|
| |
< 
Irish Railway Record
Society

Irish
Railway Bridges-3
NIALL
V. TORPEY C.Eng, F.I.Struct.E, F.IEI
CONTINUING
DEVELOPMENT
The
years 1865–1925
It is perhaps appropriate to consider the relatively long period of some 60
years, which saw the culmination of the halcyon days of the private enterprise
of railway ownership, to be followed almost immediately by the significant
political changes and Government involvement in the administration of the
railway business in Ireland. This period was the one in which the last public
railways were built in the country. These were the Rosslare Harbour – Mallow
development in 1902-6, which involved the construction of the longest railway
bridges in the country. Other railways built to help the WW I war effort
involved the lines from Athy to the Wolfhill Colliery and to a similar
facility above Castlecomer. The Wolfhill line is notable as the site of the
first use of reinforced concrete as the superstructure material in
underbridges over the river Barrow at Athy and in the hills up to Wolfhill.
Events
on the railways in 1916-1923
The
Rising of 1916 broke out at about noon on Monday, 24 April. At 1 pm on that
day the GS&WR received orders from the military to provide four troop
trains, capable of conveying 2,000 troops from the Curragh to Dublin. Empty
trains to cater for this order left Kingsbridge at 1.10 pm, 1.40 pm, 1.55 pm
and 2.10 pm. No civilian trains left Kingsbridge after 12.20 pm. A further two
empty troop trains left Kingsbridge at 8.25 pm and 8.50 pm to collect a
further 1,000 soldiers from the Curragh. Late on the evening of the same day
another special carried 200 officers and men from Cork to Mallow to protect
the Blackwater Viaduct there. Many other unusual workings took place at this
time such as non-stop specials, and passenger workings between companies’
lines.
Damage
to the railways in 1916 was modest, being mainly confined to the occupation
some of the principal Dublin stations for a part of the period of the
rebellion. Thus, Westland Row station of the D&SER was closed to traffic
by some of the garrison at Boland’s mills, and Harcourt Street station was
also closed but in this case only for a few hours. The GNR(I) line was
interfered with by rebel action at Rogerstown viaduct when a bomb was placed
against the ironwork of the bridge. The event was reported in The Irish Times
of Tuesday 25 April, 1916 as follows:
Shortly
after 3 o’clock in the afternoon an attempt was made to blow up the …
bridge at the inlet of the sea… at Rogerstown. The bridge is in sight of the
Donabate station, and a few minutes before the 2 pm train from Dublin was due
in Donabate the stationmaster heard a loud explosion. At first he thought the
sound came from blasting in the quarries which are close by, but the smoke was
immediately apparent over the …bridge. The stationmaster and some of the men
on duty ran there as fast as they could, and found that an attempt, which was
fortunately unsuccessful, had been made to blow up the middle section of the
bridge…
In
the later period of the troubles, the amount of damage caused to the rail
network was small enough, until the start of the Civil war in the summer of
1922. Between then and the war’s nominal end about a year later, much damage
had been caused to the engineering infrastructure of the railways,
particularly to bridges and signalling. In the case of bridges, damage and
destruction was concentrated in the NE, SE, S, SW, and W of the country. In
this period, the Ballyvoyle viaduct was destroyed and Monard viaduct was
severely damaged, but repairable.
TWENTIETH
CENTURY DEVELOPMENTS
The
years 1925–1965
The
financial effects of the Great War and the immediately subsequent Troubles and
the Civil War resulted in a large amount of necessary bridge repairs and
rebuilding. This placed even the most commercially successful companies under
almost impossible financial strains. In order to ensure the future of the
railway network, the Free State Government arranged for the amalgamation of
all the railways within the Free State into one company, called the Great
Southern Railways. The difficulties caused by the Border with the new state of
Northern Ireland resulted in the Great Northern Railway Ireland and some other
minor lines straddling the Border being left out of the Free State’s
amalgamation. Further general difficulties caused by competition with road
transport began about this time and continued up to the end of this review,
and indeed beyond.
As
far as railway bridge works are concerned, the general financial constraints
had a serious adverse affect on the ability to renew bridges and a
make-do-and-mend approach seems to have pervaded the network. The effect of
this was to cause many heartaches to those charged with maintaining a railway
network which could not be funded from earnings, and which Governments were
increasingly reluctant to fund from general taxation. It is appropriate to
record the appreciation that is due to those engineers and others who in such
a hard financial climate managed to keep a public railway running, whether
from the point of view of motive power, or the engineering infrastructure.
However, an amount of necessary bridgework was undertaken. In the period up to
about 1940, most renewals were carried out using structural steelwork, in many
cases supplied from Britain, and in not a few cases using salvaged bridge
materials from closed lines.
The
period of WW II was of course one of extreme shortage of materials of all
kinds, and in our case of bridge building materials. However, a distinct
emphasis on the use of structural concrete is discernible at about this time.
This was to continue and to become a normal material for bridge renewals, at
least south of the Border. In the earlier days of its use, delays caused by
concrete setting and hardening resulted in its use being restricted to
overbridges, where the closure of lines could be avoided. The use of pre-cast
concrete also emerged particularly for underbridges, but the difficulties
caused by the limitations of rail mounted steam cranes to lift heavy pre-cast
concrete units into position made it difficult to adopt for other than smaller
bridges and culverts or at least for liftable pre-cast concrete sections.
In
the case of the use of structural steel, 1957 saw the last example of riveted
construction at the Quagmire viaduct on the Mallow-Tralee line. The following
year saw the first example of an all-welded bridge carrying the Dublin-Belfast
railway over the North Wall branch.
As
a subset of reinforced and pre-cast concrete, the first use of pre-stressed
concrete bridge beams for railway use can be shown to date from about 1943,
when such beams were used in wartime Britain by the LNER and the LMSR on spans
of 50ft and 42 ft respectively23. In Ireland pre-stressed concrete
was used for the renewal of OB 56 near MP 22 south of Sallins in the early
1950s to the design of L. F. Stephens. A little later in the same decade,
pre-stressed concrete was again used, this time by the GNRB, in the renewal of
the under-bridge over the river Tolka and East Wall road which had been
destroyed in severe flooding on 8 December 1954. The new bridge was brought
into use on 12 January 1956, and the temporary Bailey bridge in use from 4
January 1955 was removed on 19 January 1956. In November 2002 this early Irish
pre-stressed concrete underbridge was itself replaced, to allow for an
increase in both road and rail traffic24. An interesting use of
pre-cast concrete units, stressed together, was at the construction in 1956 of
the pedestrian access tunnels to Lansdowne road Rugby ground under the Dun
Laoghaire railway. Pre-stressed concrete is the material, which has emerged as
an important structural material for railway bridge renewals in the period up
to the end of this review and indeed beyond.
CONCLUSION
I
have already noted that for much of the time covered by this review, the
financial condition of the railways was difficult, and this inevitably
reflected on the business of maintaining the railway and its various parts,
including its bridges. Many forces at the time, for example the Beddy Report,
were leading to the demise of railways altogether, or at least their serious
curtailment. In Northern Ireland, such forces held much sway in Government
with the resultant loss of much of the network there and the serious running
down of what remained in preference to the construction of the first motorways
in Ireland. That engineers and others, in spite of these influences,
maintained a public railway network is surely a matter for quiet satisfaction.
References
|
1
|
Across
deep waters – Bridges of Ireland –
M Barry, Frankfort Press, Dublin, 1985
|
|
2
|
Irish
structural engineering in the second millennium –
J W de Courcy, Institution of Engineers of Ireland, Dublin, 1999
|
|
3
|
A
statement in explanation of evidence relative
to the construction of the Boyne viaduct –
J A Galbraith, M H Gill, Dublin, 1858
|
|
4
|
Description
of some experiments made at the Boyne viaduct in 1854 –
B B Stoney, Institution of
Civil Engineers of Ireland, Dublin, 1858
|
|
5
|
On
the economic distribution of material in the sides, or vertical
portion, of wrought iron beams –
J Barton, Institution of Civil
Engineers, Volume XIV, London, 1855
|
|
6
|
Reconstruction
of the Boyne viaduct, Drogheda –
G B Howden, Institution of Civil Engineers of Ireland, Volume LX,
Dublin, 1934
|
|
7
|
Athlone
as a railway centre – P J
Currivan, Journal of the Irish Railway Record Society, Volume 4 No 20,
Spring 1957
|
|
8
|
The
Railway Times, Saturday,
December 20, 1851 – Anon report
|
|
9
|
Memoirs
– Sir William Fairbairn –
Institution of Civil Engineers, Volume XXXIX, London, 1874-75
|
|
10
|
Report
of inquiry into accident on the railway system of Coras Iompair
Eireann at Cahir station on 21 December, 1955
– Department of Industry and Commerce, Dublin
|
|
11
|
On
the reconstruction of Innoshannon bridge, Cork & Bandon Railway –
G P Cotton, Institution of Civil Engineers of Ireland, Dublin, 1866
|
|
12
|
On
the reconstruction of Malahide viaduct –
W Anderson, Institution of Civil Engineers of Ireland, Dublin, 1862
|
|
13
|
Malahide
viaduct –
R T Holloway, & C D Waters, Institution of Engineers of Ireland,
Volume 95, Dublin, 1969
|
|
14
|
Description
of the viaduct erected over the river Nore, near Thomastown … –
Capt W S Moorsom, Institution
of Civil Engineers, Volume XI, London, 1852
|
|
15
|
Robert
Mallet 1810-1871 – Centenary
Seminar Papers, Institution of Engineers of Ireland and the Royal
Irish Academy, Dublin, 1982
|
|
16
|
Nore
viaduct at Thomastown – C R
Galwey, Institution of Civil Engineers of Ireland, Dublin, 1879
|
|
17
|
Irish
Stone Bridges – History and heritage
– P O’Keeffe & T Symington, Irish Academic Press, Dublin, 1991
|
|
18
|
A
century of innovation: structural engineering 1900-2000
– R J M Sutherland, Institution of Structural Engineers, Volume 78,
London, 2000 & Presidential Address
of Joseph Mallagh, Institution of Civil Engineers of Ireland, Dublin,
1930
|
|
19
|
The
theory of stresses in girders and similar structures
– B B Stoney, Longmans, Green and Co, London, 1886
|
|
20
|
Longmans’
Civil Engineering Series –
Railway Construction
– W H Mills, Longmans, Green and Co, London, 1898
|
|
21
|
BSI:
the story of standards – C
Douglas Woodward – British Standards Institution, London, 1972
|
|
22
|
An
Act for regulating the gauge of railways, 1846
|
|
23
|
The
precast concrete bridge beam: the first 50 years
– H P J Taylor, Institution of Structural Engineers, Volume 76,
London, 1998
|
|
24
|
East
Wall Road Bridge replacement –
D McCarthy & F Lalor, Institution of Engineers of Ireland, Dublin,
2002
|
ACKNOWLEDGEMENTS
The
author would like to thank friends in Europe, in IÉ (past and present) and in
the IRRS who helped in providing information, which was used in preparing this
paper.

Copyright © 2005 by Irish
Railway Record Society Limited
Revised: January 11, 2005
.
|