
Irish Railway Record
Society
TRACK
Mallow-Tralee
The main platform track in
Tralee
station was excavated and re-laid with CWR on concrete
sleepers in November. The run-round loop and ‘liner’ road were also re-laid
using second hand panels of track shortly before the cancellation of liners. The
main and loop tracks in Banteer and Rathmore have also been re-laid with CWR.
Portarlington-Galway
The loop in Geashill has been re-laid in
CWR.
Athlone-Westport/Ballina
Both platform and loop track in
Westport
are now CWR. In December, the down loop in Castlerea was
re-laid with CWR from the tip of the east points to the level crossing. Work
continues on strengthening embankments in the Claremorris-Manulla section. This
is also continuing in the Manulla-Ballina section along with easing slopes on
cuttings, improving drains, renewing fencing and improving level crossings.
Dublin
Heuston-Cork
Facing crossover No. 748 at the south end
of Lisduff was renewed during an overnight possession on Saturday 20 / Sunday 21
September. On the Saturday, the 17.30 Dublin Heuston-Limerick, NIR 112+6
Cravens+GSV, ran to Ballybrophy only. Passengers joined the regular 19.00
Ballybrophy-Limerick via Nenagh, 144+GSV+1 Cravens. However, the single carriage
was overcrowded with about 80 passengers. The 17.30 set then went through the
complicated manoeuvre from the
Cork
lines to the branch platform and waited to provide a
Limerick
connection out of the 19.15 Dublin-Cork. It ran as a 20.40
special to
Limerick
via Nenagh.
Cork
line passengers from the 19.15 Dublin-Cork and 19.15
Cork-Dublin were transferred by bus between Thurles and Portlaoise. On the
Sunday, bus transfers were used for trains up to and including the 12.05
Dublin-Cork and 10.50 Cork-Dublin.
Cork-Cobh
The trailing crossover at the
Cork
end of
North Esk
yard was renewed during a complete line closure from
Thursday 13 to Sunday 16 November. The old crossover had been subject to a speed
restriction for some time. During the same closure, OB418 at 170 miles 1010
yards, which had a 6-ton weight limit for road vehicles, was renewed on 14
November. A temporary level crossing was constructed for road traffic.
Dublin
Connolly-Rosslare
Strand The
down platform, middle road, and up loop in Bray have been re-laid with CWR on
concrete sleepers. The down platform in Rathdrum was closed for extension from
22 September until 17 November. Both up and down platforms in Wicklow have been
extended at the Rathdrum end to take 6-car railcars. The up loop in Wicklow was
out of use in late November /early December for this work. With no facilities to
cross trains in Wicklow, the 07.10 Maynooth-Rosslare Europort was either held
for 50 minutes in Greystones to cross the 07.20 Rosslare Europort-Dublin
Connolly or the Maynooth train ran to Rathdrum, depending on how the up train
was running. On Sundays in December when the train operated throughout, the
10.00 Dublin Connolly-Rosslare Europort was deferred to 10.20 and crossed the
08.45 Rosslare Europort- Connolly in Greystones instead of Wicklow. The down
siding, points and associated signals were also removed.
Re-laying
outstanding sections of the line with CWR on concrete sleepers continued
throughout the autumn. During re-laying of the gap between 511/4-533/4,
707/8-727/8 and 731/2-757/8,
the 07.10 Maynooth-Rosslare Europort and 14.45 Rosslare Europort-Dublin Connolly
were substituted by bus between Arklow and Gorey or Enniscorthy as appropriate.
Re-laying was suspended when the line north of Greystones was closed on
Saturdays and Sundays for DART upgrading works and was generally carried out
from Monday to Thursday.
During
excavation and re-laying of Ferrycarraig tunnel, all trains were substituted by
bus south of Enniscorthy after the 07.20 Rosslare Europort-Dublin Connolly on
Monday 20 October until the 13.25 Dublin Connolly-Rosslare Europort on Thursday
23 October. There was a similar closure and bus substitution to allow excavation
and re-laying of the platform in Wexford station through to the tip of the level
crossing at Wexford Quay from Monday 17 November until Thursday 20 November. On
weekdays during November and December, the 07.10 Maynooth-Rosslare Europort and
14.45 Rosslare Europort-Dublin Connolly were substituted by bus south of
Enniscorthy for plain track re-laying. By end of 2003, CWR had been installed
from 893/8-923/4.
On
Sunday 23 November, 152+185+11 bogie wagons of CWR+re-laying gantries was held
in Wellingtonbridge from 14.48 until 17.34 due to a possession while en route
from Portlaoise to Wexford. The Waterford-Rosslare Strand line is normally
closed on Sundays but was opened because the line from Pearse to Bray was closed
as part of the DART upgrade project. The following Monday, the set for the 07.05
Rosslare Europort-Waterford departed Water-ford empty at 05.15 for Rosslare and
was formed by 074+GSV+2 Cravens.
Limerick-Ennis
Re-laying with CWR on concrete sleepers and
upgrading work on bridges continued into winter (See JOURNAL 152). Bridge work
included the renewing the Canal Bridge OB6 at 2 miles 240 yards, refurbishment
of the Shannon Bridge UB16 and renewing the deck of the Oil River Bridge UB42 at
12 miles 200 yards. Other work included strengthening of embankments, easing
slopes of cuttings, renewing fencing and improving views at level crossings.
Both platforms in Ennis have been excavated and re-laid. Trains remained
completely suspended from end of September until early December. Bridge and
track re-laying work have now been completed.
Ballybrophy-Killonan
Junction
To facilitate track re-laying with second hand materials between
Cloughjordan and Nenagh, the 09.45 Ballybrophy-Limerick and 15.00 return were
substituted by bus on various weekdays from mid-October into December.
Dublin-Belfast
The loop in Skerries has been re-laid with CWR.
Drogheda-Navan
In November and December, relaying with
second hand materials took place at night between
Drogheda
and Navan. The fourth
Tara
mines train was cancelled as a result.
Limerick
Cement Factory Sidings
Yard track has been re-laid using second-hand jointed rail on timber
sleepers.
CWR
Summary
The status of re-laying at the end of 2003 is noted below. CWR refers to
Continuous Welded Rail laid on concrete sleepers, although there are locations
such as Sandycove-Dalkey where hardwood timber sleepers are used. Large bridges
where track is often laid on timber waybeams are excluded from the data below.
On the Cherryville Junction-Waterford, Mallow-Tralee and Maynooth-Sligo lines,
new points and crossovers will be installed as part of the Mini-CTC project.
Dublin-Cork:
The line is fully CWR except for the platform tracks at Limerick Junction and
the loop platforms in Ballybrophy and Mallow. The points at Portarlington have
not yet been renewed and a 30-mph speed restriction applies through the station.
The main tracks through Ballybrophy station are continuous welded rail on timber
sleepers and a 70-mph speed limit applies.
Cork-Cobh:
fully CWR between both stations.
Mallow-Tralee:
fully CWR except the station at Farranfore and the bay platforms in Killarney
and
Tralee
.
Limerick-Limerick
Junction: fully CWR except the loop in Dromkeen and station areas of
Limerick
and Limerick Junction. Platforms 2 and 3 in
Limerick
station are CWR.
Limerick-Ennis:
fully CWR, including the main but not loop platform in Ennis.
Portarlington-Athlone-Galway:
fully CWR, except for the loop in Clara and No. 2 platform in Athlone, both of
which have relatively new jointed track.
Athlone-Westport:
fully CWR except for Ballyhaunis down platform and the loop in Knockcroghery,
which is relatively recent jointed track.
Manulla
Junction-Ballina: fully CWR.
Dublin-Sligo:
fully CWR except for the down platforms at Longford, Dromod and Boyle stations
and Inny and
Shannon
river bridges.
Dublin-Dundalk-Border:
fully CWR from East Wall Junction.
Dublin-Rosslare
is the only radial line not yet fully re-laid with CWR, but is being re-laid at
present and is over 88% complete. There is CWR continuously from Dublin Pearse
to Enniscorthy exclusive, with the exception of the platforms at
Dún Laoghaire
, Dalkey and Wicklow (main) and MP611/8-63.
South of Enniscorthy there are long stretches of CWR and the longest stretch of
jointed track is 35/8 miles. Jointed track total is 113/4
miles.
The
Ballybrophy-Killonan Junction and Limerick Junction-Rosslare Strand lines have
small sections of CWR, but are effectively all jointed track. Drogheda-Navan-Kingscourt,
Waterford-New Ross, Mullingar-Athlone, Glounthaune-Youghal and Limerick-Foynes
are all jointed track.
Other
IÉ are now importing long welded rail through
Belfast
Port.
The rail is road hauled to
Adelaide
yard, where it loaded on trains for Portlaoise for welding
into ‘strings’ of long welded rail (LWR). A path was published showing a
Mondays-Only 10.30 Portlaoise-Belfast and a Wednesdays-Only 08.25 Belfast-Portlaoise.
In recent
years, rail
had been
imported
exclusively through
Waterford
Port.
IÉ
has issued an enquiry for ‘Steel Railway Rails mainly type 54E1 to
specification EN 13674 - Part 1, 1999 (formerly UIC 54 kg/m). Quantities
required are estimated at between 5,000 tonnes and 10,000 tonnes per year for a
three-year contract period with an option to extend the contract for a further
one to three years. Contract(s) may be awarded to more than one supplier’.
This equates to between 28 and 56 miles of track per annum.
SIGNALLING
Mini-CTC
Project
The
Galway
line Mini-CTC system was integrated into the Mainline CTC
system controlled from Dublin Connolly on 30 November. All signals and points
between Ballinasloe and
Galway
are now normally controlled from Connolly. In mid-December,
Closed Circuit TV (CCTV) monitoring of the level crossings at Ballinasloe,
Woodlawn and Athenry was transferred to CTC in Connolly.
Installation
work continues on the
Waterford
,
Sligo
and
Tralee
lines. The
Waterford
line is next to be commissioned, scheduled for late spring
2004. Colour light signals were erected in Athy during November. Athy loop will
be extended at the south end and concrete sleeper track panels were delivered to
site during November. Some signals had been erected in Muine Bheag and Carlow by
end of December.
Work
on the Mallow-Tralee line is concentrated in the Banteer area with signal bases
and cabling in place by December. The same was the case at Dromod on the
Sligo
line.
Bray
The
set of hand points between No. 1 and No. 2 Wicklow sidings in Bray were
converted to trailable power points on Friday 10 October. The power-operated
points are operated by train drivers and are not interlocked with signals, but
have stencil type indicators indicating which siding the route is set for.
Duplicate control and indication boxes are mounted 40-metres and 80-metres from
the points on the Bray side of the sidings.
Train
Radio The
train radio between
Cork
and
Cobh
was converted in November from open channel Mode C, channel
18, to secure Mode A, channel 75, as used on the CTC system. Channel 75 now
extends from MP 421/2 at Portarlington to MP 1771/4
at
Cobh
. Mode A provides direct communication between the train
driver and the CTC Signalman or Regulator in Connolly. For the
Cobh
line, CTC will then connect the driver to the appropriate
controlling signalman.
A
similar conversion from Mode C to Mode A took place on the Dublin-Rosslare line
in November. Mode A, channel 61, now covers from MP 1 at
Lansdowne Road
to MP 56 near Gorey. The gap in radio coverage that
previously existed between MP 38 and MP 43 has been eliminated. Mode C, Channel
28, applies south of MP 56.
With
the transfer of control of the Ballinasloe-Galway section to CTC on 30 November,
secure train radio (Mode A), channel 63, covers from MP46 (Portarlington-Geashill)
to
Galway
.
Signal
Cabins With
the temporary closure of the line between Limerick Junction and
Waterford
, opportunity has been taken to refurbish Carrick-on-Suir and
Clonmel signal cabins. Parts of redundant interlocking frames from the
Ballinasloe-Galway line were used, Athenry providing parts for Clonmel.
Ennis-Athenry
The manual staff for the Ennis-Athenry section is now held by the Ennis
Permanent Way Inspector, who will conduct any engineers trains in to the
section. No other trains are permitted to enter the section
The
remainder of this article appears in IRRS Journal number 153, published February
2004.

Copyright © 2004 by Irish Railway Record Society Ltd.
Revised: March 10, 2004
.