
Irish Railway Record
Society
TRACK
Mallow-Tralee
The main platform track in Killarney station was re-laid with CWR in
May.
Portarlington-Galway
The loop in Clonnydonnin
was re-laid with CWR on concrete sleepers in May.
Athlone-Westport/Ballina
The remaining plain track sections between Athlone and Westport have been
re-laid with CWR on concrete sleepers. Track re-laying on the Athlone-Westport
line finished on 14 July, with ‘stressing’, ballasting, regulating and
tamping work continuing throughout the summer. During the re-laying of the
section between MP1073/4-1097/8, the
08.05 Dublin-Westport and 13.25 Westport-Dublin were substituted by bus between
Roscommon and Castlerea.
For
re-laying between MP139-1403/4 and MP1447/8-1453/4,
the 08.05 down and 13.20 up were substituted by bus between Claremorris and
Westport. The Monday-Friday 11.18 Manulla Junction-Ballina and 13.09
Ballina-Manulla Junction were also substituted by bus throughout the summer and
into September to allow CWR to be ‘stressed’. During this period, the main
and loop platform tracks in Claremorris were excavated and re-laid, with this
work continuing into September.
Dublin
Heuston-Cork Facing
crossover No. 699 connecting the up and down lines at the west end of Inchicore
was renewed over the weekend of 14/15 June (See JOURNAL 151 for drawing). The
loop tracks in Hazelhatch and Sallins have been re-laid with CWR on concrete
sleepers.
Renewal
of the Lisduff north-end trailing crossover No. 751 resulted in the 19.15
Dublin-Cork and 19.15 Cork-Dublin being substituted by bus between Portlaoise
and Thurles on Saturday 6 September. The 21.00 Dublin-Cork was substituted by
bus between Portlaoise and Cork. On Sunday 7 September, all trains up to the
12.05 Dublin-Cork and 10.50 Cork-Dublin were substituted by bus between
Portlaoise and Thurles. New Westinghouse Type 63 point machines have replaced
the Clamp-Lock type used previously. The north and south turnouts to the ballast
sidings had previously been renewed on 15 June.
Dublin
Connolly-Rosslare Strand Re-laying
with CWR on concrete sleepers between Gorey and Enniscorthy re-commenced in May
and resulted in the 07.20 Maynooth-Rosslare Europort and 14.45 Rosslare
Europort-Connolly being substituted by bus south of Gorey. On several Sundays,
the 08.45 and 14.43 Rosslare-Dublin and 10.00 Dublin-Rosslare did not operate
south of Gorey. Substitute buses were provided. A large stockpile of concrete
sleepers was built up in Wexford station. However, many of these were
transported from Portlaoise by lorry rather than by rail. Permanent Way trains
often used 071-class locomotives, with 083 observed in Enniscorthy and 079
observed in Wexford on 24 May. However, since June they have generally been
replaced by pairs of 141/181-class locomotives.
Due
to road traffic congestion in Gorey, which badly delayed substitute buses in
previous summers, re-laying was suspended south of Gorey during the peak summer
period. Delays to substitute buses had often been more than an hour, for a
service that had only a half-hour turn-round in Dublin. Instead, re-laying moved
to completing the Wicklow-Rathdrum sections during July and August. On Monday to
Thursday, the 13.25 Dublin-Rosslare Europort ran to Wicklow, where passengers
transferred to buses that took them to Arklow. There, a second train formed a
continuation to Rosslare at 14.50. The second train was formed by the stock of
the 07.03 Longford-Dublin Pearse that ran empty at 09.18 from Pearse to Arklow
before the possession started. It was usually an 071-class + GSV + 6 Cravens.
All other trains ran normally.
After
the peak holiday season was over, re-laying re-commenced south of Gorey. From 7
September, the 07.10 Maynooth-Rosslare Europort and 14.45 Rosslare
Europort-Dublin Connolly were operated by bus south of Gorey.
By
mid-September, track re-laid was from MP291/2-353/4
and MP651/4-707/8 with long welded
rail laid out to close the gap to MP727/8.
Excavation
and re-laying with CWR on concrete sleepers of the south part of the up platform
in Bray saw DART services terminate in Dún Laoghaire from 21.00 on Saturday 6
September, with minor alterations the following morning. The remainder was
completed two weeks later in a similar manner.
Dublin-Sligo
Major track rationalisation took place in Mullingar during a complete
line closure between 10.00 on Wednesday 17 September and 18.30 on Wednesday 24
September. It saw the removal of the last traditional MGWR double-track junction
(between Sligo and Galway lines), removal of the double-slip crossover providing
access to the up sidings, removal of the single-slip crossover allowing
movements between the up sidings and the down Sligo line and the slewing of the
down Galway line into the up Galway line between existing platforms. The former
down Galway platform line is now a siding.
New
semaphore signals were erected pending completion of the Mini-CTC project. They
were a new up starting signal from the down main, new up advance starter and new
fixed at danger down starter from the Galway platform line. The latter line is
now known as the ‘up and down main’. Effectively, the rationalisation
incorporates much of the final Mini-CTC track layout of a single passing loop on
the Sligo line and a single line on the Galway line, but with semaphore
signalling (limited) in advance of re-signalling. Other work included installing
drains, excavating and re-laying with CWR on concrete sleepers the Sligo line
platforms and approaches. Substitute buses ran from Edgeworthstown to Enfield.
Limerick-Ennis
Re-laying with CWR on concrete sleepers continues on the
Limerick-Ennis line. During the summer re-laying was done by road-rail
excavators, rather than using the beam re-laying machines. Work was concentrated
on difficult areas, such as under bridges and in deep cuttings. As a result,
progress has been slow. The line was generally closed completely from Monday
morning until Friday evening, but with some periods of complete mid-week
closure. Passenger train services were restored for July and August.
From
late August, re-laying with the beam re-laying machines commenced, with about
two miles to be completed. This consisted of 11/2 miles
near Ballycar and 1/2 mile from the down distant signal
into Ennis station. The latter was re-laid by early September. Midday trains
were suspended from Monday 25 August to Thursday, 28 August. The line was closed
completely from 08.30 on Monday 1 September until 17.00 on Friday 5 September,
with midday trains suspended in subsequent weeks.
Limerick
Junction-Waterford-Rosslare Strand
The Waterford-Wellingtonbridge section was closed from 08.30 on
Saturday 26 July until 18.00 on Sunday 27 July for signalling and electrical
repairs to the Barrow Bridge. Substitute buses operated.
The
Summer Only 07.05 Rosslare Europort-Limerick and 09.35 Limerick-Waterford were
suspended between Waterford and Limerick Junction during some of the busiest
weeks of the year, including the August Public Holiday weekend, to allow
re-laying near Cahir. Suspension was from Monday 28 July for two weeks. The line
was open each day in time for the 15.42 Limerick-Rosslare Europort. The 11.34
Waterford-Limerick empty bulk-cement ran via Lavistown Loop and Kildare. The
section between MP36-371/2 was re-laid using jointed
bullhead rail.
Dublin-Dundalk
Single line working was used to allow tamping of track between Drogheda
and Dundalk on weekdays in May. The 06.55 Arklow-Dundalk and 10.34
Dundalk-Pearse operated to and from Drogheda only. The 09.55 Dundalk-Connolly
operated from Drogheda. Delays and disruption to Enterprise services were severe. On Monday 26 May, the 10.30
Belfast-Dublin, 8-piece De Dietrich (DT9002) pushed by 207 arrived in Connolly
at 13.16, instead of 12.35. This train forms the 13.20 Dublin-Belfast. Smart
working by station staff in Connolly saw the train depart at 13.28.
Four
new sidings were commissioned in Dundalk in July. They are located on the down
side and can hold 8-car trains. They are accessed off the running loop. Siding
No. 1 is 262 metres long, siding No. 2 is 286 metres long, siding No. 3 is 262
metres long and No. 4 is 263 metres long. No signalling alterations were made,
with hand points being used.
Howth-Howth
Junction Track in Howth station was excavated and re-laid during weekend
possessions in May and June. Panels of concrete sleepers were laid using
road-rail excavators, with CWR subsequently replacing the jointed rail. The
branch is now completely laid with CWR. On Sunday 18 May, 078 worked a spoil
train at Howth. As it was unable to run-round, 083 ran light engine from
Connolly in the afternoon and hauled the train into North Wall.
Weedspray
The weedspray programme continued into the summer with Drogheda-Navan
sprayed on Friday 16 May. Mullingar-Athenry on Friday 23 May. Athenry-Ennis was
sprayed on Tuesday 27 May. The train sprayed the Limerick cement factory sidings
on Thursday 5 June. The programme concluded on Saturday 7 June when the train
departed Portlaoise at 08.40 and sprayed the Dublin suburban lines. Locomotive
175 was used throughout. Lines not sprayed by the train this year included
Navan-Kingscourt, Tara Mines, Glounthaune-Youghal, Bray - Rosslare Strand,
Cherryville Junction - Waterford, Athenry-Galway, Athlone-Westport/Ballina,
Mallow-Tralee, Howth Branch, and Limerick-Foynes.
Tamping
IÉ has advertised for contractors to carry out tamping and
regulating over a portion of its network and
may also include new track.
Tenders
IÉ has sought suppliers for ‘Points and crossings layouts in new
perfect quality grade 900A rail steel, on hardwood timber sleepers complete with
all ancillary fastening and construction materials for a period of three years
commencing mid-2003 with an option to extend for a further two years’. IÉ has
also advertised for approximately 350,000 tonnes per year of ballast.
IÉ
has sought tenders for the collection, removal and disposal of refuse, litter
and material collection in addition to weed spraying along specified sections of
railway lines and in specified locations of the Dublin Division including DART
lines for a thirty-month period. The area extends to stations such as
Portlaoise, Dundalk and Rosslare.
BRIDGES AND TUNNELS
Several
bridges on the Limerick-Ennis line have received attention. Two spans of the
Shannon Bridge, UB16, at 3 miles 936 yards are being refurbished and repainted
this year. The Canal Bridge, UB6, at 2 miles 240 yards was renewed during a full
line closure at the end of September. The three steel spans were replaced by new
concrete spans. New decking was added to the Oil River Bridge, UB42, at 12 miles
200 yards.
OB196
at the south end of Lisduff was renewed on 15 June. OB311 at 135 miles 520 yards
between Charleville and Buttevant on the Dublin-Cork line was renewed on 6
September.
The
Royal Canal Bridge, UB389, just north of Mullingar station was renewed with a
‘silent’ bridge on Friday 19 September.
The
remainder of this article appears in IRRS Journal number 152, published October 2003.

Copyright © 2004 by Irish Railway Record Society Ltd.
Revised: January 07, 2004
.