|
<
Irish Railway Record Society
Telegraphs to Tullow The
Contractor Robert Worthington commenced construction of the Sallins-Tullow
branch of the GS&WR in 1883 and the line opened to Baltinglass in September
1885. The Great Southern & Western Railway (Tullow Extension) Act, passed on
14 July 1884 sanctioned an extension to Tullow and the contract for building
this section was also awarded to Worthington. Since it was intended to work the
new line on the Block System, on the 17 October 1885, George Ilbery, the GS&WR
Traffic Superintendent, wrote to the Post Office Secretary to arrange for the
erection of the necessary poles and wires. "This Company have in the course of
construction, a railway in continuation of their Baltinglass terminus in the
County Wicklow, to Tullow in the County of Carlow and I am directed to inform
you that my Board are desirous that a line of telegraphs for their use should be
erected along that branch upon the terms of the 46th Clause of the telegraph
agreement dated 27 day of June 1883, the Company in due course complying with
the conditions of Clause 45 of the same agreement. My
Company would require an instrument for speaking purposes at Tullow station, as
well as the block instruments for the section between Baltinglass and Tullow. The
construction of the branch line is not yet sufficiently far advanced to admit of
telegraph poles being placed in position, but I shall give due notice when it
shall have arrived at such a state as to allow of the work being gone on
with." The Clause 46 referred to by Mr Ilbery concerned the erection and maintenance of wires and instruments by the PO and the payment of the costs involved. Clause 45 obliged the Railway Company to grant to the Postmaster General the same rights and privileges on new lines as he enjoyed on existing lines. It was intended that the intermediate station at Rathvilly should be a block post, so four Preece's Block instruments were required for the sections Baltinglass-Rathvilly and Rathvilly-Tullow. The "speaking" instrument mentioned was not necessarily a telephone, as the term was frequently used for the Morse telegraph that the signalmen used for conversing. In this instance it was to be a Morse sounder. On
the 9 November, William Louth, the PO Superintending
Engineer, dispatched
Inspectors
Sheridan and
Tansley to make a "conjoint" survey of the line and on the 28th, Mr
Sheridan reported back with an estimate of cost and the intention to use one
special train to distribute the poles. The Railway Company asked the PO to be
ready to commence work in any subsequent month and on the 23 February 1886, Mr
Ilbery wrote to Mr Louth: "Mr
Bayley [GS&WR Engineer] informs me that he has intimated to you that the
telegraph poles can now be erected along the line nearly the whole way from
Baltinglass to Tullow and I shall be much obliged by your kindly having the work
proceeded with at once. It is the desire of my Directors to open the line to
Tullow if they can, on 1st May next." By
the 4 March, Mr Louth had received the block instruments and batteries and he
warned Mr Sheridan "we must not be late". The latter arranged with the
GS&WR to run a special train of an engine and ten pairs of trucks from
Kingsbridge on Sunday the 21 March to carry the poles and stores and a gang of
ten men to the new line. In a telegram, Mr Ilbery advised Mr Louth that the
special could "go entire distance on new line". However, things did
not go according to plan on the Sunday, as Mr Sheridan reported to Mr Louth: "The special went through
satisfactorily today, so far as our part was concerned and so far as we were
able to run - but a deplorable and vexatious bungle was made of it between the
Contractor and the Railway Company. The new line was not fit for the main-line
engine to run any portion of the way. The Contractor's engine took us eight
miles and could go no further. I was obliged to bring back 57 of the poles and
two wagons of small stores to Rathvilly and leave them there for the present. I
had walked through the whole line yesterday and so far as the drenching rain and
heavy mud could allow me to see, I was prepared for this failure and called for
[instructions] last night and this morning on an advice to postpone running. I
await further instructions on the disposal of the five trucks lying at Rathvilly." A
cold, wet and mud-stained Mr Sheridan can hardly be blamed for wanting to
postpone the work. However, in the absence of instructions to the contrary, the
special had to run on Sunday. The next day, Mr Louth informed Mr Ilbery of the
events of Sunday and requested him to arrange as to when the gang could be sent
back to distribute the remaining stores. Mr Ilbery apparently conducted his own
inquiries and did not reply until the 17 April: "With reference to your letter of 22nd
March, I am told there was no reason why the trucks should not have gone on to
Tullow on 21st ult and the road is no better now than it was then. If you do not
wish to have the poles sent over the temporary road, it will be some time before
they can go forward, but if you like, they can be sent over the temporary road
any Sunday you name. The Contractor does not think there would be any danger in
sending them on now, as a light engine could be used." Mr
Louth then wrote to Mr Sheridan, referring to the decision to cut short the
journey of the special train: "I
do not understand that you declined to proceed." The latter, to justify his
action, replied with a fuller explanation of what happened: "The exact particulars of what occurred
are as follows. When the special arrived at Baltinglass from Kingsbridge, I was
informed that the main line engine could go no further, but that the
Contractor's heavy engine was under steam ready to take us on as far as the 8
mile post where a lighter engine would meet us, the road at that point not
admitting the passing of the Contractor's heavy engine. When we got to the 8
mile post, the driver of the lighter engine declined to take our heavy trucks on
for two reasons - one was that no instructions had reached him - the other that
their own small trucks had tumbled over the embankment the previous evening,
owing to the weakness of the temporary road and he would not be responsible but
that the heavy trucks would do the same. I left the discussion between the two drivers, one of whom I remember
threatened the other with the consequences of refusing to bring us on. Several
of our men were listening." The
PO gang who would have to travel with the heavy trucks doubtless warmly
appreciated the driver’s prudence. On the same day as the above was written,
20 April, Mr Ilbery put some more pressure on the PO, inquiring about the
progress of the work of erecting the wires, saying that he expected the
Government Inspector to inspect the line about the middle of May and hoping to
open the line on the 1 June. Mr Louth replied to this on the same day: "I thought it had been made clear to
you in my letter of 22nd ult that the only reason why the distribution was not
completed was because the driver of the Contractor's engine refused to proceed
beyond the 8th mile post because some of their own small trucks had run off the
temporary track on the previous evening. I shall be glad to complete
distribution as soon as you can arrange for it. I am told, however, that the
stores we had to leave at Rathvilly have been unloaded from the trucks there by
your people".
Locomotive 171 shunting cattle wagons at Baltinglass for the local fair, 16 March 1959. (Photo Michael Davies) Mr
Ilbery took his time replying to this and on the 29 April, Mr Louth sent him a
telegram asking for a reply and saying that the work of erecting the wires could
not commence until the stores had been distributed. Mr Ilbery eventually replied
on the 4 May to say that he was arranging to have the stores distributed on next
Sunday the 9th and asked how many trucks would be required. Mr Louth replied by
telegram the next day: "We left poles and other stores loaded
on trucks at Rathvilly. If they are still there, we shall require no further
trucks. I heard your people had unloaded and returned them. If so, we require
three pairs of "Aspinalls" and one flat truck sent down at once for
reloading and distribution on Sunday." The
"Aspinalls" referred to were apparently a type of wagon designed by
John Aspinall, who was the GS&WR Locomotive Superintendent at that time. Mr
Ilbery replied that he would have the necessary trucks sent to Rathvilly on
Saturday and a special engine and van would leave Kingsbridge at 10am on Sunday.
On Friday he telegraphed Mr Louth to say that only the stores had been unloaded
at Rathvilly, the poles were still on their trucks. The confusion over the
wagons having been sorted out, the work went ahead on Sunday and Mr Sheridan
duly reported to Mr Louth on Monday the 10th: The remainder of this article appears in IRRS Journal number 148, published June 2002.
Copyright © 2002 by Irish
Railway Record Society Limited
|