|
FUTURE OF NETWORK The
campaign to retain and develop the lines from Ballymena to A
local politician claimed that the DRD were using artificially low passenger
figures to justify closing the line. He claimed that tickets issued at
intermediate stations, Day Tracker unlimited travel tickets or those issued by
conductors onboard trains were excluded. In
October, the DRD said funds have been allocated in the draft budget to be spent
on the ‘non-core network’. A DRD spokesman said: ‘The draft budget
proposals provide for the development of the core railway network in line with
the funding estimates in the report of the Railway Review Group and for an
element of capital renewal of the lesser used lines in accordance with Option 1
of that report. But it should be stressed that the final decision has yet to be
taken in relation to the future of the lesser-used lines’. However, on 20 December, the Finance Minister announced that further funding had been approved for Option 2. The three options were:
The
announcement was welcomed by Translink Chief Executive Ken Moffat: ‘This is
wonderful news. A question mark has been hanging over the future of the network
north of Ballymena and Whitehead for 18 months so the announcement securing the
future of the lines is very welcome news for us as a rail operator and of course
for our passengers. The investment is all the more welcome as it represents
an increase on the amount originally set aside for the Derry and Larne lines in
October’s draft budget’. PASSENGER JOURNEYS The
number of rail passenger journey in Northern Ireland increased by 10% in the
2003-4 financial year from 6.3 million journeys to 6.9 million, according to
data published by the Government in September. In contrast, TIMETABLE A
new Working timetable was introduced on Monday 4 September. However, there were
no changes to passenger trains and no new public timetable was issued. A feature
of the timetable is that the Mk IIf (Gatwick) set and four railcars are stabled
overnight in Great Victoria Street (GVS) to make space in INFRASTRUCTURE Larne Line Trooperslane automatic half barrier (AHB) level crossing has been converted to a four-barrier CCTV monitored level crossing. Temporary block working was instituted between Carrickfergus and Greenisland from 00.15 Thursday 16 September until 05.00 Tuesday 21 September, with drivers receiving instructions from hand- signalmen.
A temporary timetable with only minor disruptions was issued, except for the
Sunday when trains ran between Two weeks later Jordanstown level crossing was converted from AHB to four-barrier CCTV monitored. Temporary bock working was instituted between Bleach Green Junction and Greenisland from 00.15 Thursday 30 September until 05.00 Tuesday 5 October. A temporary timetable was issued and single line working was used for a period. Relocated signals protect both crossings. Abutment
strengthening to OB450 at MP193/4 resulted in bus
substitution between Larne and Whitehead on Saturday 6 November and A contract was signed between NIR and Amec Spie Rail just
before Christmas for re-laying of the line between Bleach Green Junction and
Whitehead. The Contract will commence on site on Belfast-Londonderry Ballykelly level crossing (MP815/8) was renewed during a nighttime possession on Saturday 14 and Sunday 15 August. The bearing plate pads on UB208 at Limavady Junction (MP793/4) were replaced during Saturday/Sunday nighttime possessions on 4/5 September and on 2/3 October. Further track re-laying with CWR took place on the down line at the south end of Ballymena station in September and in Coleraine station during November. Due to embankment stabilisation and drainage work north of Dunloy, there was bus substitution between Ballymena and Ballymoney on Saturday 13 and Sunday 14 November. The trackbed under OB151 at MP 491/4 was excavated. Rockslide protection has been installed at Downhill. Netting has been installed on cliff faces and barriers on the road adjacent to the railway. LISBURN-ANTRIM The usefulness of Lisburn-Antrim for diversions was again demonstrated on Saturday 25 September following a fire on 8091 at Yorkgate, which had been working the 10.35 GVS-Londonderry. The line was also used for training purposes on a regular basis Lisburn-Antrim proved its worth again on Friday 19 November, when the main line was closed at Whiteabbey following a non-railway related incident. The 09.35 Londonderry-GVS and 10.35 GVS-Londonderry were diverted. STATIONS The
Belfast Metropolitan Transport Plan published in November proposed a new station
at Tillysburn, which would cater for both the DEPOTS Work
commenced in August on construction of the new train cleaning facility at
Fortwilliam on the up side just north of Work progressed well on site clearance during the autumn. Structural steel erection commenced in November. LOCOMOTIVES AND ROLLING STOCK 3000-class
CAF set 3006 was delivered to Reliability running trials continued in September.
Daytime running took place between Commenting on the trials Mr Mal
McGreevy, General Manager NIR said ‘They are running exceptionally well. We are very
pleased with them. Regarding the Londonderry line he said ’I believe it would
reasonable to expect a 1 hour 40 minute limited stop service, calling at
Coleraine, Ballymena and Antrim’. Commissioning of the new
trains went well with just one major problem outstanding at the end of October.
This delayed the entry of the trains into service and resulted in a suspension
of further deliveries. The computerised passenger information system, which
makes announcements to passengers and displays information on a screen on the
exterior of each carriage, continued to have software problems. NIR said that
‘Until the software is right, we cannot comply with the requirements of the
Disability Discrimination Act and therefore cannot get the necessary
certification’. NIR made extensive use of
their new driver-training simulator to train drivers in the new trains. The £1.1m
facility was supplied by Corys Tess and is an exact working replica of the C3K
cab, complete with controls, VDUs and is fitted with all the various radios. The
software incorporates a track-building tool to allow the creation of a detailed
virtual copy of the actual rail network. The first of the new trains entered commercial service on
Wednesday 24 November when 3-car set 3001 operated the 10.32 Portadown-Bangor
and a non-stop 12.15 Bangor-Belfast Central. It was followed closely by empty
3-car set 3002 as a back up. Translink Chairman Dr Joan Smyth said, 'This is an
historic day for Deliveries re-commenced with set 3008 being delivered to Set 3002 entered commercial
service on Monday 29 November, set 3003 on Thursday 2 December and set 3005 on
20 December. Initial operations were on Bangor-Portadown services and the new
trains soon showed their high performance capability. On Locomotives
GM 111 continued to operate the Newry-Belfast
service throughout autumn and winter with former Gatwick Mk IIf carriages,
although newly painted 209 was used in December. No. 112 continues on loan to IÉ
and 8113 remains out of service at 80-class
Mechanical failures continued to affect operations as NIR struggle to
keep the ageing fleet in service. Members of the class continue to be
‘stored’ as they become defective. Four 80-class power cars have been
withdrawn; 67 on In late August, 8081, 8087 and 8736 were observed in Following
a fire on power car 8083, power car 67 was brought from De
Dietrich
A series of ‘comfort ride test’ trains took place between Train
Cleaning
In September, NIR awarded Maybin
Support Services NI Ltd, OPERATIONS Following
introduction of 3000-class railcars, 6-car 80-class sets took over many
peak-time links from 3-car sets to relieve overcrowding. The
former Gatwick Mk IIf set continues to substitute for failed De Dietrich trains
on The
next morning, the 06.50 Belfast-Dublin was worked by 111 + 6 Mk IIf + generator
van. It departed
Copyright © 2005 by Irish
Railway Record Society Limited
|