|

Irish Railway Record
Society
TRACK
Dublin
Connolly-Rosslare
Strand
Track re-laying using CWR
(Continuous Welded Rail) on concrete sleepers resumed on Monday-Friday in
February. The 07.10 Maynooth-Rosslare Europort and 13.25 Rosslare
Europort-Maynooth were substituted by bus between Enniscorthy and Rosslare.
Track renewed was between MP811/8-843/4.
This leaves 8 miles of jointed track remaining south of Gorey, including the
section along Wexford Quay, which is restricted to 5-mph.
In
April, concrete sleepers were delivered by rail to Wexford in preparation for
more re-laying. On Tuesday 20 April, 153+170 + 10 laden bogie wagons passed
Rathdrum at 16.28.
The
connections to the former fertiliser factory at Shelton Abbey from the mainline
have been removed, as have points within the former yard. The factory is being
dismantled and shipped to
China
. Traps have been installed in the
extended bay platform at
Dún Laoghaire
. This allows trains be stored in the
platform.
Limerick-Rosslare
Europort Renewal
of trailing crossover No. 71 in
Limerick
on Sunday 1 February saw morning trains
substituted by bus between
Limerick
and Limerick Junction.
With
the line between
Waterford
and Limerick Junction closed,
opportunity has been taken to refurbish and re-lay track. Second hand panels
were used to re-lay between MP341/4-36 between
Tipperary
and Cahir. Second hand panels were also
used to re-lay between MP761/4-77 between Waterford Abbey
Junction and the
Barrow
Bridge
.
Athlone-Westport/Ballina
The remaining siding at Castlebar was taken out of use on Tuesday 27 January
and subsequently lifted. The siding was located on the up side and faced towards
Westport
. It was accessed by a ground frame
released by the Electric Train Staff for the Manulla Junction-Westport section
and was used for storage of permanent way trains during track re-laying in
recent years. Up direction colour light stop signal MJ11 and associated distant
signal MJR11 protecting this siding were removed. Subsidiary token instruments
in Castlebar and Manulla Junction were also removed. There is now only single
line plain track through Castlebar.
The
Westport-Athlone line was closed west of Castlerea between 08.00 and 20.00 on
Tuesday 17 February to allow renewal of the turnout at the Claremorris end of
Ballyhaunis.
Westport
trains were substituted by bus between
Westport
and Castlerea, while Ballina branch
trains skipped the Manulla Junction stop and operated between Ballina and
Claremorris.
Dublin-Belfast
There were delays and disruptions due to single line working between
Drogheda
and
Dundalk
from Monday 9 to Friday 13 February and
from Monday 16 to Friday 20 February. Work involved packing and tamping. Delays
to
Enterprise
services ranged from 20 to 45 minutes.
The 06.45 Gorey-Dun-dalk, 07.57 Pearse-Dundalk, 10.00 Dundalk-Connolly and 10.41
Dundalk-Gorey were subst-ituted by bus between
Drogheda
and
Dundalk
.
Cork-Cobh
To allow excavation for drains between Rushbrooke and
Cobh
, MP1751/2-1761/4,
there was a full line closure from 09.40 on Saturday 7 February until 16.50
Sunday 8 February and the same times the following weekend. All off peak
services were substituted by bus on Monday-Friday from 15 February until Friday
16 April, with a break for Easter.
Mallow-Tralee
Both main road and
loop road in Farranfore station were excavated and re-laid with CWR on concrete
sleepers in March. All stations between Mallow and
Tralee
have now been re-laid with CWR except
the bay platforms at Killarney and
Tralee
.
Dublin-Sligo
Work on extending the up and down
Sligo
line platforms in Mullingar commenced
in March. Work also commenced installing track in the former
Cavan
Bay
, which was on the goods yard side of
the up
Sligo
platform and faced towards
Dublin
. Concrete sleepers and flat-bottomed
rail were used. By early April, the high wall between the station and the former
goods yard had been partially demolished and the ‘Jail’ siding on the up
side at the
Dublin
end of the station had been re-laid.
UB58 at 49 miles 1,620 yards is to be widened to allow the track at the
Dublin
end of the station to be slewed and the
curve for the
Sligo
line to be eased.
Cherryville
Junction-
Waterford
A section of the line between Lavistown West Junction and Kilkenny is to
be diverted to accommodate the extension of the
N77 Kilkenny Ring Road northwards
from the Dublin Road Roundabout. The
section is between MP283/4-291/2. On
9 January, CIÉ ‘in exercise of the powers conferred upon it by Part 3 of the
Transport (Railway Infrastructure) Act, 2001’, applied to the Minister for
Transport for a Railway Order to construct, operate, and maintain the new
section of line and a Public Enquiry was held in the County Hall, Kilkenny, on 6
April.
Limerick-Ennis-Athenry
Work continues on
improving views at accommodation crossings between
Limerick
and Ennis. Hedge cutting has taken
place between Craughwell and Ardrahan in the out-of-use Ennis-Athenry section.
Ballybrophy-Killonan
Junction
The maximum line speed continues to be 40-mph. In addition, there were 15
temporary lower speed limits over the 523/4-mile line in
March. These were mainly 25-mph and included a stretch of 6 miles and another of
21/4 miles.
Portlaoise
Depot
Following completion of the five year track re-laying programme at the
end of 2003, IÉ reduced the number of contract staff employed at Portlaoise
concrete sleeper factory by twenty-eight. They were offered alternative
employment on the DART upgrade project and about one third took up this offer.
In
early 2004, IÉ sought further reductions with newspapers indicating between
fifteen and twenty-one permanent staff positions will be eliminated by a
voluntary severance scheme. IÉ said that staff will be trained in other
activities in the depot in order to reduce the lay offs when the sleeper making
section is shut down. Other activities in the depot include rail welding,
assembling track panels and scrapping old panels. Funding is only available for
26 miles of track re-laying over the next five years, down from 400 miles
re-laid between 1999 and 2003.
BRIDGES
AND TUNNELS
The
Bridge Gang has carried out major structural repairs to Span 11 of the
Barrow
Bridge
, UB140, on the Waterford-Rosslare line.
This work was completed at the end of March.
Repairs
are also being carried out to Thomastown Viaduct, UB87 at 39 miles 810 yards, on
the Kilkenny-Waterford line in preparation for a composite deck renewal, which
is programmed for later this year. The bearings on this bridge were replaced
with ‘Elastomeric’ type bearings in the shutdown of the line between 19-28
April.
Major
repairs are also taking place on UB186, 39 miles 440 yards, Dublin-Rosslare
line, which is the 5-span bridge over the
Avonmore
River
at Rathdrum. OB699 (96 miles 240 yards)
at the south end of Roscommon station was renewed on Sunday 4 April as part of
the bridge renewal safety plan to eliminate all Cast Iron Jack Arch Bridges. On
Sunday 18 April, a new overbridge was installed at Shandra, MP443/8,
in the Portarlington-Geashill section.
SIGNALLING
Mini-CTC
Project
The construction sequence for the Mini-CTC project is
Galway
,
Waterford
,
Tralee
and
Sligo
lines. The second line to be
commissioned was the Cherryville Junction-Waterford West section on Wednesday 28
April and represented an investment of €6.5m.
Work
also continued on the other lines. By mid-April, signals and cables were in
place in Banteer, with signal posts and foundations for location cases
constructed in Millstreet.
Train
Radio The
Cherryville Junction-Waterford line was converted from the open channel radio
system linked to each signal cabin (Mode C) to the standard mainline train radio
system with the commissioning of Mini-CTC. The signalman in Waterford ECP can be
contacted on Channel 61.
From
25 February, train drivers have been able to directly contact the signalman in
the Heuston SER (Signal Equipment Room) who controls the signals in Heuston
station, Inchicore and its approaches, over the mainline train radio system.
Before this, they contacted CTC in Connolly who put them through to Heuston SER.
Axle
Counters To
identify their location for operators of trolleys and permanent way machinery,
the location cases adjacent to axle counter detection heads on both Galway and
Waterford lines are now marked with two horizontal reflective white strips
facing trains entering the section and one reflective white strip facing the
trains leaving the section. Trolleys and other such items are to be removed from
the track before encountering the detector heads.
LEVEL
CROSSINGS
31
March, new Braking Point Marker Boards were brought into use in advance of four
level crossings protected by colour light distant signals in the Thomastown-Waterford
section. The crossings were Rossinan (XW169 at 53 miles 1,012 yards),
Ballygeoghan No.1 and No.2 (XW175 at 54 miles 858 yards and XW176 at 54 miles
990 yards) and Milltown (XW181 at 55 miles 1,144 yards). The colour light
distant signals were installed many years ago closer to the level crossing than
current practice and also without a stop signal in advance of the level
crossing, which is now current practice.
Upgrading
On Sunday 28 March,
Ashfield level crossing XA068 at MP677/8 in the Tullamore-Clara
section was converted from an A-type with road user operated metal gates to a
four-barrier type. Standard flashing lights are provided to alert road users.
Two-aspect green-yellow distant and green-red stop signals give signal
protection to the crossing in up and down directions. Previously there were no
signals. The crossing keeper controls the signals from a local control panel,
but it is later planned to transfer control to the CTC in Connolly.
Closure
In January, IÉ applied for planning permission for the construction of a
new road to allow closure of Commons AHB level crossing (XB018) at MP491/2
between
Drogheda
and
Dundalk
.
The existing road through the level crossing ends in a dead-end following the
construction of the M1 motorway and has virtually no traffic.
CAHIR
VIADUCT
The
contract to re-build the viaduct was awarded to a consortium led by IrishEnco
(See JOURNAL 153). The work is estimated to cost €2.8m and it is expected that
the line will re-open to traffic in July in time for the Diocese of Waterford
and Lismore Knock pilgrimage on 1 August. Initially, work was mainly off-site,
but scaffolding was in evidence at the viaduct in March. Work on site was much
in evidence at the end of April with cranes at river’s edge and at the station
end of the bridge.
The
repaired bridge will feature a new concrete deck slab inside the existing box
girders. The slab will rest on new structural steel cross members, which are
suspended from the top of the existing box girders by new external steel frames
that are in effect saddles on top of each box girder. The box girders will be
repaired and will be fitted with additional internal bracing. The track will
remain to one side of the bridge.
The
remainder of this article appears in IRRS Journal number 154, published June
2004.

Copyright © 2004 by Irish Railway Record Society Ltd.
Revised: August 03, 2004
.
|