Irish Railway Record Society

Home Up Operations 151 Rolling Stock 151 Stations 151 Track 151 NIR News 151

TRACK

Mallow-Tralee   The remaining plain track section between Killarney and Farranfore has now been re-laid with continuously welded rail on concrete sleepers (CWR), completing installation of CWR on plain track sections of the Mallow-Tralee line. Track re-laid was from MP393/4-403/4. Work took place in January after the Christmas break and train operations were similar to those described in JOURNAL 150.

The track through Millstreet platform and the main and loop tracks in Rathmore have been re-laid with CWR. This leaves the stations at Banteer, Killarney, Farranfore, and Tralee as the only jointed track on the Mallow-Tralee line.

Portarlington-Galway The tracks through plat-forms 1 and 3 in Athlone have been re-laid with CWR on concrete sleepers, as have the main and loop tracks through the former MWGR station west of the Shannon. The latter also features some steel sleepers. Other gaps in CWR between the two stations have also been closed, although the through road, platform No. 2, in Athlone (Southern) station remains good quality jointed track on timber sleepers. All the re-laying was carried out using Atlas road-rail excavators and road-rail dumper trucks for ballast, as opposed to using the re-laying and ballast trains. In May, work started on re-laying the loop at Clonnydonnin with CWR on concrete sleepers using the same method.

Main and loop tracks through Ballinasloe and Athenry stations have been re-laid with CWR on concrete sleepers in conjunction with work on the Mini-CTC project. This work also included installing crossovers and points for the new track layout, but not the point blades. These are only installed just prior to commissioning of new signalling.

Athlone-Westport/Ballina   Re-laying between Manulla Junction and Ballina re-commenced on 6 January after the Christmas break and continued throughout the winter and spring. There were complete closures for short periods, with passenger trains substituted by bus and freight trains diverted to Sligo. At other times, the 11.30 Manulla Junction-Ballina and 13.05 Ballina-Manulla Junction were substituted by bus between Claremorris and Ballina, with all other trains operating. The entire line has now been re-laid with CWR on concrete sleepers, including stations at Manulla Junction (main and branch platforms), Foxford and the arrival platform at Ballina. In May, work continued on laying, tamping and regulating ballast on the new track and ‘stressing’ the long welded rail, with trains substituted by bus as above. 

The remaining jointed track between Manulla Junction and Westport had also been re-laid with CWR by the end of April. Generally, the 08.05 Dublin-Westport and 13.15 Westport-Dublin were substituted by bus between Claremorris and Westport for the work.

Re-laying between Manulla (MP1453/4) and MP1447/8 in the Claremorris section commenced on 1 May. As is now the practice with re-laying, cuttings are opened up and embankments widened and strengthened and to take the heavier CWR, as well as to improve views at level crossings. The 07.00 Westport-Dublin and 18.00 Dublin-Westport operated during the work period, with all other passenger trains substituted by bus west of Claremorris.

Remaining gaps on the Athlone-Westport line are MP1073/4-1097/8, MP139-1403/4, MP1447/8-1453/4, platform tracks at Claremorris and the loop tracks at Castlerea, Ballyhaunis and Westport (part). Preparation work on embankments and cuttings for re-laying MP1073/4-1097/8 was well in hand in April.

In February, rationalisation work took place in Claremorris. The double track junction at the south end, a common characteristic of former MGWR stations, was removed along with several crossovers in the middle of the station. The signal cabin diagram is shown on page 407 of JOURNAL 150. Crossovers 21 and 56 were converted into turnouts by removing the loop end points. Turnout 23 was converted into a set of traps. Additionally, crossovers 26, 27, 29, 54, 55 and traps 57 were removed along with associated signals. This has had the effect of leaving the Athenry line accessible only via the back of the island platform, number 3, and the Dublin-Westport route with effectively a main and loop track through the station. The removed track at the Dublin end was replaced with plain flat-bottomed rail on concrete sleepers, as a prelude to installing CWR.

Dublin Heuston-Cork   There was single line working between Charleville and Limerick Junction on Sundays 9 and 23 March due to ballast cleaning. There were some delays to morning trains, but these were advertised in advance on IÉ’s website.

The trailing crossover at the north end of Portlaoise has been renewed. The new trailing crossover intended for the former IFI fertiliser factory sidings at Marino Point on the Cobh line was re-located to the north end of Lisduff on 14 January and is awaiting installation.

Cork-Cobh   Further re-laying with CWR has taken place on the Cork-Cobh line, during which the line was either closed completely (11 -28 April) or during the off-peak period. The up line at Tivoli, Glounthaune (Cobh Junction), Fota, the down line at Carrigaloe and both platform and run-round tracks at Cobh were excavated prior to re-laying. The last small section of jointed track, the up line at Myrtlehill MP166-1661/8, was excavated and re-laid on Sunday 11 May. The large bridges at Belvelly and on the causeway at Fota are jointed bullhead track on timber beams and Cobh station remained jointed track. The crossovers at North Esk and Glounthaune have not been renewed. Other than these, the line is now completely re-laid with CWR on concrete.

Dublin Connolly-Rosslare Strand   DART services between Greystones and Dún Laoghaire were cancelled until noon on several Sundays during the spring. This was to allow various engineering works take place, including repairs to the slab track between Dún Laoghaire   and   Sandycove.   Rosslare   trains were not affected.

Rockslide detector fences have been fitted to the cutting at Whiterock, east of Killiney. They consist of steel posts embedded into the ground that carry heavy steel ropes and wire mesh.

The remaining gap in CWR between Rathdrum and Arklow (MP481/2-49) has now been filled. CWR is in place between the top of Rathdrum bank (MP353/4), through Rathdrum and Arklow stations to MP53.

Both the main and loop tracks in Gorey have been re-laid with CWR on concrete sleepers. CWR is also in place from Gorey to MP601/8. Re-laying in the Gorey-Enniscorthy section re-commenced in May. Generally, the 07.20 Maynooth-Rosslare Europort and 14.45 Rosslare Europort-Connolly were substituted by bus south of Gorey.

Limerick-Ennis   Re-laying with CWR continues on the Limerick-Ennis line. The line was closed completely from February into May. Other work included replacement of the Canal Bridge and structural work on the Shannon rail bridge. Further track relaying work is planned for shorter periods for up to October 2003.

Howth-Howth Junction   Both tracks of the Howth-Howth Junction branch were largely jointed track with flat-bottomed rail. Work commenced on renewing this track with CWR on concrete sleepers in February. This work took place at night and at weekends, with DART services suspended completely for these periods and a limited substitute bus service in operation. Weekend closures took place on 15/16 February, 22/23 February and 1/2 March. Services were suspended on the branch after 21.00 on weekday nights between these weekend closures. Some DART trains ran to Malahide whilst others turned back from Howth Junction. On February 12, 167 towing 134 + 3 bogie wagons of concrete sleepers arrived in North Wall from Portlaoise at 13.00 with new sleepers for the Howth branch.

Permanent way trains now regularly feature 071-class locomotives hauling them and many were in use during Howth branch re-laying. On Saturday 22 February, 079 was on ballast train duties, with 081 on a spoil train. Locomotive 086 was on a ballast train on the Howth branch during a full line closure on Saturday 26 April.

The first phase left the up line completely re-laid from the crossovers at Howth to the facing crossover at Howth Junction. The second phase saw the down line re-laid between the same points. It commenced with a combination of weekend and weeknight closures on 31 March until 27 April. DART services operated to a similar pattern to the earlier closures.

Mullingar-Athlone   The Divisional Engineer, Athlone, has signed out of use the line between Mullingar and Athlone, but will ‘permit Engineers trains from time to time to travel on the line’.

Weedspray   The weedspray programme started earlier this year on Wednesday 16 April when the train sprayed the line from Portlaoise to Cork. As last year, locomotive 175 hauled the train. However, problems with on-board spray pumps resulted in the train returning from Cork to Portlaoise for repairs next day. The programme re-started on Thursday 1 May, when the line from Portlaoise to Cork was re-sprayed. The Ballybrophy branch was sprayed on 8 May, Limerick-Waterford on 12 May and Waterford-Rosslare on 13 May. The Drogheda-Navan line was sprayed on 16 May, but not the Kingscourt or Tara Mines lines. The Mullingar-Athlone section was sprayed on 23 May.

 

 

Home
Copyright © 2003 by Irish Railway Record Society Ltd.
Revised: January 07, 2004 .