<
Irish Railway Record
Society

Galway
Mini CTC
Following
the Knockcroghery accident, on 8 November 1997, a major relaying programme to
renew more than 400 miles of track was implemented. The Galway line was the
first to be renewed. This covered the plain track sections between the stations
but not the station layouts. It was also decided that four routes (Galway,
Waterford, Kerry and Sligo) should have a simplified CTC system provided in
conjunction with a total renewal of the station layouts. Much of the track
layouts in the stations were designed for a traffic pattern no longer extant. In
MGWR era and into CIÉ days, the Galway passenger service was four trains each
way daily with through coaches to and from Westport and Sligo. It was only with
the arrival of the AEC railcars in 1954 that the Sligo line had its own through
services from Westland Row. The evening Westland Row-Galway and the morning
return was a double-diesel, to use the railway term of the day, two 4-car AEC
sets which divided at Athlone and coupled up again in the morning thereby
proving a Westport through service. After the demise of the railcars, the Galway
and Westport lines became independent – each having their own through
services. The arrival of the Mark ll carriages in 1973 led to longer trains but
retaining the four services each way daily. This lasted until the Athlone
commuter service was extended to work to and from Galway thereby creating a
fifth though service each way on weekdays, breaking a pattern that existed since
Victorian times.
With
the arrival of the 071 locomotives and the Mark lll carriages, nine vehicle
trains became the norm – far from the 4-4-0 steam locomotive and three or four
carriages in the MGWR days for which the line was designed. On the freight side,
Ballinasloe was designed to cater for the great fair days when up to six cattle
specials would operate to North Wall. This traffic is no longer available with
the change in cattle dealing from fairs to cattle marts and, in more recent
times, with the arrival of meat factories and few cattle exported live.
Athenry
layout was fitting of a major junction, originally with double junctions at both
ends and two turntables. Galway has always had its layout constrained by the
approach lines being over Lough Atalia Bridge spanning what is, in effect, an
inlet of the Atlantic.
Before
the mini-CTC project, sections of the layouts were life expired and signed out
of use leading to difficulties in operation. Special instructions covered the
degraded conditions.
The
fundamental difference between mini-CTC systems and traditional CTC is the use
of axle counters between stations instead of track circuits. It is only in
recent years that reliable, reasonable cost axle counters have become available.
Also, mini-CTC does not have CAWS (Continuous Automatic Warning System).
In
designing the layouts, modern train sizes and operating requirements were
leading considerations and the emphasis was keeping the layouts simple and easy
to maintain. In case of failure, a simple layout is faster to scotch and clip
points and get trains moving quickly. A design consideration, on the Galway,
Sligo and Kerry lines, is the signalling of the station level crossings. There
are three on the Galway line (Ballinasloe, Woodlawn and Athenry), four on the
Kerry (Banteer, Millstreet, Rathmore and Farranfore) and one on the Sligo
(Killucan). With ongoing difficulties with timetabling trains between
Ballinasloe and Athenry and outline plans to increase passenger train frequency
on the Galway line the 30-minute block section between Athenry and Ballinasloe
needed an intermediate loop. This was provided at Woodlawn making the sections
from Galway to Athlone 16, 10, 13, and 19 minutes (stop to stop) in length for a
9 coach Mark lll and 071 or 201-class locomotive. Previously the sections were
16, 23 (assuming no stop at Woodlawn or Attymon), and 19.
Today,
the scheduled traffic on the line on weekdays is five passenger trains in each
direction and a return freight train from Galway to Athlone at night. On Sundays
there are also five return passenger workings but concentrated on the afternoon.
Occasionally, there are passenger specials either for sporting fixtures or to
cater for the high number of students who travel in summer to learn Irish in the
Gaeltacht area in the west of the county.
The
new layout at Ballinasloe has simply up and down lines so trains may be crossed
and a siding on the up side. In the current timetable, no trains are scheduled
to cross at Ballinasloe. To avoid blocking the busy level crossing when trains
were in the station the turnout at the Dublin end was moved westward to
eliminate the problem.
Woodlawn
never had a second platform or loop but had an eccentric layout whereby trains
could cross by one propelling into a siding to let the other pass. The new
layout provides a simple passing loop with no traps or sidings. In the current
timetable the 16.50 from Heuston to Galway does not call at Woodlawn but crosses
the 18.20 from Galway to Dublin, which does serve Woodlawn.
The
once complex layout at Athenry, built largely to cater for cattle specials
arriving and departing in four directions, was greatly simplified. The
connection to the Claremorris line was not retained as the line is currently out
of use. In the event of the line re-opening a connection could be made as part
of the line’s possible re-construction. At the western end there is a power
operated connection to the Ennis line and a siding trails in for freight or
ballast loading. Special arrangements exist for the inter-working between the
CTC and Ennis signalmen when trains require to operate between Athenry and
Ennis. The are two trap points controlling access to the Ennis line. It is not
signalled for passenger movements.
Any
major re-designing of the Galway station layout is made difficult by the nature
of the site. Some simplification of the layout took place but perhaps, the most
significant change was the provision of the locomotive release at the
buffer-stop end of the main platform. To avoid having to reverse trains out onto
Lough Atalia bridge to allow the locomotive run around, trains now discharge
their passengers and set back to clear the crossover. The locomotive is then
uncoupled and pulls forward to allow the signalman reverse the crossover,
permitting the locomotive to go out onto the bridge where the driver can change
ends through the engine. The locomotive comes back onto the train, propels it a
short distance almost to the buffer stops and ready to board passengers.
Level
crossings at stations are all four-barrier CCTV monitored type. These are
controlled form adjacent rooms known as Re-locatable Equipment Buildings. During
the initial six months of operation they are worked from the local pedestal
panel normally only used in the event of control being lost at the CTC. The
lights and barrier movements are initiated by approaching trains suitably timed.
When all four barriers are down the gate operator checks that the crossing is
clear and clears the vital control to allow the protecting signals give a
proceed aspect. The Automatic Open Crossings, designated type LB, at Healys,
Frenchfort and Garraun are monitored by Athlone, as is Oranmore AHBs. Other
level crossings have telephone communication with the Athlone ECP.
All points are operated by Westinghouse type 63 machines.
The
mini-CTC projects do not include any upgrade at mid-section level crossings
except where they are close to stations such as at Athenry where Caherryon to
the east and Castle Lambert on the Galway side are both included in the Athenry
signalling. Separate projects are dealing with mid-section crossings.
The
new mini-CTC systems are based on a central computer system, supplied by
Westinghouse Rail Systems Ltd. of Chippenham, working all the locations. Hence,
all signals and points have a GL (Galway Line) identity. The system has three
parallel processors and two have to agree before a route is set. Fibre-optic
lines link the computer with the stations. Axle counters work the plain track
sections between the stations. The axle counters communicate with each other,
also, using the IÉ fibre-optic network. Should the cable between two
axle-counters be damaged, the system will seek an alternative route, such as
Athenry-Woodlawn via Ennis - Limerick - Portarlington – Athlone. Copper data
lines link the fibre-optic cable at stations with the various station modules.
Track circuits are provided from the down home signal berth track through the
station area to the up home signal berth on through stations.
The
Galway line console – known as Galway Line ECP - is located in Athlone in the
same building as the Athlone Emergency Control Panel. The latter is used to
operate Athlone in the event of the CTC losing control.
The
line-side signal and point modules each have 2 computers/loaded Eproms and each
module has a unique number which is addressed by the interlocking in Athlone up
to a maximum of 63 modules. Each point module can handle 4 point ends, with
signal modules handling 2 four-aspect signals including route indicators. Each
module is ‘listening’ to both data streams simultaneously. The modules
receive a ‘heart beat’ signal every 0.6 seconds to ensure they are working
and communication is still active to the Galway Line interlocking.
The
workstation consists of two Flatron colour screens giving the layout and
indications. The signalman operates the system using a roller ball and a
keyboard similar to most modern CTC systems. The mainline train radio system was
extended to cover the entire route. The system is equipped with SPAD (Signal
Passed At Danger) indications so that in the event of a driver passing a signal
at danger an alarm is immediately activated and the signalman can immediately
contact the driver directly.
To
facilitate installation of points and crossings there were a series of permanent
way possessions during the month prior to the week the line closed for
commissioning of the system. During this week a locomotive was used to test the
routes. The new system was commissioned at 16.45 on 8 June 2003 with Signalman
Kieran Kelly the first signalman.
ATHENRY-ENNIS
SECTION
The
section between Athenry and Ennis is worked by the Manual Token System with
special arrangements. All the movements are under the control of the Ennis
signalman. In the up direction the section commences at a “Stop & Obtain
Instructions” board on the opposite side of the track to the “Limit of
Shunt” board. At Athenry it terminates at a similar board beyond which are two
trap points facing in opposite directions. These ensures no train enters or
leaves the section without the agreement of the Ennis and Galway Line signalmen
(either in Athlone if locally controlled or the CTC).
In
the down direction the section commences at a “Stop and Obtain Instructions”
board on the Athenry side of the traps and terminates at the Ennis Outer Home
signal. The manual token is normally housed in the “Line Closed” apparatus
in Ennis cabin. This is associated with the AHBs in the Ennis-Athenry section
(Kiltartan, Ardrahan & Craughwell). Before a train can leave Ennis, the
signalman must ascertain from the Galway Line signalman that the line is clear
at Athenry station for the train to exit the section. He removes the token from
the Line Closed apparatus and hands it to the driver who is instructed to
proceed to the “Stop and Obtain Instructions” board at Athenry. Upon arrival
the guard takes the token to a special panel where he inserts the token and
rotates it 90 degrees. If the hand-operating crank handle for the traps is also
in the panel, the guard obtains the permission of the Galway Line signalman to
close the traps using a switch on the panel. This allows the train enter Athenry
station. On observing the tail-lamp the guard advises the Ennis signalman that
the train has left the section and opens the trap points.
The
guard then places the token in a subsidiary instrument and holds down the tapper
key to allow the Ennis signalman withdraw a token. This is placed in the “Line
Closed” apparatus, ready for the next movement from Ennis to Athenry. Should
the next movement be from Athenry the down train proceeds to the “Stop &
Obtain Instructions” board and the guard goes to the subsidiary instrument and
requests the Ennis signalman for a token, When the token is obtained and
inserted in the panel the traps are closed, the train enters the section clear
of the traps which are then closed. The token removed from the panel. Upon
arrival in Ennis the token is stored in the “Line Closed” apparatus.
Mr.
Pat Judge, was the engineer in charge of installing the system and Training
Executive David O’Keefe provided the training for the four signalmen who
currently operate the system.

Copyright © 2004 by Irish
Railway Record Society Limited
Revised: January 07, 2004
.