
Irish Railway Record
Society

STATIONS
HEUSTON
RE-DEVELOPMENT
Installation
Progress
The crossover connecting the down siding at the west end of Inchicore
into the down Cork line, No. 700, was renewed on 30 June.
Construction
progress continued at a good pace on the installation of additional platforms at
Heuston. Following deep excavations and drain installation, prefabricated
concrete platform sections were installed for new Platforms 6, 7 and 8 in the
area to the north and west of Platform 5 during June and July. The structural
steel supports for the canopies were largely completed by late July and some
signals and signal equipment cabinets were in place. Welded rail on concrete
slab track was also installed for platforms 6, 7 and 8. A new subway was
constructed under the new running lines to provide access from the north of the
station yard to the Valeting plant.
Platform
5 and No. 7 siding, which was located between platforms 4 and 5, were
disconnected with effect from 00.01 on Monday 22 July. The points at the west
end of the platform and siding were removed immediately, as were connections to
the Valeting plant at the Dublin end. This allowed the fenced-off worksite
boundary to be extended with work being able to proceed without hindrance from
train movements. The Valeting plant remained accessible from the Inchicore end
and Platforms 1, 2, 3, 4 and 10 were available for normal use. The ‘Wash
Road’ remained available along with up and down main lines to Inchicore, but
was only accessible from the Cork end from 19 August.
Platform
10
From 22 July, it became necessary to transfer more trains to Platform 10.
The Heuston-Kildare trains departing at 09.05 (only on Fridays), 09.50, 11.00,
11.45, 16.10 on Monday-Thursday), 17.35 and 18.40 Heuston-Portlaoise, along with
corresponding arrivals were transferred.
From
26 July, the 05.05 Cork-Heuston (only on Saturday), 06.45 Limerick-Heuston (only
on Friday), 11.40 Galway-Heuston Summer Saturdays-Only and the 11.30
Cork-Heuston Fridays-Only transferred to Platform 10. Mainline departures
transferring were the 10.35 Heuston-Waterford Summer Saturdays-Only, 13.25
Heuston-Tralee Fridays year-round and Summer Saturdays-Only, 14.00
Heuston-Limerick Fridays and Saturdays-Only, 15.55 Heuston-Ballina Fridays-Only,
16.30 Heuston-Waterford Fridays-Only and the 16.30 Heuston-Carlow (only on
Saturdays) were advertised to use the platform.
A
shuttle bus was provided for passengers to the main station building, with the
last bus departing the main building 10 minutes before train departure.
Passengers were advised to allow 15 minutes extra for the transfer if walking.
All route 91 buses from the City Centre to Heuston served both the main building
and Platform 10 from 15.30 hours Monday-Saturday.
Consequent
to the commissioning of platforms 5, 6, 7, and 8, platform 10 reverted to being
used by the Heuston-Kildare service at certain periods from 2 September.
However, the 13.25 Heuston-Tralee Fridays-Only departed from it on September 13.
The shuttle bus service was provided for these trains.
Commissioning
Phase II was commissioned over the weekend of 30 August to 1 September.
Complete possession was taken from 23.00 on Friday, with weekend trains
operating to and from Newbridge, Kildare and Athy as in previous closures (see
JOURNAL 146). On Friday 30 August, all services to and from Heuston operated
normally except the 19.15 Cork-Heuston and the 17.00 Westport-Heuston, which
both terminated at Sallins with bus transfers to Heuston. The 18.08 Galway-
Heuston terminated at Kildare, where passengers transferred to the 20.43
Kildare-Heuston. The 21.45 and the 22.45 Heuston-Kildare were replaced by bus
transfers. The last passenger
train signalled into the old part of the station from Heuston signalbox before
it closed was the late running 20.43 Kildare-Heuston, 3-car 2700-class, which
arrived at 22.27.
Heuston
cabin closed at 23.00 on Friday 30 August. It was the last remaining miniature
lever frame cabin on the IÉ network since the closure of Westland Row and West
Road cabins. The Heuston SER signal cabin took over control of an additional 22
signals and 21 sets of points from 15.00 on Sunday 1 September. Possession was
handed back in time for the departure of the 16.00 Dublin-Cork,
214 + EGV + 7 Mk III, which departed at 16.21. The 16.05 to Limerick departed at
16.33 and consisted of an 8-car 2700-class railcar.
The first arrival was the 13.50 Galway-Dublin, 084 + GSV + 3
Cravens, which arrived at 1705. Subsequently,
signalling problems resulted in considerable disruption to services on the
Sunday evening.
CAWS
(the Continuous Automatic Warning System based on signal indications transmitted
to the locomotive or railcar using coded track circuits) was commissioned on the
new track at the same time as the new signalling system.
New
Facilities
Platforms 5, 6, 7, 8 and 10 became available from 1 September with
platforms 1, 2, 3 and 4 being closed for re-building. Platforms 5 to 8 are
243-metres long from top of ramp to buffer face. Platform 5 is the original
platform extended towards Inchicore, but along with platforms 6, 7 and 8, it is
accessed from the north side of the Valeting plant. Platform 5 can be accessed
from two roads, but Nos. 6, 7 and 8 have only one access track, which limits
operational flexibility.
Access
to the Valeting plant is available from platform 5 and from ‘No. 4 Road’ via
a 43-metre long 1:10 switch-diamond double-slip manufactured by Cogifer in
France. No. 4 road is the re-titled No. 7 road. It continues to have no platform
face and is now fully signalled but is not to be used for stabling trains. At
the south end of the Valeting plant a headshunt is provided along the former
down line to allow trains enter and exit from both ends. This ends in a buffer
stop under South Circular Road Bridge. The Wash Road was renamed the Holding
Road in anticipation of the removal of the existing carriage wash.
The
three tracks between Inchicore and Heuston have been re-designated with the
former down main, up main and ‘third road’ now called the relief line, down
main and up main respectively. All are signalled for bi-directional working. A
new feature for IÉ is the provision of OFF indicators at the south ends of
platforms 7 and 8. These indicate to platform staff that the starting signal is
clear and it is in order for the guard to show a green flag or lamp to the
driver. A full track and signalling diagram will be provided in a later JOURNAL.
New
platforms 6, 7 and 8 feature servicing facilities for carriages and generator
vans. A canopy is provided over the platform area and a temporary tented
concourse was installed at the buffer stop of these platforms, which is in the
area formerly occupied by the Fastrack office. The concourse also features a
temporary booking office. A new departures board has been installed along with
monitors showing arrivals. Each platform also has its own indicator board.
The
Phase II layout also restores access to the station from Islandbridge Junction
and transfer movements between Heuston and Connolly and vice versa no longer
have to go via Inchicore. Revised instructions were issued regarding locomotive
hauled passenger movements between Islandbridge Junction and the platforms at
Heuston. Two locomotives are still required, but it is no longer allowed to
leave a locomotive on the rear
Dundalk
Siding
space is at a premium in Dundalk following rationalisation in conjunction with
re-signalling as part of the Dublin-Belfast line upgrade and the provision of
badly needed additional car parking spaces. With the forthcoming delivery of
eighty 2900-class railcars from CAF, which are likely to be predominantly used
as 8-car formations, the situation will get worse. Therefore, additional sidings
are to be constructed on the down side at the north end at an estimated cost of
€3 million. A staff footbridge will also be
constructed. To allow removal of the former Dundalk North signal cabin, the
signalman’s PC and other contents were re-located to a room on the platform on
25 September.
Lansdowne
Road
Work commenced in mid-June on extending
the southern
end of the up platform
to cater for 8-carriage trains. The extension will be on the site of the former
Royal Dublin Society cattle sidings, now part of the AIB Bank Centre. There will
be access from the platform to the Bank Centre for bank staff.
View
of Heuston Station from Islandbridge just before the withdrawal of locomotive
B114 in 1971. (Photo: Barry Carse)

Loco
No. 041 on a Guinness train at Heuston in the early 1970s. (Photo: Barry Carse)
Malahide
A developer is seeking planning
permission to take over part of the station building in Malahide and construct a
bar and lounge. The same developer constructed a similar facility at Howth
station some years ago.
Portmarnock
Work has commenced on the installation of a new footbridge complete with
wheelchair accessible lifts.
Tara
Street
An Bord Pleanála (the planning appeals board) gave the IÉ/CIÉ scheme
for Tara Street station the go ahead on 13 September (see JOURNALS 145 and 147).
Other
IÉ has advertised for the supply, installation and maintenance of
between 55 and 60 ‘Pay and Display’ machines for Dublin suburban railway
station car parks. They have also advertised for car park management companies
to manage the car parks for a five-year period subject to annual review. At
present car parking is free in Dublin suburban stations.


Copyright © 2002 by Irish Railway Record Society Ltd.
Revised: January 07, 2004
.