|
NEWS LISBURN - ANTRIM On
20 February, the Minister for Regional Development said: ‘Against the backdrop
of other competing transportation priorities, I have concluded that the
continuance of rail services on the Antrim-Knockmore line, given the limited
financial resources available to my Department, is not such a priority as to
enable me to fund it within the current budgetary allocation’. The Minister
said it was important to stress that discontinuing the service did not mean the
abandonment of the line. It was suggested that the line will be mothballed in
the hope and expectation that it could be reinstated as part of a
Belfast-Antrim-Lisburn-Belfast circle line in years to come. He also said that a
review of the line's future potential will be undertaken every five years and a
full bus substitution programme will be provided to cover the services
previously provided by the rail service. He said: ‘I am fully committed to
advancing public transport in Northern Ireland and where feasible rail travel in
particular. However, the continuance of rail services on the Antrim-Knockmore
line could only be achieved at huge opportunity costs to wider transportation
needs. Getting the balance right between competing transportation priorities is
a challenge for all of us, especially since funding is finite and our current
transportation assets are in poor condition following years of under-investment.
Clearly there are difficult choices to be made’. However, the Minister
stressed that while he was prepared to propose a discontinuance of services,
under the statutory procedure any decision to discontinue rail services on the
Antrim-Knockmore line would require the approval of the Assembly. LOCOMOTIVES Hunslet
loco 102 now bears the number 8102 on the cab sides. Work on returning the loco
to service took place as resources permitted during the spring. By mid-April,
the engine was running and it was used to shunt in York Road Works. It
re-entered service on 24 April shunting Adelaide yard. Subsequent reliability
was poor and it was often substituted. ROLLING
STOCK New
Railcars The
new trains will have a top speed of 90-mph and will be able to accelerate from
0-60 mph in 99 seconds, compared to four minutes for the existing 80-class
railcars. They will seat 200 passengers with additional space for bicycles and
wheelchairs. The internal layout of the carriages is still being finalised, but
it will be two-by-two seating, with a mix of bays and aircraft style seats. They
will be air-conditioned and the floors will be carpeted. The trains will be
No-Smoking and all standard class. Automatic doors will be provided one third
and two-thirds of the way along each carriage. The
announcement of the order described the new trains as ‘a diesel version of the
Heathrow Express trains’. It also stated that two of the new trains are
earmarked for the Belfast-Ballymena line, the aim being to improve commuter
services on the new Bleach Green link. Since the line was re-opened last June
and a new station opened at Mossley West, passenger traffic has increased by
29%. The remainder of the new trains will be deployed throughout the system,
augmenting the existing 450 Castle class trains which are themselves due to be
retired in 2010. Under
the terms of the agreement with CAF, the Spanish company will provide a warranty
for the new trains that will extend over 15 years. The contract for the new
trains stipulates that they will be able to operate for at least 40,000 miles
without suffering mechanical breakdown. At present, despite the best efforts of
NIR maintenance staff, the existing aged railcar fleet is suffering a failure on
average every 3,000 miles. A driver training-simulator is also being supplied as
part of the order. IÉ has also ordered CAF railcars for outer suburban working
and expects to take the first delivery in Summer 2002. It
was also announced that one of the new trains is to be named The
Belfast Telegraph in recognition of the role the newspaper played in NIRs
‘Save Our Railways’ campaign. The nameplate was unveiled in a ceremony at
Belfast Central Station in February. Ted Hesketh, Managing Director of Translink,
said the company was grateful to the newspaper for running its Save Our Railways
campaign. He said: ‘By highlighting the issue of the lack of investment in
public transport, the Belfast Telegraph played a valuable role. The paper
initiated a debate, which raised the profile of public transport and attracted
the attention of the public and the politicians’. A focal point of the
campaign was a petition, which was signed by 12,000 readers, calling for
additional investment in the rail network. De
Dietrich Mk
IIf (ex-Gatwick Express) On
Sunday 17 February, a clearance train operated from Dundalk to Dublin Connolly
and return. The train consisted of IÉ loco 150 hauling 8947
+ 8946 + 8943 + 8944 + 8911. The loco had been on loan to NIR to free up
111-class locos to work permanent way trains for the Belfast-Bangor re-laying
project and had acted as pilot in Adelaide on weekdays. The remaining four
passenger carriages were under test in late February. Test running between York
Road and Carrickfergus was scheduled for evenings in February and March. IÉ
loco 150 was used on 18 February, with 8113 taking up the duty a few days later. Testing
continued on a daily basis with a full 9-carriage train running to Ballymena. On
24 Feb 8113 + 8911 + 8941 + 8942 + 8945 + 8948 arrived at Londonderry at 11.00
and departed for Portrush at 12.25. It arrived at Coleraine at 13.15 and
departed for Portrush at 13.35, returning immediately. It was then seen passing
through Crumlin at 16.00. Trials were suspended from Friday 15 March until
Monday 22 April, when 112 + 8911 + four standards ran to Newry and return. Railcars INFRASTRUCTURE Bangor
Line Re-laying
of the down line between Bangor and the crossovers at Craigavad proceeded at a
rapid pace in January and February using the Harsco re-laying train. The train
continued to be supplied with concrete sleepers from the temporary depot at
Crawfordsburn. The entire section had effectively been re-laid by mid-February.
Generally, ballast was deposited using NIR loco 111 plus 6 ballast-wagons. In
addition, the down line rail between the facing and trailing crossovers at
Craigavad, previously removed as a trap-point for the down line, had been
replaced. At one stage, IÉ loco 150 was employed on the concrete sleeper
delivery train. A
drainpipe was installed between the running lines at Bangor West. In Bangor
station, old track was removed from the down line, old ballast dug out and
removed between the crossovers and the platforms, and a drainpipe was installed. At
weekends commencing in February, sections of the up line were temporarily lifted
between Holywood and Belfast to allow failed ballast be removed, a
‘geo-textile membrane’ be installed and new ballast be deposited. An Atlas
machine was used to lift and replace the sleepers, approximately six at a time.
Existing concrete sleepers were re-used but with new welded rail. A
nine day closure was arranged over the Easter period from Saturday 30 March to
Monday 8 April to allow work proceed in the Craigavad-Belfast section. During
this period, all turnouts and the track on the approaches to the Bangor station
were renewed. The facing crossover was renewed and moved approximately 70 metres
towards Belfast. During
the closure, work started on the up line first and later moved to the down line.
The up line from the crossovers at Craigavad to Cultra was completely renewed
using the Harsco machine. The down line was renewed between Marino and Cultra.
The down line through Sydenham was also re-railed during this possession. The
line re-opened on schedule on Monday 8 April with single line working over the
up line and with a 20-mph speed restriction on the new track. Over
the weekend of 13/14 April the down line between Holywood and Seapark was
renewed, but re-using the existing sleepers in a similar manner to that on the
up line. IÉ loco 184 was seen on 20 April hauling a spoil train past Holywood.
Over subsequent weekends, the down line was excavated and re-laid between Cultra
and Craigavad. The line has effectively been totally reconstructed from MP119 to
Bangor. The
crossovers at Craigavad will be left in place when the re-laying project is
finished and will be controlled from the panel at Belfast Central.
Bi-directional signalling, without intermediate signals for
‘wrong-direction’ movements, will be available for movements during
permanent way work or in emergencies. The crossovers will be protected by colour
light home and distant signals. Installation of AWS magnets started in May. SIGNALLING Automatic
electric point heaters have been installed in the Belfast Great Victoria Street
- Westlink Junction area. Point heaters were first provided on NIR at the four
sets of points on the Dargan Bridge (1 at Yorkgate, 2 at Donegall Quay, and 1 at
Queens Quay Junction) in 1994, as the exposed locations were deemed impractical
for staff to remain in attendance during snowfall or freezing conditions. LEVEL
CROSSINGS NIR
sponsored a quiz competition for students of the University of Ulster at
Jordanstown aimed at raising awareness of the dangers of trespass and to
encourage proper use of the level crossing at Jordanstown Halt on the Larne
line. Since the introduction of CCTV monitoring of the crossing, there has been
a significant reduction in trespass incidents but a rise in motoring offences.
NIR plan to upgrade the existing AHB to a full barrier crossing (See JOURNAL
147). TIMETABLE From
2 February, NIR introduced a timetable valid to 1 June. It features minor
changes; the most significant being the 06.30 Londonderry-Belfast Great Victoria
Street advanced to 06.15 in order to provide better connections at Belfast. It
arrives in Belfast Central at 08.20 and Great Victoria Street at 08.28. The
corresponding down 07.05 Belfast Central-Londonderry is advanced to 07.01 and
now crosses the up train at Ballymena instead of Magherabeg. The 16.14 Belfast
Central-Londonderry is advanced to 16.07 in order to cross the 14.35
Londonderry-Belfast Central on the double track at Monkstown. The timetable also
takes into account the closure of the Bangor line at weekends to allow
re-construction. OPERATIONS On
Friday 18 January, public sector workers throughout Northern Ireland staged a
‘day of action’ following the murder of a postman earlier in the week.
Railway staff, with full support of Translink Managing Director Ted Hesketh,
took part in rallies and train services were cancelled between 12.00 and 14.00,
with services disrupted for about an hour before and after the events. The 11.00
Dublin-Belfast operated to Dundalk only and formed the 13.40 Dundalk-Dublin in
the path of the cancelled 12.30 Belfast-Dublin. The
Ireland v Wales Rugby game in Lansdowne Road, Dublin, on Sunday 3 February
produced Dublin Connolly-Belfast Central specials at 16.55, 17.28, 18.05 and
19.10 in addition to regular departures. The 17.28 special was formed by 9-car
80-class railcar, 8091 + four + 8083 + two + 67. The 18.00 Dublin-Belfast
regular was 234 + 8 De Dietrich (DT 9003). The 18.05 special was 8093 + four +
8084. It was followed by the 18.30 Dublin-Belfast regular, 206 + 7 De Dietrich
(DT 9001). The 18.35 Dublin Connolly-Dundalk special was a 4-car 2600-class
railcar and the 19.05 Dublin-Belfast special was 8090 + four + 8097. The
Ireland v Scotland Rugby game in Lansdowne Road on Saturday 2 March produced
four specials from Belfast Central to Dublin Connolly, plus a relief from
Dundalk. The 08.35 Belfast-Dublin was formed by 6-car railcar 8090 + four + 8068
and arrived five minutes early at 11. 00. The 09.30 special was 8091 + four + 67
and arrived one minute late at 12.06. The 10.00 special was 8093 + four + 8096
and arrived twelve minutes late at 12.44. It
was followed two minutes later by the 11.50 relief from Dundalk to Connolly,
four-car 2600-class railcar, which served Drogheda only. It ran ahead of rather
than behind the 10.30 Belfast-Dublin Enterprise
as per schedule. The result was very satisfactory, as the relief was well
filled (approximately 200 passengers) and the Enterprise
was not overloaded. The Enterprise,
9004 + seven De Dietrich + 221, arrived at 13.01. The final special was the
lightly filled nine-car 10.45 Belfast-Dublin, 8099 + four + 8081 + 8089 + two,
which arrived on time at 13.10. The fullest train of the morning was again the
10.34 Dundalk-Pearse (see JOURNAL 147). This was formed by 072 + 4 Cravens + GSV
and served all stations Dundalk-Howth Junction except Gormanston. It arrived in
Connolly two minutes early at 11.48 with approximately 500 passengers. Two
reliefs operated to augment the 10.00 Belfast-Dublin on St. Patrick’s Day
Sunday 17 March. The first was formed by 8099 + four + 8081 and arrived in
Connolly at 11.25. The second was 8087 + four + 67 + two + 8068, which arrived
at 12.20. The 10.00 regular, 9004 + seven De Dietrich + 229, arrived at 12.30. The
Ireland v Italy Rugby game in Lansdowne Road on Saturday 23 March saw returning
specials that evening departing Dublin Connolly for Belfast Central at 18.20,
19.05, 19.39 and 20.52. The 18.20 special was formed by 8081 + four + 8090+ two
+ 8084, the 19.05 special was 8087 + four + 8089, the 19.39 special was two +
8083 and the 20.52 special was 8093 + three + 8092.
Copyright © 2002 by Irish
Railway Record Society Limited
|