
Irish Railway Record
Society
TRACK
Dublin
Connolly-Rosslare
Strand During
autumn the last remaining sections of jointed plain track on the Dublin-Rosslare
line were re-laid with the IÉ standard of UIC 54 kg/m Continuous Welded Rail on
concrete sleepers. This was the last remaining radial route from
Dublin
not completely re-laid.
The
down main platform track at Wicklow was excavated and re-laid with CWR on
concrete sleepers in late October. The up loop had already been renewed, as had
points at both ends of the station.
A
section of old CWR on concrete sleepers at MP353/4-363/4
in the Wicklow-Rathdrum section was excavated and renewed with new CWR on
concrete sleepers during full line possessions over the weekends of 28/29 August
and 4/5 September. Coastal defence works also took place between Greystones and
Wicklow. Up to and including Sunday afternoon, trains were substituted by bus
between Arklow and Greystones. Saturday Arklow trains were cancelled.
The
main and loop tracks in Enniscorthy station were excavated and re-laid with CWR
on concrete sleepers. The track through Enniscorthy tunnel was excavated and
re-laid with CWR on hardwood timber sleepers during weekday line closures in
October and November. Also re-laid with CWR on concrete sleepers was a short
section of track immediately south of Enniscorthy tunnel. Both main and loop
tracks in Rosslare Strand were excavated and re-laid with CWR on concrete
sleepers. The remaining sections of jointed track between Enniscorthy and
Wexford North and between Wexford South and Rosslare Strand have been re-laid
with CWR. For this work, all trains were substituted by bus south of Enniscorthy
from 08.35 Monday to 15.30 Friday commencing 4 October until 12 November, except
October Public Holiday Monday.
There
is now CWR continuously from Dublin Pearse to Rosslare Europort exclusive, with
the exception of the platforms at
Dún Laoghaire
and Dalkey, and also between the
Dargle
River
and the level crossing in Bray and the 5-mph track along
Wexford Quay.
Limerick-Rosslare
Europort
Substitute buses ran between Clonmel and
Waterford
from Tuesday 21 until Thursday 23 December for re-laying
work with second hand materials between Clonmel and Carrick-on-Suir (MP54-551/8).
Limerick-Athenry-Claremorris
The Limerick-Ennis line was closed for miscellaneous engineering work
including ballast tamping, cable laying and signalling work on Mondays-Thursdays
between 08.50 and 15.45 from 8 November until 18 November. Trains were
substituted by bus.
The
Divisional Engineer's inspection car ran from Claremorris to Athenry and return
on Thursday 14 October and from Athenry to Ennis on Thursday 4 November.
Dublin-Sligo
Excavation and renewal of track through various stations took place
during the autumn. Dromod loop (down platform) was excavated and re-laid with
CWR on concrete sleepers in August. Boyle loop (down platform) was excavated and
re-laid in September and Longford loop (down platform) was done in October. New
facing points have also been installed to extend the loop at the
Dublin
end of Longford station.
A
new trailing turnout was installed in the up line in Mullingar on Friday 29
October to connect the new bay platform. This bay was formerly known as the
Cavan
Bay
. The new platform will be brought into service when Mini CTC
is commissioned. The facing connection between the Dublin-Sligo down line and
the former main route to Athlone was removed on Tuesday 23 November and replaced
with a new set of left hand turn points installed 89 metres nearer
Dublin
. Associated signals were also altered. The new points are
equipped with a Westinghouse type 63 points machine.
Dublin-Cork
Single line working was used for daytime re-laying work between
Charleville and Mallow from Monday 22 November until Thursday 25 November.
Considerable disruption ensued. On Tuesday 23 November, the 14.00 Tralee-Dublin,
already subject to bus transfer from
Tralee
to Mallow, arrived in Heuston after 19.00, instead of 18.25.
Sugar beet trains were badly disrupted when empty trains were delayed. Only four
trains ran before Wellingtonbridge ran out of empty wagons.
In
Limerick Junction, the unusual scissors crossover located in the middle of the
up main Platform (Nos. 1 and 3), which connects both platforms to the up
Cork
line, was renewed on the night of Saturday 18/Sunday 19
December.
Dublin-Galway
CWR has been installed on
Shannon
Bridge
in Athlone. It is on the existing timber beams.
Galway
City Council has agreed to reserve a corridor of land along the railway line in
Renmore for a future bus lane. The City Planner said the proposed bus lane would
not jeopardise the development of a commuter rail line as there was already a
designated area for a commuter link.
Athlone-Westport
The down loop at Ballyhaunis was re-laid with CWR on concrete sleepers
during weekdays in November. In Claremorris, No. 3 platform (Athenry line) and
part of the old ‘
Burma Road
’ used as sidings have been re-laid with concrete sleepers.
Howth
Junction-Howth
The ground frame controlled crossover at the buffer stops at Howth
station was removed on Sunday 21 November. This crossover had not been
operational for many years. From that date, locomotives no longer have a
run-round facility.
Re-laying
Programme
Completion of re-laying of the Dublin-Rosslare line noted above now sees
the plain track sections of all radial routes from
Dublin
fully re-laid with CWR on concrete sleepers. Also fully CWR
are Limerick Junction-Limerick-Ennis, Cork-Cobh, Manulla Junction-Ballina, Howth
Junction-Howth, Islandbridge Junction-North Strand Junction and the still out of
use Newcomen Junction - Glasnevin Junction line. Some re-laying work is still
taking place in stations in conjunction with the Mini-CTC project. Most single
line passing loops have also been re-laid with CWR. Sidings in Connolly were
re-laid with CWR during December. The Rosslare Strand-Limerick Junction,
Ballybrophy-Killonan Junction and Navan-Drogheda lines are largely jointed
track.
Sandite
Adhesion problems are at their worst during the autumn leaf fall season
and IÉ operates old track machines converted to put down a layer of Sandite (a
mixture of iron filings, sand and silica gel) to help wheels grip the rail. One
machine runs Kildare-Bray-Malahide-North Wall-Maynooth-Connolly-Kildare. A
second runs Limerick Junction to Portlaoise and return or Limerick
Junction-Cork-Cobh and return on alternate days.
BRIDGES
AND TUNNELS
The
programme of upgrading major bridges continues. Following work on replacing
bridge bearings during the closure for commissioning Mini-CTC in April, a
‘silent deck’ was installed on the
Nore
River
bridge at Thomastown (UB87)
at 39 miles 810 yards on the Dublin-Waterford line during a line closure
from Tuesday 14 September until Friday 24 September. Passenger trains ran
between
Dublin
and Kilkenny, with substitute buses to and from
Waterford
.
IÉ
have invested in major work on Belvelly and Slatty Viaducts on the Cork-Cobh
line. Both are double track and consist of arch truss girder bridges constructed
in 1887.
Slatty
(UB421) is north of Fota at 172 miles 316 yards and comprises 6 wrought-iron
bowstring girder spans and a masonry arch on both approaches. Representing an
investment of €3.1m, the work was carried out by the IÉ Bridge Gang and
included:
-
Strengthening the approach arches to
accommodate the new deck
-
Strengthening the bowstring girders
-
Repairing the piers
-
Installing a new deck
-
Installing a track direct fixing arrangement
over the bridge (embedded rail).
-
Repairing the bearings
-
Painting the retained areas of the bridge
Belvelly
Viaduct (UB 422), south of Fota at 172 miles 1,182 yards comprises 3
wrought-iron bowstring girder spans with approach masonry arches. The spans were
completely replaced by Ascon Ltd. Representing an investment of €2.9m, work
included:
-
Strengthening the existing approach arches to
accommodate the new bridge spans
-
Replacing the existing bowstring girder spans
-
Repairing the piers
-
Installing a track direct fixing arrangement
over the bridge (embedded rail).
-
Upgrading the track
Both
bridges now have a 'silent deck' and existing speed restrictions will be eased.
Thompson Engineering of Carlow supplied the new bridge steelwork.
In
October and November, preparation and coastal protection work resulted in
cancellation of weekday trains between 09.45 and 16.30. A full line closure took
place between Glounthaune and
Cobh
from 9 December until 9 January for the main works. Work is
expected to be completed by April 2005.
A
special timetable was issued with trains running between
Cork
and Glounthaune and with a bus connection to
Cobh
. Half a million passengers used the Cork-Cobh line in 2003.
Between 2003-04 there has been a 42% rise in the number of passengers using the
line.
The
Ballybrophy-Killonan Junction line was closed for five days in November to allow
renewal of UB45 (26 miles 880 yards) and UB52 (28 miles 1480 yards). Both
way-beam bridges were renewed on 24 November with pre-cast concrete units.
OB702,
which was a cast-iron jack-arch bridge at Roscommon town (97 miles 50 yards) was
renewed on the 28 November. Laytown station footbridge OB74 at 27miles 176 yards was removed on 19
December following the opening of the new disability access footbridge (
OB
73A) on 17 December.
A
programme of erecting crash barriers to prevent road vehicles crashing through
bridge approaches onto the track below has been ongoing for some time. It has
also been extended to roads running on embankments above railway lines. A
350-metre barrier is being constructed on such a road adjacent to the Dublin-Rosslare
line near MP89.
The
remainder of this article appears in IRRS Journal number 156, published February
2005.

Copyright © 2005 by Irish Railway Record Society Ltd.
Revised: June 14, 2005
.