
Irish Railway Record
Society
TRACK
Dublin
Connolly-Rosslare
Strand
Track re-laying using CWR (Continuous Welded Rail)
on concrete sleepers took place on weekdays between MP611/8-63
in the Gorey-Enniscorthy section in May and June. Over the June public
Holiday
weekend, 152+186 and a train of concrete sleepers were
stabled in Gorey. Re-laying with CWR on concrete sleepers on the ‘Wexford
South Branch’ between MP21/8-31/8
Wexford-Rosslare Strand took place from Monday 26 July to Friday 30 July. For
both sets of re-laying, the 07.10 Maynooth-Rosslare Europort and 13.25 Rosslare
Europort-Maynooth were substituted by bus between Enniscorthy and Rosslare. The
main and loop tracks in Enniscorthy were also excavated and re-laid in July and
August. Trains ran normally during this work, as one track was kept open.
The
facing turnout at the Rathdrum end of Wicklow station was renewed on Sunday 18
July. The crossover at the
Dublin
end has also been renewed.
There
is now CWR continuously from Dublin Pearse to Enniscorthy, with the exception of
the platform tracks at
Dún Laoghaire
and Dalkey and the down main at Wicklow. South of
Enniscorthy there are only a few remaining stretches of jointed track, the
longest of which is 23/8 miles. In total, there is less
than 51/2 miles of jointed track remaining and this
includes the 5-mph track along Wexford Quay.
Dublin-Waterford
The Minister for Transport has approved a 1,120-metres diversion of the
Dublin-Kilkenny line between Lavistown Junction and Kilkenny and the
construction of a new overbridge as part of a €31m single-carriageway 4.2km
road bypass scheme (See JOURNAL 154).
Mallow-Tralee
In advance of installation Mini-CTC between Banteer and
Tralee
, the up siding at Millstreet and the down siding at Rathmore
were taken out of use from 28 June.
Dublin-Dundalk-Border
Two separate sets of weekday possessions to
tamp the track between
Drogheda
and
Dundalk
caused considerable delays to trains in March and July.
Single line working resulted in delays to
Enterprise
services from which they were unable to recover. For
example, on Tuesday 6 July the 10.30 Belfast-Dublin departed
Drogheda
at 12.46, at which stage it should have been in
Dublin
. The same train working the return 13.20 Dublin-Belfast was
observed blocked at Mosney at 14.04 by the 13.17 Pearse-Drogheda stopping
service, which was at Laytown. The loop at Mosney was not used.
Enterprise
services continued to be delayed by temporary speed
restrictions, with six on the down line and five on the up line between Connolly
and
Drogheda
at the end of July.
Limerick-Rosslare
Europort
The down line between Limerick Station and Check cabins was excavated and
re-laid with CWR on concrete sleepers during August. Panel re-laying with second
hand panels took place between
Waterford
and
Belview
Port
during the summer.
In
May, weekday possessions to tamp and ‘stress’ CWR between Dromkeen and
Limerick Junction saw mid-morning trains substituted by bus. When work was
completed, a long-standing 3-mile temporary speed restriction was lifted.
Similar possessions took place in July to renew crossing timbers in Dromkeen and
in August for tamping and bridge works.
Ballybrophy-Killonan
Junction
Panel re-laying using second-hand jointed track panels took place in
June. During re-laying, the 09.45 Ballybrophy-Limerick and the 15.00 Limerick-Ballybrophy
were substituted by bus.
Dublin-Sligo
By the end of July, work had been substantially completed on the recon-struction
of the former
Cavan
Bay
platform at Mullingar. It is located on the goods yard side
of the up
Sligo
platform and is 184m long. No track will be available for
use until Mini-CTC is commissioned in 2005. The adjacent up
Sligo
platform and the new bay platform have been surfaced in tar
macadam. Construction was preceded by the lifting of track in the goods yard and
the removal of redundant Molasses wagons that were in store. Concurrently, work
was undertaken to widen UB 58 (49 miles 1,620 yards) at the
Dublin
end of the goods yard to facilitate laying of a new approach
track to the platform. The up and down
Sligo
platforms were also extended at the
Dublin
end to 184 meters.
Both
Longford platforms have also been extended to accommodate 8-car railcars. The
down loop at Dromod was excavated and re-laid with CWR on concrete sleepers in
August.
The
yard at
Sligo
was rationalised on Sunday 8 August in preparation for the
installation of Mini-CTC. Crossover No. 16 from the up line to the former
locomotive shed, turntable and sidings was disconnected and all track
subsequently lifted. Turnout and traps No. 13, connecting the up departure road
with the two platform storage sidings and crossover No. 14 connecting the down
arrival road with the up departure road were also disconnected, as were
associated signals. One remaining crossover, No. 19, remains between the down
arrival road and the up departure road, as well as the crossover No. 17 to Sligo
Quay.
Dublin-Cork
Re-railing, welding, tamping and regulating ballast between Mallow and
Rathpeacon resulted in single line working on weekdays at the end of June, in
early July and mid-August, with delays to morning Dublin-Cork and Cork-Tralee
trains and substitution of Cork-Mallow/Charleville trains by bus.
Excavating
and renewing the formation on the up line through Thurles saw the 21.00
Dublin-Cork replaced by bus south of Portlaoise on Saturdays in July and August.
Ballast Cleaning between Newbridge and Kildare resulted in the 21.45 and 22.45
Dublin Heuston-Kildare and 22.50 Kildare-Dublin Heuston operated to and from
Newbridge during weeknights from mid-July into August.
The
speed limit from MP13/4-11/4 in both
directions was reduced from 60-mph to 40-mph in July. All crossovers in this
area have been renewed in recent years and the line through this area had a
maximum speed of 70-mph in the early 1970’s. Non-stop mainline journey times
from Heuston to Hazelhatch are now scheduled to take 13 minutes compared with 11
minutes ten years ago.
Athlone-Westport/Ballina
Both platforms in Claremorris are now fully laid with CWR on concrete
sleepers.
Weedspray
The weedspray train covered the IÉ system in April, May and June. It
sprayed the Athenry-Ennis section on Wednesday 12 May, hauled by locomotive 160.
Unusually, the train, hauled by locomotive 156, sprayed the Tara Mines sidings
when it did the Drogheda-Navan line on 9 June. The train did not spray
out-of-use lines: Limerick-Foynes, Mullingar-Athlone, Navan-Kingscourt,
Glounthaune-Youghal, Waterford-New Ross, Silvermines Branch and
Collooney-Claremorris-Athenry, as well as Limerick Junction-Cahir.
CAHIR
VIADUCT
The
IÉ report on the collapse of the bridge at Cahir concluded that the derailment
of a freight train on
7 October 2003
was due to a combination of specific factors (See JOURNAL
153). The variable stiffness of the beams on the bridge combined with the
rigidity of the four-wheel cement wagons caused one wagon to jump the tracks. IÉ
determined that such an incident could not have happened to a passenger train.
All bridges of this construction have since been examined and a 30-mph speed
limit applies to trains with similar wagons travelling on such bridges.
Reconstruction
work continued during spring and summer months. By May, new steel floor girders,
which are supported from the top of the strengthened original girders, had been
erected on the small span nearest Cahir station and on the main span. The span
nearest
Tipperary
had still to have its original cross members removed. The
floor girders were welded into threes and then lifted from ground level. This
welding was originally done near the bridge site, but later moved to a covered
facility in Mitchelstown. The last girders were lifted in on Saturday 10 July.
Pouring of the concrete deck was done in two pours, the second on Monday 19
July.
The
main reconstruction contract was completed by the end of July and work commenced
on re-instating track. This was completed by 18 August, at which stage some
minor work remained.
Opportunity
was also taken to excavate and renew the track through Cahir station with
second-hand flat bottom jointed rail on timber sleepers. Following a period of
training with railcars on the line, it was expected to re-open fully in
mid-September
BRIDGES
AND TUNNELS
A
new overbridge is under construction at Kneads Bridge 43 miles 1,200 yards
between Killucan and Mullingar in conjunction with a new dual carriageway for
the N4 Dublin-Sligo road. A new underbridge is under construction adjacent to
the Dublin-Belfast line at MP563/4-57 for a new section of
M1 motorway bypassing
Dundalk
.
The
programme of replacing accommodation crossings with bridges continues. On
Wednesday 5 and Thursday 6 May, a new underbridge UB131A was installed at 57
miles 40 yards in the Farranfore-Tralee section to facilitate closure of
adjacent level crossing XT154. All trains from the 08.30 Dublin-Tralee on the
Wednesday until the 17.47 Tralee-Cork on the Thursday were substituted by bus
between
Tralee
and Killarney.
A
new overbridge OB17A is under construction at 10 miles 745 yards between
Killonan Junction and Dromkeen to replace Woodfarm level crossing XL32. The
existing level crossing has been temporarily re-located to allow building work
proceed. The user operated crossing had been the scene of several incidents in
recent years and the gates were regularly being left open by road users.
The
footbridge at Carrick-on-Suir was raised by approximately 12” on Thursday 29
July by pouring a concrete apron and sitting it on it.
Saturday
26 June was the occasion of President Bush’s visit to
Dromoland
Castle
, located between
Limerick
and Ennis. The main
Limerick-Ennis-Galway road was closed for security reasons and all road traffic
was diverted on to secondary routes. That afternoon, a lorry struck and badly
damaged the arch and shifted the parapets of underbridge UB41, a stone arch
bridge with a clear height for road traffic of 11’ 6”.
The
bridge is located near MP121/4
on the
Limerick
side of Sixmilebridge. The railway was closed until Wednesday 30 June,
when it was re-opened with a 5-mph speed restriction. Locomotives were also
banned and the 17.10 Dublin Heuston-Ennis terminated in
Limerick
, with Ennis passengers
transferring to a railcar.
One
consequence of the ban on locomotives was that a permanent way train en route
from Portlaoise to Crusheen, between Ennis and Athenry, on Monday 19 July to
collect good condition second-hand track panels had to be routed via Athenry.
The train consisted of 146+148 + 8 bogie wagons and it stabled overnight in
Ennis, before returning to Portlaoise via Athenry. The panels had been deposited
along the line some years ago with a view to replacing existing poor condition
track, but were not used after the line was taken out of use. The panels were
taken to the
Waterford-Belview
Port
section, where they were laid.
Given
the extent of the damage to the bridge, it was decided to replace it rather than
repair it and a new bridge was ordered. It was installed over the weekend of
28/29 August and all trains were cancelled on the Saturday and until 17.45 on
the Sunday. The R462 Sixmilebridge to Cratloe road remained closed throughout.
OB96
at 6 miles 750 yards Dublin-Rosslare (
Peoples
Park
Bridge
), which was a steel girder and
Hobson floor plate bridge, was renewed with pre-cast concrete beams over 3
weekends in June. The work was completed on 27 June. Strengthening work on UB186
at MP391/4
Dublin-Rosslare is expected to be completed by the end of November.
The
cast iron jack-arch beams on OB387 at 50 miles 836 yards Dublin-Sligo at
Mullingar station were renewed on 27 June. Major repairs were carried out on
UB120 at 91 miles 1,320 yards Dublin-Galway in August. The stones on this
masonry arch culvert were starting to drop.
Preparatory
work on Thomastown Viaduct (UB87 39 miles 810 yards Dublin-Waterford) is
continuing in preparation for the installation of a new deck, which will be done
during a ten-day line closure. OB32 at 16 miles 473 yards Midleton-Youghal was
renewed on 24 August. This was one of the few remaining cast iron jack-arch
bridges.
SIGNALLING
Centralised
Traffic Control (CTC) Auto
routing is now available on the Mainline CTC system. This follows an upgrade in
the computer system in the CTC building in Connolly station. Auto routing works
by having the journey details of trains pre-programmed into the computer, which
then issues commands to the local interlocking to set the route and clear
signals in advance of the train’s approach. Auto routing has been used on the
Dublin Suburban CTC system for twenty years.
Mini-CTC
Project Work continues on installation of cable
ducts, cables, signal bases, signals, radio masts and location cases on the
Mallow-Tralee line. Clearances were made in Rathmore and Killarney for
construction of new points and crossovers. The ballast bed for the extension of
the track of the bay platform in Killarney was completed by mid-August.
Signal
bases and cables are also in evidence at most stations on the
Sligo
line. Work has taken place installing a second fibre optic
cable, working from the
Sligo
end. It had reached Dromod by July.
Westport
Line
Approval has been given to install Mini-CTC on the Knockcroghery-Westport
line to follow on from
Sligo
line Mini-CTC. It is envisaged that the line will be
upgraded by 2007 and the line will be controlled from CTC in Connolly station.
As part of the upgrade, level crossings in station areas will be upgraded to
4-barrier CCTV monitored crossings interlocked with station signals. Separate
approval has also been given to replace semaphore signals at level crossings
outside station areas with colour light signals.
Navan-Drogheda
(Platin) On
Sunday 20 June, operation of the
Drogheda
(Platin)-Navan section was converted from Electric Train
Staff (ETS) operation to single line track circuit block working using an
Axle-Counter. New colour light signals were erected in Navan. They were a
fixed-at-caution yellow down distant NNDD and a two aspect yellow-red down outer
home signal NN102 and, in the up direction, new up advance red-green starter
NN101. Both stop signals are 212-metres from Factory ‘A’ type level
crossing, but are not interlocked with the crossing. Signals at Platin were
already colour light, controlled from
Drogheda
.
Renewals
With the line closed due to the collapse of Cahir viaduct, opportunity
was taken to refurbish Clonmel signalbox and interlocking frame.
LEVEL
CROSSINGS
Signals
On Sunday 4 July, new colour light distant and stop signals were brought
into use at four level crossings in the Thomastown-Waterford section, which were
formerly protected by Braking Point Marker Boards and colour light distant
signals (See JOURNAL 154). The crossings were Rossinan (XW169 at 53 miles 1012
yards), Ballygeoghan (Kilmacow) No.1 and No.2 (XW175 at 54 miles 858 yards and
XW176 at 54 miles 990 yards) and Milltown (XW181 at 55 miles 1144 yards). Three
new sets of signals, which include a mixture of two and three aspects, protect
the four crossings. Stop signals are located between 200 metres and 700 metres
from the gates. Distant signals are located 1,489 metres and 1,971 metres from
the stop signals.
Renewal
Excavation and renewal of the road surface through Lisnagry level
crossing, which carries the N7 Dublin-Limerick road over the
Ballybrophy-Killonan Junction line near Castleconnell, resulted the closure of
the line for a complete week at the end of July. All Nenagh branch passenger
trains and Kilmastulla-Limerick cement works shale trains were cancelled. A
temporary road was laid to allow road traffic around the worksite.
Wexford
Quay A
new temporary level crossing has been brought into use at 5 miles 1443 yards
(Wexford South) and is open daily from 08.30 until 18.30. The crossing provides
vehicle access to the new car park on the Quay. Manually operated barriers are
locked in the lowered position for the passage of trains.
The
remainder of this article appears in IRRS Journal number 155, published October 2004.

Copyright © 2005 by Irish Railway Record Society Ltd.
Revised: January 11, 2005
.