|
NORTHERN IRELAND RAILWAYS FUTURE
PLANS In
January, the Belfast Telegraph
interviewed Translink Chief Executive Keith Moffatt. It reported that he is keen
to modernise the entire network and views the recent government-inspired
separation of the railway system into core (the greater On
the He
said ‘Retention of the 80-class trains is not our preferred option. As the new
trains arrive the 80-class units will be phased out’. The existing 80-class
trains could carry on until 2006, when new safety legislation will outlaw slam
door carriages, but the units are becoming increasingly unreliable and shabby. In
January, the Department for Regional Development said that the Minister, John
Spellar, felt it was not practical to allow uncertainty about the future of the
non-core network to linger on until the results of the ‘current cycle of
expenditure’ could be assessed. ‘Consequently, officials in the Department,
together with Translink senior management, are in the process of reviewing both
the scale and timing of the investment required to enable Translink to continue
to operate services on the non-core lines in the longer term and the benefits
which such investment would be likely to produce’. In
March, the Belfast Telegraph reported
that Translink will undergo internal restructuring that will see separate
divisions set up for rail and bus services. Both divisions will report to
Translink Chief Executive Keith Moffatt. Translink came into being in December
1996, taking control of constituent companies of NIR, Ulsterbus and Citybus. In
1968 the Ulster Transport Authority, which had control of road and rail
operations, was disbanded and control divested to the three companies. Translink
confirmed that a reorganisation was taking place with focus on improving service
delivery. FARES Fares
on Northern Ireland Railways were increased by 5% from March 29. PASSENGER
SURVEYS The
General Consumer Council surveyed passengers on public transport in Autumn
2003 Monitoring Results NIR
Observation Ratings (Trains) %
NIR
Individual Customer Performance Ratings (Trains)
%
INFRASTRUCTURE Bleach
Green Junction-Whitehead
In January, NIR advertised for contractor(s) to re-lay
the line between Bleach Green Junction and Whitehead. The project is ‘to
excavate, drain, relay and signal approximately 13-kilometres of double track
and 3-kilometres of single track to be suitable for 90-mph running. This will
consist of the removal of existing line, excavation of the track bed,
reinstatement of fresh ballast and relay of new CWR track on concrete sleepers
at 1,600 mm gauge, together with complete re-signalling of the new line with
colour light multi aspect signalling controlled from Belfast Signalling Control
Centre’. The value of the work is estimated at £12.9m but work is not now
anticipated to start until April 2005. Coleraine
- Portrush
Due to construction of a subway at Dhu Varren by Department of the
Environment Roads Service, trains were substituted by bus on Saturday 17 April
and most of Sunday 18 April. The line re-opened with the 16.59 Coleraine-Portrush. Belfast-Dublin
To reduce rock-face instability, rock-bolting and removal of loose rock
is taking place in the Wellington Cutting south of Newry. A 20-mph speed
restriction is in place between MP643/4-66 and
consequently train punctuality has suffered. Other
NIR have taken delivery of a new Plasser & Theurer USP5000RT ballast
regulator. It is numbered 7010. Ballast
hoppers 521-526, built in STATIONS Carrickfergus
Carrickfergus station won the London Underground Award at the National
Heritage Awards. This is the second year in a row that the station has won an
award. The award was for the restoration of the subway and installation of
lifts. The judges were particularly impressed with how NIR managed to make the
station fully compliant with the latest Disability Discrimination Act, while
retaining the character of our 19th century station building. Judges praised the
sympathetic restoration of the subway tiling, some of which have been replaced
with tiles sourced from London Underground. They were also impressed with how
the two new lift towers were designed to blend in with the original station,
being constructed from recycled Platform
Extensions To
accommodate the new CAF railcars, which are longer than existing railcars, a
programme of platform lengthening is being undertaken. Among platforms being
extended were those at Portadown (up), Moira, Lisburn, Lurgan, Balmoral, DEPOTS Site
clearance work has commenced for the construction of the new railcar maintenance
depot at Fortwilliam, north of SIGNALLING Part
of the signalling system at Lurgan, which was destroyed by terrorists some years
ago, was replaced between Saturday 28 February and Sunday 7 March. Absolute
block working with a temporary timetable was used to permit trains to continue
to operate. The block section was Portadown to Moira in both directions and
train drivers received a Temporary Block Working ticket from a hand-signalman
when entering the section. A 50-mph speed limit applied. There was also some bus
substitution between Lisburn and Portadown. LOCOMOTIVES
AND ROLLING STOCK Locomotives
GM 112 returned to NIR
for a short period in January/February, before heading south again where it was
based in the Connolly/Drogheda area initially. It featured on Navan-Dublin Tara
Mines trains in February. De
Dietrich
The
riding quality of the De Dietrich coaches has been under evaluation by De
Dietrich staff. On Friday 6 February, a test train consisting of
9003+9402+9205+9103 + 209 operated between 80-class
The struggle with ageing equipment is adversely affecting reliability of
services as illustrated by recent failures. Power car 8092 suffered major engine
damage on 20 February (piston out of block). Others to suffer engine damage were
8081 (March), 8082 (February), 8087 (November) and 8094 (returned to service in
late February). Parts have been salvaged from
8084 (December 2002)
and its
engine is being
repaired. Power car 8067, damaged in
the Downhill derailment, has been withdrawn. 450-class
8455 returned to service in mid-January having been out of service for
over a year. Overhaul of 8453 commenced in January. 3000-class
The 23 new railcars from CAF will be known as the 3000-class, with the
sets numbered 3001-3023 and individual vehicles within the sets numbered 3301-23
(driving motor cars - DM1), 3401-23 (motor intermediates - M) and 3501-23
(driving motor cars - DM2). All cars are motorised with a MAN diesel engine
driving a Voith hydraulic transmission. Maximum speed is 90-mph. There are
painted in a silver and blue livery. The
3-car diesel multiple units can be altered to operate as 2-car or 4-car sets by
the removal or addition of an intermediate carriage. The maximum train size will
be 12-cars. Six sets will equipped for operation on IÉ (CAWS and IÉ train
radio). The
units comply with British safety legislation including new regulations on
interior impacts, and safety and accessibility for the disabled. All carriages
have one driven and one non-powered bogie. The
first 3-car set, No. 3001, was delivered to Belfast Docks on Monday 19 April by
the MV Linda Buck. Each vehicle was offloaded onto a trailer and brought by road
to Translink’s
General Manager (Rail), Mal McGreevy, said the arrival of the first of the new
trains would be a milestone for the NIR. He said: ‘These trains, which we have
called the C3K, are the beginning of a very exciting period for NIR. The £80m
investment we have been able to make in rolling stock will go a long way towards
improving levels of reliability and comfort, as well as the perception of rail
as a modern, convenient means of transport. We expect all the trains to be
delivered by mid-2005, and for them all to be in service by the end of next
year’. The
trains will be subjected to a rigorous testing and commissioning programme of up
to 16 weeks before entering service. Each train will have to complete 2,000
miles of fault free trial running before entering revenue service. A further
£30m is expected to be spent on parts and maintenance over the first 15 years
of the trains' operation. Storage
Movement
On Sunday 28 March, several out-of-service vehicles were moved from
Copyright © 2004 by Irish
Railway Record Society Limited
|