
10am
Banteer departure instead of a
9.30am
as originally planned. Extra
time, in excess of the twenty minutes allocated, was allowed for shunting in
Kanturk if necessary. A
3pm
return from
Newmarket
remained as originally scheduled.
At a subsequent banquet in Kanturk the Traffic Manager, Mr. D. Stewart,
stressed that the occasion was experimental and that the line’s continuance
would depend on the volume of traffic offering.
To get into the spirit of a joyous celebration, G601 was brought back
light from Banteer as an added attraction for the many enthusiasts and the town
people.
Paid gatekeepers received 31s
(€1.33) a week to operate the gates, a figure arrived at in view of the new
limited service passing through.
The branch continued to prosper in
every way but this did not sway the Board of CIE in 1962 when it decided that
many minor branches, including
Newmarket
were to be closed permanently.
In a press release of Friday 30 November 1962, the Board stated that the
rail connection between Mallow and Banteer would enable merchandise to be
carried by a combination of road and rail transport, with Banteer as a transfer
depot, and that it would cater for the variable demand for the carriage of
livestock, and for any seasonal or occasional traffic previously carried by rail
on a wagon load basis. It was
announced that the Board had completed an investigation into the economies of
operations on the
Newmarket
branch, solely on direct costs, and taking no account of
many normal overhead charges. The
result showed that revenue amounted to £1,349 (€1,713), while expenditure was
£3,000 (€3,809), showing a loss of £1,651 (€2,096).
The demise of the branch occurred on
3 February 1963
. Despite many protests, wagons were cleared off the branch
on the previous day. Anything that
could be salvaged, such as furniture, clocks, staffs, and hand lamps were sent
to Mallow in a covered wagon known as a ‘Hard Top’.
‘C’-class locomotive No. 221, hauling eleven wagons and van, worked
the last scheduled train.
To enjoy oneself to the full, for a
steam enthusiast like myself, a footplate trip is a perquisite.
Here, good banter, local knowledge, and liquid refreshment from the ever
present black can are among the main ingredients and attractions.
Therefore my planned trip from Mallow to Kanturk for its Livestock Fair
was eagerly anticipated. I was most certainly not disappointed.
Locomotive 104, a
Cork
0-6-0 engine, was the motive power to 25 cattle wagons and
van.
The thoroughly washed and
disinfected wagons were hauled to the ground disc, south end turnout of goods
yard. There we awaited the hand ring
and miniature staff for Lombardstown, which bore the inscription ‘Killarney
Junction for Mallow’ on one side and Lombardstown on the other.
Before proceeding the signalman in the South cabin had to obtain
permission to do so from his counterpart in the north box.
A
7.30am
start brought us along the up main line, crossing the ten
arches bridge as we briskly passed Killarney Junction, where a sharp 40 mph
curve was negotiated.
Killarney Junction had special rules
for its operation.
 |
Trains
were accepted from Lombardstown, or beet siding, as far as the branch home
signal, when an up train was on from Mourne Abbey, the road from the branch
being trapped. |
 |
When
two trains were accepted simultaneously, and it was desired to give
precedence to the branch train, the train on the main line had to be stopped
at the junction home signal and the signalman had to satisfy himself that it
had done so before any attempt was made to reverse the points. |
 |
When
branch down trains ran from Mallow station to Killarney Junction, trains
could not be accepted from Mourne Abbey, or from Rathduff, if Mourne Abbey
was switched out, or from
Blarney
, if the previous two were switched out, until the branch
down train had cleared the Junction points and Track Indicator in the cabin
showed ‘Clear’. Track and
signals were then set up for main line working. |
Webb’s
siding, at MP ¼, catered for an adjacent flour mill.
It had no run around facility and it was permissible to propel a maximum
of 12 wagons and van from Mallow station into the two sidings.
A shunter, who acted as guard, travelled as brakes man in the van, in
front of the train. The siding was
controlled by a ground frame and a one-staff subsidiary instrument.
A train could therefore be locked in the sidings and the mainline be
clear for the passage of trains. The
siding closed on
23 September 1962
.
We continued our journey in a
westerly direction by passing, on the right hand side at MP 1½, Mallow Beet
Siding. Its signal cabin was
switched out, making the section Mallow South/Lombardstown.
Gradients from here on were easy, as we passed New Berry East and West
level crossings. A fall of 1 in 195
gave way to a gentle rise as Lombardstown, on the level, was reached.
On
December 22 1922
, during the Civil War. Lombardstown was raided.
A wagon was taken from the goods yard and pushed into the Banteer section
where it derailed as a rail had been removed.
A second wagon was also derailed at the platform, again due to a lifted
rail. The goods store was attacked
and looted. Spirits, tea, bacon and
sugar were taken. By January 1922,
several small under bridges were in poor condition and a speed limit of 10mph
was imposed between MPs 2 & 2¾ and between MPs 5 & 6, while 20mph was
the limit through Banteer. All
temporary speed restrictions were removed in July 1923.
Lombardstown, being a quiet rural
station. did not generate much traffic. Revenue
came from a few passengers travelling to Mallow, wagons of stock and Sunday
sporting excursions. Its mainstay,
however, was the large quantities of milk and butter forwarded to
Dublin
and
Cork
. The station had
been reduced to a halt under Mallow, before closing on
9 September 1963
.
After exchanging staffs we moved
swiftly across the level crossing as our journey got more arduous with inclines
of 1 in 134, 197 and 430 being a feature to MP9½.
From there on falls of 1 in 151, and 270, brought us into Banteer at MP
10¾. Banteer, a block post, with miniature ETS staff working with Millstreet
and Lombardstown, and large staffs with Kanturk, dealt in livestock, maize, coal
and Guinness, and was signalled for two-way running with direct connections to
the Newmarket Branch.
The 18-lever signal cabin was at the
west end of the station, adjacent to a level crossing.
No watering facilities were available.
The branch platform and run around loop were at the back of the station
premises. A stationmaster was in
charge. At the Mallow end of the
complex a long loading bank once catered for livestock and maize, but now is
used exclusively for ballast loading.
On
18 November 1922
Banteer signal cabin were destroyed by fire.
Its points and chairs were broken and the rails were torn up.
Its only source of income is from
regular passengers and occasional sporting events.
As our journey resumed to Kanturk
the
Bogeragh
Mountains
with its scenic valley to our left was in sharp contrast to
the rich, flat agricultural land on our right.
The Banteer signalman informed the driver that we were to go to
Newmarket
with a wagon of bagged cement, and a second wagon of
permanent way material, picked up in Banteer.
This was an added bonus.
With the gentle nudge of the
engine’s regulator we moved steadily over the gates and swung in a sharp
right-handed curve over the 5mph River Blackwater bridge.
Progress was steady for the next three miles, with No. 104 blowing a fine
head of steam. After a ¾-mile climb
of a 1 in 60, Kanturk was reached at 9.15am
where, even
then, cattle
and sheep
were
awaiting loading. After wagon
placement we set out for
Newmarket
, again with a large section staff.
Although some of the gradients were easy, those of 1 in 165, 150, 100, 90
and 60 presented some difficulty. Imagine
how difficult it would be hauling 25 wagons and a van for
Newmarket
’s annual livestock fairs.
A J-class 0-6-0 engine was allowed
to haul, on outward journeys, a maximum of 35 laden wagons between Banteer and
Kanturk, 25 between Kanturk and
Newmarket
and, on return, 40
Newmarket
and Banteer.
When
busiest in the years to 1940,
Newmarket
dealt in bagged cement, Guiness, fertiliser, sugar beet and
pulp as well as passenger and other sundry traffic.
From 1936 to 1943 an average of three wagons of beet were forwarded to
Mallow each Monday of the campaign. Thereafter
road transport took over.
A small signal box of eight levers
stood on the right-hand side as one entered the compact station yard.
All points at its terminal end were hand operated.
In 1942 a driver, fireman, cleaner,
guard and two porters were on the payroll, with a stationmaster in charge.
Other features were: engine shed, 45ft turntable, 4,750 gallon water
tank, goods store, loading bank, a platform of 130 feet, offices and station
residence.
On returning to Kanturk No. 104 was
gently steamed for approximately 200 yards, then raced forward, unaided, to
within 150 yards of Kanturk home signal.
The
livestock fair yielded 23 wagons, mostly for
Cork
, and at
1.35pm
we departed for Mallow, where a fresh crew took over to
continue the journey. Our engine was
turned at
Newmarket
and latterly at Mallow.
Over time, interesting loadings have
revealed: 2 February 1931 – 28 wagons of pigs for Cork, 17 August 1936 – 52
wagons of various for Cork and Waterford, 27 October 1946 – 50 wagons of
various for Cork and Tralee, September 1947 – 80 wagons of various for Dublin,
Cork and Waterford and 16 August 1961 – 30 wagons of cattle and sheep for Cork
and Waterford.
Newmarket
:
1 September 1936
– 29 wagons of cattle for
Cork
. The largest
number of cattle and sheep out loaded occurred on
9 November 1946
, when 45 wagons were forwarded to
Cork
. This figure was
the highest ever from a Newmarket Livestock Fair.
As petrol rationing eased, so did
rail traffic and both
Newmarket
and Kanturk in common with many other stations, saw their
fairs’ traffic dwindling. Specials of empty cattle wagons left
Cork
at
6am
on fair days. As
far as possible, overnight turns away from home were avoided.
However, during 1920, 1921 and 1946, some empty specials departed
Cork
at
11am
the previous day.
During July, October and November of
1948 a
3pm
special of 45 empties left
Cork
for Kanturk, with sleeping car 238A attached.
The fairs in 1948 were regarded as having a potential of an output of
anything up to 80 wagons. To cope
with this possibility, on the morning of each fair, Mallow had an extra special
of 35 empties ready to leave at
10am
for Kanturk, and did so on four occasions.
Since
1963 many changes have occurred between Mallow and Banteer.
Central Traffic Control has taken over the Tralee Line with all points
and signals electric. The station has become a Halt.
The 1912 GS&WR Appendix to the
Working Timetable revealed that all types of locomotives were allowed over the
Newmarket Branch. The heaviest, A
class – 355/371, were capable of hauling fifteen laden wagons of stone. The
GSR appendix of 1934 forbade such a loading as J class engines became the
heaviest type (axle weight 14½ tons) to operate throughout the remaining years
of the line’s existence.
On 30 November 1962, notices, signed
by Secretary, CIE Kingsbridge, appeared in the National daily newspapers, and
the Cork Examiner reading:- “Pursuant
to section 19 of the Transport Act 1958, the Board of CIE hereby gives notice
that on and from the 2 day of February 1963 all services of trains for the
carriage of merchandise operating on the railway between Banteer and Newmarket
will be terminated and that road services will be substituted for the
railway.”
Despite an emergency meeting of the
Kanturk Development Association, who arranged a meeting with Dr. Andrews early
in December 1962 to postpone the closure, their efforts were in vain. On
25 January 1963
services was cancelled, and a replacement service provided
from Abbeyfeale. The Newmarket Branch, after a long history of faithful service,
closed at
4pm
on
Saturday, 2 February 1963
.
Subsequently an auction of 1,800
sleepers, in bales of 20, was held in Banteer on
19 October 1963
, and all were sold. Kanturk
station was purchased by Cork County Council for development by the local Trades
Association.
On a recent visit to Banteer, I
found it hard to recognise the route of the Newmarket Branch, due to thirty
years of vegetation growth. I did
not need a staff to walk towards the
Blackwater
River
bridge, only local permission.
I am very grateful to the Committee
of the Irish Railway Record Society for its permission to use the archives in
compiling this paper. The diagrams of Kanturk,
Newmarket
and Banteer were kindly drawn by Herbert Richards.
The
remainder of this article appears in IRRS Journal number 157, published June
2005.

Copyright © 2005 by Irish
Railway Record Society Limited
Revised: August 16, 2005
.
|